6.1. SR 09-24-2001River MEMORANDUM TO: FROM: DATE: Mayor and Council //~ Pat Klaers, Cit7 Adminis~ September 24, 2001 SUBJECT: City Hall Expansion Update Item 6. I. On June 18, 2001, the City Council hired Tushie-Montgomery Architects to complete the programming phase for a city hall and police station expansion. A staff committee, plus Councilmembers Kuester and Motto, have met with Gary Tushie on a number of occasions to discuss city needs and to review how these needs are "programmed" into an expanded and remodeled facility or a new facility. In general, the city needs identified by staff got translated into office space dimensions as if we were building from scratch. In the next phase, the design phase, the desired (or ideal) space and programs will get revised to reflect financial realities. Attached for your information is the programming material that has been completed. We need to review the status of the project with the City Council prior to taking the final steps of the programming phase. These £mal programming steps include 1 .) making a recommendation on a new, expanded, and/or remodeled facility (which includes the space requirements for various departments) and 2.) the development of a rough construction budget estimate. At this time we are planning to build for everything within the 2013 needs. However, we are making building site provisions for the next expansion. The next expansion (in about 2013) will address the 2023 needs. Accordingly, we are btfilding for ten years but planning for twenty and when we do an expansion in 2013 we would do the same thing...build for ten years and plan for twenty. Staff will need feedback from City Council on the programming process from a "big picture" point of view. We need to know if there is anything that is out of line in the direction we are moving and the assumptions that we have made. (Some of the assumptions we have made are listed at the end of the programming information under the general requirements heading. This section lists a number of statements including what is not part of the program.) When looking through the office space program you will note some new departments, positions, and programs which are assumed to be needed before the next expansion in 2013. These new positions/departments and new programs will require some Council discussion, especially such items as the city engineer department, the gun range, and the EOC. One issue that requires Council feedback is whether or not it is acceptable for the committee to be looking at a one or t~vo building option. We need to know if the City Council firmly believes that the police station must be attached to city hall or whether it's all right to develop a campus environment with police in a separate facility. If all of the cost estimates are relatively equal, I believe we will seriously be looking at the campus option, whereby the police would build a separate facility in 2003 and then we would remodel the police station and our existing facilities and expand into the police space in 2004. This is especially true if the fire department is planning to locate in our campus and then the police and fire station could be connected by way of the emergency operations center (EOC) between the two departments/facilities. (In speaking with the fire chief, he prefers a city hall location connected to the EOC versus being an independent facility at a different location on the western side of the city). Additionally, two separate facilities would make the planning for the 2013 expansion easier. Another issue, which needs City Council discussion, is the fact that the large meeting room (with catering kitchen) for banquets, wedding receptions, etc. and the connected senior center facility are not part of this project. At this time we are not sure if we could afford this space; don't know how political this large meeting room space is; the space could be developed by the private sector; the space could be constructed with another public or semi- public facility (i.e., YMCA or family center); this space could be added into the 2013 expansion; or, per direction from the Council, this space could be put back into this 2003 project. The committee and myself are just not sure of the need and do not want to get the city hall and police station delayed by political issues which are not essential to our government responsibilities and functions. This issue requires Council feedback but at this time the senior center and large meeting room space are not in the program. The Utility Commission have recently indicated its desire to pursue the city hall location for its office. It is very early in this process but it is assumed that the utilities would essentially build on to our existing facility and that they can design the space as desired and as they can afford. I believe they currently occupy about 3,400 square feet and Gary Tushie will be working with Bryan to program then needs and layout. As noted above, the committee needs some feedback from the Council on some key issues before moving forward. The next steps in the process will include putting together a recommendation and a rough estimate for a construction budget. A report is expected by the end of November depending on how quickly the utilities information can be assimilated into the project. The Council will then need to consider moving into the design phase of the project. The design phase puts the programming into a building layout for everyone to visualize. The design phase gets the city to the point of being able to put together the construction documents. This design phase becomes part of the architectural fees for a project (generally about seven and a half percent of the total cost). At the completion of the design phase, most project decisions have been made. TUSHIE MONTGOMERY 612 861 9632 7645 Lyndale Avenue South, Suite 100 Minneapolis, Minnesota 55423-4084 612. 861 . 9636 Fax: 612,861 . 9632 www , tmiarchitects . corn TRANSMITTAL To: Patrick D. Klaers City Administrator City of Elk River 13065 Orono Parkway, Box 490 Elk River, MN 55330 T U S H I E MONTGOMERY ARCHITECTS Date: 9/2I/0I Project Number: 201051A Project Name: Elk River City Hall Expansion Phone: 763-441-7420 Fax: 763-441-7425 WE ARE SENDING YOU VIA: [] Fax- Total Pages: 27 [] Picked Up [] U.S. Mail [] Hand Delivery [] Overnight Delivery TI-IZ FOLLOWING ITEMS: [] PRINTS [] Messenger [] SPECIFICATIONS [] SHOP DRAWINGS [] OTttER COPIES DATE NO.SHTS DESCRIPTION 1 26 Rivisod Expansion Program, Standaxdized Work Spaces, Typical Work Spaces [] YOUR USE [] APPROVAL REMARKS: [] AS REQUESTED [] BIDS DUe [] REVIEW AND COMMENT [] DISTRIBUTION TO OTHERS COPY TO: File FROM: Gary Tushie Kindly notify us if you have any questions or concerns regarding this transmittal. P.01/27 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 612 861 9632 P.02×27 T U S H I E MONTGOMERY ARCHITECTS REVISED SEPTEMBER 13 2001 Current 2001' 2003 2013 2023 Total Total Buildin~l Space Area Condition Need Need N=cd P-----"~ ScI, Ft. Staff Council Cha, mbers -- OounciJ Chambers 50 seats ............... 50 seats 100 sts 0 (Council & Staff Seating - 11} (1,510 s.f.) +1,000 s.f. 2,510 Cable TV Control Room and (1) (2)' ' ................... 3 A/V Equipment Room (existing) 9.5' x 19' 6' x 20' (Equil3ment Workstations) (181 s.f.} 240 s.f. 421 Staff/Council Bathroom ......................... 0 6' x 6' (36 s.f.) 36 Cable TV Production Studio ............... ' Storage Rm .......... 0 8' x 8' 20' x 30' 64 s.f. 600 s.f. 664 Storage Room .............................. 0 (Existing Coat Room 3' x 15' conver~ed to Stora.qe) 45 s.f. 45 Subtotal (1) (2) ...... ~ 3 1 r727 s.f. 240 s.f. 45 $.f. 64 s.f. 1~600 s.f. 3,676 16% Add for walls and circulation 323 s.f. ~,S s.f. 7 s.f. 10 s.f, 299 s.f. 684 Section Subtotals (1) (2) --' --- 3 2r050 $.f. 285 s.f, 52 s.f. 74 s.f. 1,899 s.f. 4,360 Police Department "~ecured Resident Waiting .............................. 0 Room , 16' x 11' 20' x 20' (176 s.f.) +224 s.t. 400 interview Room ......................... (2 tot) O - 9' x 7.5' 10' x 10' 10' x 10' (68 s,f.) ,+32 s.f. 100 s.f. 200 Receptionist/Secretary (1) ..... (1) ..... (1) (3 ws) 3 Workstation 16' x 13' 10' x 10' ws 10' x 10' ws 10' x 10' ws (208 s.f.) -108 s.f. 100 s.f. 100 s.f- 300 Transcription Room (1) (.5) (.5) (1) ..... (3 ws) 3 6'x 10' 8' x8'ws 8' x8' ws 8'x8' ws (60 s.f.) +4 s.f. 64 s3. 64 s3. 192 Computer Room .............................. 0 6'x 10' 10'x 14' (60 s.f.) 80 s.r. 140 Emergency Operations Center .............................. 0 30' x 50' 1~500 s.f. 1~500 CSO Workstations (3) ..... (1) .......... (4 ws) 4 10' x 17.5' 3-8' x 8'ws 1-8' x8' ws (175 s.f.) ~-17 s.f. 64 s.f. 256 Records Storage Room ....................... 0 9' x 15.5' 20' x 20' ,. (140 s:f.) 400 s.f. +400 s.f. 940 Copy/Mail Room .............................. 0 5.5 x29' 12' x35' (160 s.f.) , .2,6q.s-f, 420 Records Technician Work~za[;on (1) ..... (1) (1) .... (3 ws) 3 14' x 10' 8' x 8' ws 8' x 8' ws 8' x 8' ws (140 s.f.) -76 s.f. 64 s.f. 64 s-f. 192 Investigating Sergeant's Office (1) .......... (1) ..... (2 - off) 2 -- 9'x 11' 12' x 12' 12' x 12' j (99 s.f.) +45 s.f. 144 s.f.I 288 S~P-~1-~001 09:56 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 612 861 9632 P.03×27 T U $ H I MONTGOMERY ARCHITECTS REVISED SEPTEM_RER 13 2001 Current 2001 ° 2003 2013 2~)23 Total Total Building Space Area Condition Need Need N~-~ H-,_~4_ S¢I. Ft. Staff Police Depart. Continued Investigator's Office '(3) ..... (1)" (1) (1) (6 - off) 6 9' x 9.5' ea 10'x 10' ea 10'x 10' ea 10'x 10' 10'x 10' ea _ (258 s-f-) +42 s,f. 100 s.f. 100 s,f. 100 s,f, 600 Interview Room ........................ (4 total) 0 2- 9.5'x 10' 10'x 10'ea 10' x 10' 10'x 10' ea +10 s.f. 100 s,f, 100 s.f. 400 (19o s.f.) Juv, Investigator's Office (2) .... (1) .... (1) (4 - off) 4 9' x 12' 10' x 10' ea 10'x I0' 10'x 10' (227 s.f,) -27 s.t, 100 s.f. 100 s.f. 400 Assistant Chief Office (1) .................... (1 - off) 1 9' x 11' 12' x 16' _ (99 s.f.,) +93 s.f, 192 Corporal's Office ............... ' '. ............ {~ Captain's Office .......... (1) ..... (1) (2 - off) 2 - 12' x 12' 12' x 12' 144 s,f, 144 s.f. 288 Patrol Sergeant's Office (4) ..... (2) ('[) (2) (5-off) 9 (Shared Office) 9' x 10' 12' x 12' - ......... 12' x 12' ea (125 s.f.) +451 s.f. 144 s.f. 720 Shift Sergeant's Office ............................. 0 (Shared Office) 14' x 20' 280 s.f. 280 Patrol Brie[ing Room ............................. 0 10'x 15' 14' x22' 155 s.f. 153 s,f. 308 Janitorial Room ............................. 0 6' x 11.5' 10' x 15' (69 s,f.) +81 s,f. 150 Winter Gear & Equipment ............................ 0 Storage Room (could be 9' x 10,5' 20' x 25' above garage) (95 s,f,) 405 s.f. +300 s.f. 800 CSO Storage Room ....................... 2' .... - .... 0 6.5' xg' 10' x 15' (59 s,f.) +91 s,f, 150 Suppo~ 'Ser. Su~. Office (1) ................... (i - off) 1 9' x 11' 12' x 12' (99 s.f.) + 45 s.f. 144 Interview Rooms ....................... (2 total) 0 (Juvenile Ho[ding Rooms) 2 - 7.5' x 10' 2-10' x 10' ea +50 s.f. (150 s.f,) 200 Booking Room .............................. 0 15.5' x 8' 10'x 16' (124 s.f.} +36 s.f. . . .. 160 Intox Room ............................ 0 7,5' x 5' 8'x8' (38 s,f.) +26 s.f, 64 Bathroom ............... public .......... 0 7,5' x 5' 8'x8' 2-8'x 8' 2-8' x8' (38 s,f,) + 26 s,f, 128 s,f, 128 s,f, 320 Reserve Storage Room .............................. 0 7.5' x 8.5' 10' x 15' (64 s-f.) +86 s.f. 150 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 612 861 96~2 P.04×27 T U $ H I MOI~TGOM]~R¥ A RCHITI~ CT$ REVISED SEPTEMBER 13, 2001 Current 2001' 2003 2013 2023 Total Total Building Space Area Condition Need N,~,~. l'.'==d N==d Sq. Ft. Staff Police DeFt. Continued ' - Weapons Room ........................... 0 (14' of counter space) 7.5'x 8.5' 14'x 20' (64 s.f.) 216 s.f. 280 Evidence Room .............................. 0 16.5' x 15' 2,0' x 30' (233 s,f,) +367 s,f, 600 Patrol Write-up Room (14) (1) (6) (9) (10) (20 ws) 40 (Shared workstations) 7.3' x 5' 8 - 6' x 8' ea 3 - 6' x 8' ea 4 - 6' x 8' ea 5 - 6' x 8' (105 s.f,) +279 s,f. 144 s.f. 192 s,f. ea 240 s.f. 960 Conference Room .......... .............. (1 tota[) 0 19.5' x 10.5' I - 14' x 22' (205 s.f.) +103 s.f. 308 Chief's Office (1) .................... (1 - off) 1 11.5' x 17' 14' x 20' _ (196 s.f.) +84 s,f, 280 Chief's Secretary Office (1 ) .................... (1 ws) 1 11.5' x 11.5' 8' x 8' ws (137 s.f.) .68 s.f. s4 Vehicle Garage ......................... 0 (12 - 14 vehicles) 24' x 92' 25' x 160' (2~208 s.f.) 1~792 s.f. 4~000 ,-ocked Garage Storage ......................... ' 0 24' x 9' 25' x 20' (216 s,f.) 284 s.f. 500 Lab & Cleaning Area ............................ 0 -- 7' x 24' 14' x 20' (168 s,f.) 112 s.f. 2..80 Men's Locker Room ............................. 0 18,5' x 26' 20' x 40' Add (405 s,f.) 395 $.f. Lockers 800 Women's Locker Room ............................. 0 18,5' x 26' 20' x 25' Add Exercise Room (405 s,f,) 95 s.f. Lockers 500 Shared with C.H. 0 911 Call Center ................................... By Coun_ty Large Conference Room ........................ (1 total) 0 14' x40' 560 s.f. 560 SmalJ Conferer[ce Rooms ......................... (1 total) 0 12' x 12' 144 s,f. 144 A V Room (For hard and soft ............................. 0 Interview rooms) 10' x 10' 100 s.f. 100 Garage Storage Area #2 ..... Not .................... 0 5' x 18' Required _ (90 s.f.) -90 s.f.. 0 Hazardous Waste Storage .............................. 0 8' x 10' 80 s.f. 80 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 861 g632 P. 85/2? T U S H I E MONTGOMERY ARCHITECTS REVISED SEPTEMBER 2001 Curre,~ zu01' 2003 2013 2023 Total Total Building Space Area Condition N,,~a Need Need N=¢=I Sq. Ft. Staff Police Dept. Continued Supplies Storage .............................. 12' x 10' Gun Range 120 s.f. 120 20' x 104' 2,080 s,f, 2~080 City Attorney Office ..... .... (1) (1) (1) (3 - off) 12' x 16' 12' x 12' 12' x 12' lg2 s,f. 144 s.f. 144 s.f. 480 City Attorney Assistant's .......... (2) ..... (1) (3 ws) 3 Workstations 8' x 8' ea 8' x8' ws Quiet Room 128 s.f. 64 s.f. 192 7'x9' 63 s.f. 63 Employee Breakroom/Kitchen ........................ 20' x 30' , 600 s,f. 600 Subtotal (34) (1.5) (17.S) (15) (18) 86 7~503 $.[ 1~599 s.f. 11,371 s.f. 836 sof. 1p836 $.L 23~145 29% Add for Walls and Circulation 3~045 $.f. 656 s.L 4~6~2 s.f. 343 s.f. 753 $.f. 9,459 NA ~*~-,tion Subtotals (34) (.5) (15.5) (15) (18) 86 10;548 s.f. +2255 s.f. 16,033 s.f. 1,179 s.f. 2,589 s.f. 32~604 -Common Areas: Emergency Readiness Room ..... In Police .................... (EOC) 32,5' x 26.5' Station (874 s.f,) -874 s,f. 0 Wellness Room ........................... :'- 0 28' x 29.5' _ _ (826 s.f.) +400 s.f, 1~226 Upper Level Records Retainage ............................ 0 Storage 34' x 12.5' (425 s.f,) 425 Upper'La'el Mechanical Room ........................ 0 31' x39' 31'x39' (1,209 s,f.) 1 ~209 s,f. 2~418 I~lain Level Boiler Room ....................... 0 22' x 1S' 22' x 15' (330 s.L) 330 s.f. 660 Electrical Room ......................... " 0 8' x 15' 8' x 15' .... (1.20 s.f.) 120 s.f. 240 Men's Room ............................ o 7.5'x 12,5' 8' x 25' 8'x 10' (94 s,f.) 106 s,L 80 s.f. 280 s.L Women's Room .................... -£---- - ~ - .... 0 7,5'x 12.5' 8' x25' 8'x 10' (94 s.f,) 106 s,f, 80 s.f. 280 s.t, Quiet Room ......................... 0 9'x7' 9'x7' (63,,s.f.),, 63 $.t, 126 Sitting Area ............................ 0 9' x 7' 20' x 20' 20' x 20' (63 s.f.) 337 s.f. 400 s.f. 800 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 612 861 96~2 P.06/27 T B $ H I E MONTGOMERY ARCHITECTS REVISED SEPTEMBER 13 2001 PAGE 5 Current 2001' 2003 2013 2~)23 Total Total Building Space A. rea Condition Need Need Need N--=,~ Sq. Ft. Staff Common Areas Continued: ' Entrance Lobby ............................. 0 32' x 21' 20' x 30' (753 s.f,) 600 s.f. 1~ .3.53 Vending Machine Room ............................. 0 8'x 10' 8' x5' 10'x 12' (80 s.f.) 40 s.f. 120 s.f, 240 EmPloyee Break Room .............................. 0 23' x 27.5' (541 $,f.) 541 Quiet Employee Break Room ........................ (2 total) 0 -- 10'x 18' 10'x 18' 180 s,f, 180 s.f. 360 Kitchen/Vending Room ............................. 0 16.5' x 11.5' 12' x 16' (190 s.f.) 192 s,f. 382 Large Meeting Room/ .......... To be ............... 0 Conference Center/ Dealt with Convention/Public Use Room as With a catering kitchen and a Storage to accommodate separate 450 - 500 issue Senior Citizen Center with .............................. 0 Meal Program Resource Library ......................... 0 (Centrally located) 14' x 18' ~-~ s.f. 252 Election Equipmenffl-raining ................... '-'--;'-' ' ' 0 Room 32.5' x 26.5' 20' x 20' 874 s.f. 400 s.f. 1~274 Computer Room ....................... 0 (Network Resource Center) 8' x 9.5' 12' x 16' 12' x 16' (76 s.f.I +116 s.f. 192 s.f. 384 Large Copy Room ........................... 0 (Future include Mail) 21' x 18,5' 14' x 30' (389 s.f.) +31 s.f. 420 Staff Men's Room ............................. 0 8' x 11,5' 8' x 10' (90 s.f.) (80 s.f.) 170 Staff Women's Room ............................. 0 8' x 11.5' 8' x 10' (90 s.f.) (80 s:f.) 170 Large Conference Room ............................. 0 13.5' x 27.5' 14' x44' (372 s.f.) +244 s.f, 616 Small Conference Room .................... ';'"-- (4 total) 0 (Near each department) 12.5' x 20' 1 - 12' x 14' 2 - 12' x 14' I - 12' x I4' (250 s.f.) -82 s.f. ea ea 336 s,f. 168 s.f, 672 Wellness Men's Locker Room .......................... '_L_ '" 9' x 8.5' 9' x 9' 9' x 9' (76 s.f.) ...... 81 s.f. 81 s.f. 238 Wellness Women's Locker Room .............................. 0 9' x8.5' 9'x9' 9'x9' [ ... (76 s,f.) 81 s,f. 81 s.f. 238 S~P-~1-~001 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 861 96~2 P. 0?×2? T U $ H I E MONTGOMERY AR CHITE£TS REVISED SEPTEMBER 13, 2001 Current 2001' 2003 2013 2023 Total Total Building Space Area Condition Need Need N==d N=¢d ScI. Ft. Staff Common Areas Continued , Small Copy Room ............................. 0 8'x8' 64, s.I=, 64 Building Maint. Storage/Repairs .............................. 0 10' x 16' General Storage R~om ..... 160 s.f. 160 10'x20' 200 s.f, 200 Subtotal (0) (0) (0) '(0) (0) 0 7,081 s.f. -809 $.f. 2~817 s.f. 1~534 s.f. 3~566 s.f. 14~189 14% Add for Walls & Circulation 1~150 s.f. -131 s.f. 456 s.f. 249 ~.f. 578 $.f. 2,302 NA Section Subtotals (0) (0) (0) (0) (0) (0) 0 8~231 s,f. -940 s.f. 3~273 s.f, 1,783 s.f. ,4~144 s.f. 16~491 Administration: C.H. Receptionist (1) ......................... 1 13' x 13' 10' x 10' (169 s.f.) ..-69 s.f. 100 Reception Waiting Area .............................. 0 14'x 14' ., 196 s.f, 196 Counter Area Fin. & Admin./ ............................. 0 Economic Dev. 8' x 16' +128 s.f. 128 Parks & Recreation/Planning ........................ 0 Counter 8' x 16' 128 s-f. 128 Mail Room part of in large .................... 0 Recept. copy room 8' x 12' . 96 s.f. 96 US State Rep. Office ........................ (1 - off) 0' 11' x9.5' 12' x 12' (123 s.f.) +21 s.f. 144 s.f. File Room - Finance only ................... Autorile 0 (Existing Shared) 9.5' x lg' 12' x 16' (181 s.f.) 192 s.f. 373 Auto Fi[es - Admin./Econornic ........................ 0 Dev. 8' x 12' 8' x 12' +96 s.f. 96 s,f. 192 Finance Equip./Printer Room .............................. 0 12' x 12' 144 s,f, 144 Cable TV Manager Office (1) ........................ 1 13.5' x 10' 12' x 12' (135 s.f.) +9 s.f. 144 Workroom ............................. 12'x 12' 10' x20' (144 s.f.) +56 s.f. 200 Ciiy Administrator Office (1) .................. (1 - off) 1 12' x 16.5' 14' x20' (198 s.f.) +82 s.f, 280 Cost Room .............................. 0 3 - 3' x 5' es 3' x 20' 3' x 25' i(4~. s.f.) 60 s.f. . ..... 75 s.f. 180 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 612 861 9632 P.08×27 T U $ H I E MONTGOMEI~Y ARCHITECTS REVISED SEPTEMBER 13 2001 PA IE Current 2001 ' 2003 2013 2023 Total Total Buildin~l Space Area Condition Need Need Need Need ScI. Ft. Staff Adrnin;~ation Continued; Microfishe Workstation .......... (1) '-' ........ (1 ws) (1) 8' x 8' ws 64 s.f. 64 Planning Secretary ..... (1) .................... 8'x 8'ws 64 s.f. 64 Director of Planning Office (1) .................... (1 - off) 11' x 12' 12' x 16' City Engineer Offi~:e (132 s,f.) +60 s.f. 192 (1) ................... (1 - off) 1 9' x 12' 12' x 16' (108 s,f,) +84 s.f. 192 Assistant Finance Director Office (1) .................... (1 - off) 1 11,5'x 12' 12'x 12' (138 s.f,} , +6 s.f. 144 Finance Director Office (1) .......... I .......... (1 - off) 1 15.5' x 12' 12' x 16' (186 s.f.) +6 s.f. 192 Mayor/Council Office ....................... (1 - off) 0 11,5'x 12' 12' x 16' (,138 s.f.) +54 s.f. 192 City Clerk (1) .................... (1 - off) 1 12' x 12' (144 s.f.) 144 Economic Dev. Manager Office (1) ................... (1 - off) 1 12' x 12' (144 s.f.) 144 Building & Zoning Dir. Office (1) .................... (1 - off) 1 12'x 12' 12'x 16' (144 s.f.) +48 s.f. 192 Building Official Office (1) ............... "' - .... (1 - off) 1 9.5' x 12' 12' x 12' (!14 s.!.) +30 s.f. 144 EConomic Dev. Assistant Office (1) ............ '-- ' .... (1 ws) 1 9.5'x 11.5' 10'x 10'ws (109 s,f.) -9 s,f. 100 Commercial Building Inspector (1) ................... (1 ws) 1 Office 9,5' x 11.5' 10' x 10'ws (109 s.f.) -9 s.f. 100 Admin. Sec. Workstations (2) .......... (1) (1) (4 ws) 4 7.25' x 10' ea 8' x 8' ea 8' x 8' ws 8' x 8' ws (145 s.f.} -17 s.f. 64 s.f. 64 s.f. 256 Human Resource Mgr, Office .......... (1) ...... '---'- (1 -offi 1 12' x 12' off 144 s.f. 144 Human Resource Assistant ................... (1) (1 ws) 1 8'x8' ws 64 s,f. 64 Accounting ~lerk Workstations (3) .............. (2) (5 ws) 5 (Payroll & Payables) 7.25' x 10' ea 10' x 10' ea 10' x 10' ea (145 s.f-) +155 s.f. 200 s,f,: 500 ~ssociate Planners Workstations (3) ..... (1) ..... (1 ) (5 ws) ..... 7,25' x 10' ea 10' x 10' ea 10' x 10' 10' x 10' ws (218 s,f,) +82 sif, 100 s,f, 100 s,f, 500 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY. 2001 REVISED AUGUST 21, 2001 612 861 9632 P.89/27 T U $ H I E MONTGOMERY ARCHITECTS REVISED SEPTEMBER .... . .-....---.-..% --vv, PAGE 8 Current 2001' 2003 2013 2023 Total Total ~ce Are._____ Condition Need Need Need Need S ,o,:.,~., Staff Administration Continued: ~ '"- ~ I.T. Coordinator Workstation (1) .....-- ..... (2) (1) (4 ws) 4 7.25' x 10' 8' x 8' 2-8' x 8' ws 1-8' x 8'ws (73 s.f.) -9 s.f. 128 s.f. 64 s.f. 256 Autofiles - Planning & .......... . .... Engineering 12' x 16' - ......... '0 Accountant Office 192 s,t. 192 ............... (1) (i) (2- off) 2 10'x 10' 10'x 10' 100 s.f. 100 s.f, 200 Planning/Zoning/Building/ ..... Engineering Reception Area 14' x 14' ' ......... 0 Parks & Recreation Workstations ..... 196 s.f. 196 .......... (4) ..... (4 ws) 4 8' x 8' ws 256 s,f. 256 Engineering Technician ..... (4) ..... (4) (8 ws) 8 Workstations 8' x 8' ws 8' x 8' ws City Forester Workstations -~ 256 s.f. 256 s.f. 512 Hotel Workst'at[ons ........ (1) ..... (1 ws) 0 6' x 8' 48 $.f. 48 seni~)r Citizen Coordinator (1) .................. (1 ws) 1 Workstation 7,25' x 10' 8' x 8' .... (73 s.f.) -9 s,f, 64 Building Inspectors Workstations (4) .... (1) (1) .... (6 ws) 6 8.5' x 10' ea 10' x 10' ea 10' x 10' ea 10' x 10' ea (340 s,f.} +60 s.f. 100 s.f. 100 s.[. 600 Building/Zoning Sec. (2) .......... 5.5' x 8' ea 8' x 8' ea 8,(1) Workstations (3 w$) 3 x 8' (88 s.f.) +40 s,f, 64 s.f. 192 Building/Zoning Counter ........................... 0 5' x 14' 8' x 16' Environmental Specialist (79 s.f.} +S8 s.f. 128 .......... (1) (l) ..... (2 ws) ~, - lO'x 10' ws lO'x lO'ws 100 s.f. 100 s,f. 200 Community & Economic .............. (1) ..... (1 - off) 1 Development Director 14' x 20' off. 280 s.f. 280 Building Maint, Coordinator (2) .................... (2 ws) 2 Workstations 6' x 11.5' 6' x 8' ea (,6,9 s.f.) +59 s.f. 128 Engineering Secretary .... .... (~) .......... (~ ws) 8' X 8' ws 64 s,f, 64 Engineering Plotter Room .......................... 0 12' x 14' G IS Coordinator Workstation , , 168 s,f, 168 .......... (1) ..... (1) (2 ws) 10' x 10' ws 10' x 10' Parks & Recreaiio~ Di~'ector 100 s.f. 100 200 .......... (1) ......... (1 - off) Office 12' x 16' 192 s.f. 192 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 612 861 96~2 P. 10×27 T U S H I E MON'FGOMERY ARCHITECTS REVISED SEPTEMBER ......... ,-n ,g, =uu ~ ,PAGE 9 Current 2001' 2003 2013 2023 Total Total Building Space Area Condition Need H-_ca_ ,,,.,~_a Need Ft. Staff Adminis[,,a[;on Continued: ---" PI;~nning & Zoning Counter ......... 8'x 16' 128 s.f. 128 Building Inspections & Environ. - ....... 8 spaces ..... 4 spaces ..... 0 Spec. Vehicle Garage 11' x 24' ea 11' x 24' ea 2I112 s.f. 1T0S6. s.f. 3,168 Auto Fil~"_ Building/Zoning .................... 16' x 12' 192 s.f. 192 · ~dmin. & Economic Dev ................ Storage 10' x 20' 200 s.f. 200 Economic Development Storage ................... '(1 ws) 0 Workstation Space 10' x 12' ws 120 Building Inspections Storage ..... 120 Space (within Department) 10' x 20' ' ......... 0 Engineering Storage Space ..... 200 s.f. 200 10' x20' 2..00 s.f. 200 Parks & Recreation Storage ..... LoCated in Lion's Park Space ............... Building Maintenance Storage ........................... 0 Space 10' x 10' Vault _ 100 s.f, ,100 10' x 16' 160 s.f. 160 Subtotal (31 ) (1 ) (12) (12) (12) .... 68 3,682 s.f. lt234 s.f. 5t354 $,f, 1~140 $,f. 2,367 s.f. 13,777 46% Add for Walls & CirculatiOn 3,116 s.f. 1,04~, s.f. 4,529 s.f. 964 s.f. 2,002 s.f. 11~655 Section Subtotals (31 ) (1 ) (12) (12) (12) --- 68 .... 6;798 s.f. 2;278 s.f. 9,883 s.f. 2,104 s.f. 4~369 s.f. 25,432 Utility Department: " Director ......... (1) .......... (1 - off) 1 14' x 20' 280 $.f. 280 Fi'r~anc~e Director .......... (1) .......... (1 - off) 1 12' x 16' 192 s.f. 192 Clerk .......... (:~) ..... 10'x 10' 200 s.f. Water Superintendent .......... (1) ......... (1 - off) 1 10' x 10' off. 100 s.f. 100 Secr~;arial .......... (6) .... 8'x8' ws 384 s.f. RecePtionist Workstation .......... (1) .... and Counter 8' x 22' 176 s.f. ~P-21-2001 TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUr1' 21, 2001 REVISED SEPTEMBER 13. 2001 612 861 9632 P. 11/27 T U S H I E MONTGOMERY ARCHITECTS PAGE 10 Current 2001' 2003 2013 2023 Total Total ..Buildin9 Space Area Condition Need Need Need Need ScI. Ft. Staff _Utility Department Continued: Existing Department Space ................................... 3r500 S.[. Reception Area .................... 14' x22' 308 s.f. Small Conference Room ................... 99 s.f. Larg~ Conference Room ................... 14' x28' 392 s.f. Production Room ................... 270 s.f. Storage/Receiving .................... 19' x22' Subtotal % Add 'for Walls & Circulation · ~ion Subtotals Total Existing Building Area (58) 27?627 s.f. ,, , , Total Existing Building CirCulating (58) 7,205 s.f. .. Average % Add for Walls & 26% Circulation for Entire Buildin~l GENERAL PROGRAM REQUIREMENTS: 1. Police outside storage needs: Fenced/secured outside vehicular storage (impound lot) for 30 vehicles. Expandable to 40 by 2013. 2. Police Station does not need to be attached to City Hall. 3. Add larger and separated customer counter space for: Building & Zoning Planning Engineering Administration / Economic Development/Finance Parks & Recreation 4, Senior Citizen Center located next to large meeting room. 5. Resource Library should be located in central location next to files - to be used for research/quiet work area. 6. Parking lot needs to be expanded. 7. Shipping/Receiving room to accommodate loading docks for full semi-trucks and UPS vans. TUSHIE MONTGOMERY 612 861 9632 ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 REVISED SEPTEMBER 13, 2001 Natural light and ventilation important to comfort of work environment. P. 12/27 T U S H I E MONTGOMERY ARCHITECTS PAGE 11 This program assumes that the current expansion plans includes programmed needs through 2013 and that the site plan has allowed for future expansion through 2023. 10. City Attorney position to be used as prosecutor for court cases. 11. Not included in expansion plans are: Property Assessing (done by County) Police Dispatching - 911 (done by County) Council Chambers - AV Room to be expanded only 12. Large Community/Conference Room can be used for training and/or be used for the EOC room. Other options for this room include: DO not include in Program Partner with: Private Sector YMCA School District 13, Senior Center will require four (4) employees and include small craft rooms, offices, commercial kitchen, storage rooms, billiards room, large activities room (could be large Community Room) and a separate entrance. 14. There is a possibility that School Board meetings may be held at City Hall. 15. See Exhibit 'A' for Emergency Operation Center room requirements from the Police Department. 16, Program Legend: Office I i Investigator's Workspace (2) ~ 9.5'xl0'ea ~ ; (~9o s.f.) ~ j Square Footage of Workspace/spaces Size of Workspace "Ea" indicates there are multiple works ~ces of the same size Number of employees in workspace/spaces . 17. Replace wall between Council Chambers and Lobby with a glass wall and add monitors in Lobby for public viewing of meetings. 18. Locate cable TV Manager's Office close to Cable TV Production Studio. 19. Election equipment storage to be in new training room in a locked storage room. (20 x 15) 20. Locate Mail Room close to Admin. Receptionist workstation. 21. Have TV monitors and cable TV connected to training room from Council Chambers. 22. Consider option of connecting Police Station to City Hall. TUSHIE MONTGOMERY ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA 23. EXPANSION PROGRAM JULY, 2001 REVISED AUGUST 21, 2001 REVISED SEPTEMBER 13, 2001 If departmental needs exceed budgeted costs consider the following: · Some space built as shell space. · Elimination of space to meet budget. · Extend some needs into 2013 building phase. · Interim use for future spaces i.e. small conference now- office in future. 861 9632 P. 13/27 T I3 $ H I E MONTGOMERY ARCHITECT5 PAGE 12 24. For storage needs consider: · Using shell space temporarily for storage. · Provide storage off-site. 25. Consider waiting until 2013 building phase to build exercise room in Police Station. They can share with city Hall until 2013, 26, 27. 28. 29. 30. Should gun range be designed to be rented out to other Police departments similar to Maple Grove's faciJity. Consider option of a separate utilities building connected to City Hall next to existing building and zoning space. Location must aJlow for future City Hall expansion. Make public vending area more visible & accessible. Future offices could be used as temporary conference rooms until 2013 expansion. Locate Quiet Room in a more public location. 31. Make entrance Lobby sitting area a more friendly environment. 32. GIS to be part of Engineering Department, 33, Locate Cable TV Production Studio next to AV/Cable Equipment Room. 34. Locate Evidence Room off Police garage and with 12' ceiling clearance. 35. Locate Hazardous Waste Storage off Police garage. 36. Relocate employee vending machines to Breakroom and increase counter space and number of refrigerators, 37. Provide easy truck access for receiving supplies in General Storage Room. Loading dock is not required, but provide a platform lift, 38. Locate workroom to be shared by City Administrator and Mayor/City Council. SEP-21-2001 09:59 TUSHIE MONTGOMERY 612 861 9632 P.14×27 ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA STANDARDIZED WORKSPACES August, 2001 Revised August 21, 2001 T U $ t-I I E MONTGOMERy ARCHITECTS PAGE 1 14' x 20' Private Office Police Chief City Administrator CED Director Utility Director 12' x 16' Private Office Building & Zoning Director City Engineer Assistant Police Chief Director of Planning Finance Director City Attorney Parks & Recreation Director Mayor/Council 12' x 12' Private Office Assistant Finance Director City Clerk Police Sergeants (shared - 2 per office) Assistant City Engineer Transportation Engineer Building Official MIS Manager Economic Development Manager US State Representative Hotel Office Captains Office Human Resource Manager Cable TV Manager Police Duty Office (shift shared) 10' x 10' Private Office Investigators Support Ser. Sup. Water Superintendent Accountant SEP-21-2001 09:59 TUSHIE MONTGOMERY 612 861 96~2 P.15×27 ELK RIVER CITY HALL SPACE NEEDS ASSESSMENT ELK RIVER MINNESOTA STANDARDIZED WORKSPACES August, 2001 Revised August 21, 2001 T U S H I E MONTGOMERY ARCHITECTS PAGE 2 10' X 10' Workstation Public Information Coordinator Administrative Assistants Associate Planners Accounting Clerk (Payroll, Payables & Utilities) Building Inspectors Plan Reviewers Specialists Economic Development Assistant Receptionist/Secretary City Forester GIS Coordinator (2) Finance - open workstation 8' x 8' Workstations Senior Citizen 'Coordinator IS Coordinator Community Service Officer Administrative Secretary Environmental Assistant Zoning/Code Enforcement Department Secretaries Paralegals Engineering Technicians Seasonal Positions 6' x 8' Workstations Police Officers Police Reserves Building Maintenance Coordinator Interns Small Conference 12' x 14' Rooms Accommodate 6 - 8 Group Conference 14'x 22' Rooms Accommodate up to 20 Large Conference Room 14'X 40' Accommodate up to 30 SEP-21-2001 09:59 TUSHIE MONTGOMERY 612 861 9632 P.16×27 ~ ~00~ TU$1u.~-.~u~'r'~.i:~:'~' ',' A~'~o¢l~'l'~'. I'x'c ' ' W1 I ELK RIVER CITY HALL TYPICAL PRIVATE OFFICE DATE: 8/1/01 SCALE 114"= 1'-0" SEP-21-2001 09:59 TUSHIE MONTGOMERY 612 861 9632 ,/ A DU 5TAB L,F__. TOOL i0': PAPER TRA.T' Dr AGONP.,' COAT ~4OOK TASK S~D'E Ct~.A~ RS IW2 ELK RIVER DATE: 811101 CITY HALL TYPICAL PRIVATE OFFICE SCALE 1/4"= iLO" T U $ H I E MONTGOlVfERY ARCHITECTS SEP-~1-~001 10:00 TUSHIE MONTGOMERY 612 861 g632 P.18×27 ° "~.-~S LIST: 2 24" X 2 ~0;' X ~i" MOBILE P~ISTaL FILE (~/B/F O~ F/F) TOOL 2 D~AGON~L 'FR~T CO~ ~OO~ W3 ELK RIVER CITY HALL TYPICAL DATE: 811101 SCALE 1/4"= 1'-0" T U S H I B MONTGOMERY ARCHITECTS SEP-21-2001 10:00 TUSHIE MONTGOMERY 612 861 9632 P. 19×27 (,o~?-~oN =2 ) F,O~_..z ST±,,'q,'PX-,~D :0' X iO' ~O~K6T-TiON Z, 24" X B~" ~O~KSU~FICE ; 42" ~ ~l~: ] ~0" / ~i" PANEL 2 ~" X ~i" 4 ~ X i5" FABRIC ?~CK ~O" X i6:' FAB~!C TACK ~051LE PEDISTAL_ FILE (B/~/F O~ F/F) TOOL 2 ~AGON~L W3 ELK RIVER CITY HALL TYPICAL DATE: 8/1/01 SCALE 1/4"= 1'-0" T U S H I E MONTGOMERY ARCHITECTS SEP-21-2001 10:00 TUSHIE MONTGOMERY 612 861 9632 P.20×27 ~,~., ~0~. 1'I; D*I.II~-,~lO,'4TOONf*fc~' ~, ~;~oc~ ~Tr]:~ ~ NC J ...... 48" 24" X 48" CO~.NE:~ ~OP-,,K. SU'C. FAC=_ 48" TAS<, LIC~NT5 MOBILE ~E,.'},'ISTAD FILE (5/B/=' 0-~ F/F') COAT ~OOK W4 ELK RIVER CITY HALL TYPICAL DATE: 811101 SCALE 114"= 1'-0" T U $ H I E MONTGOMERY ARCHITECTS TUSHIE MONTGOMERY 612 861 96~2 P.21/27 FOR W5 ELK RIVER CITY HALL DATE: 8/1/01 TVDIPA/tMADVOTATI~UO IIFIV/'~LVVUIAi~OlflIIUI~iO , u s , MONTGOMERY I ARCHITECTS SCALE 1/4"= 1'-0" SEP-21-2001 10:00 TUSHIE MONTGOMERY 612 861 9632 P.22/27 ~AP-.T$ LIST: W6 ELK RIVER CITY HALL TYPICAL DATE: 8/1/01 SCALE 1/4"= 1'-0" T U S H I E MONTGOMERY ARCHITECTS SEP-21-2001 10:01 TUSHIE MONTGOMERY 612 861 9632 P.23/27 TY~!C.z'''_ ~'C'~ _L P-.,ECEPTIONI$-F 5 2'4:' X 4&" ~QP, KSL,'~FAC. E ~4" X &O" S-';:': / 24" ~O~KDU~.,FACE 19" ~X ~,0" "f'~A. NGACTION COUNTE,~. ;5': X 48" CORNE~ T~,ANAC-r'iON COUN]-E~ iD" / 48' T~.X..NSAC. T;ON COUNT-_-~ r~O" X ~" ~.~ic TACK ~ENCTL 1 ;0" PAPER TRAY 2 DI-',GON~,L T~.~,¥ 2 -'AS~. C.'-4. Al~, W7 ELK RIVER CITY HALLTYPICAL DATE: 8/1/01 SCALE 1/4" = 1'-0" T U S H I E MONTGOMERY ARCHITECTS SEP-21-2001 10:01 TUSHIE MONTGOMERY 612 861 9632 P.24×27 W8 ELK RIVER CITY HALL TYPICAL CONF. ROOM DATE: 8/1/01 SCALE 1/4"= 1'-0" T U S H I E MONTGOMERY ARCHITECTS TUSHIE MONTGOMERY 612 861 9632 P.25×27 II II STX;.~Dx-~D $i'1 ' LL :RQC;'<,' i2' :X,, ]2' &-6 CONFE,~ENCE CHAI ~.$ DATE: 811101 ELK RIVER CITY HALL TYPICAL CONF. ROOM SCALE 1/4" = 1'-0" T U S H I E MONTGOMERY ARCHITECTS TUSHIE MONTGOMERY II 612 861 96~2 P.26×27 II ~ A~MS li~ L~ITWGASTER. S ~ND WlO ELK RIVER CiTY HALL TYPICAL SEATING DATE: 811101 NO SCALE T U S H I E MONTGOMERY ARCHITECTS 441-294~ · Ext. 4945 TUSHI E MONTGOMERY ti '1~/1 VCR 612 861 9632 P.27/27 I TVI 441-2946 VCR Ext. $al. Army (radio & telephone) 241.552'/ext. 4521 Volunteer C~ord. 441-2545 ~ 4948 Damage Assessment 241-~23 ext. 4523 MESSAGE CENTER Citizen Une/City Hal 441-7420 Ex't. 4001 Message Control City Administrator Call Takers EMERGENCY OPERATION CENTER ROOM LAYOUT 05-01 441-7425 Copy Machine Closet O EXHIBIT "A" TOTAL P. 2? ~TR~F MEO4ANICAL -~ RECORD5 . OPEN TO OELO~ NORTH JNNEL /I LEVEL ~'LOOIP. PLAN T U S H I E MONTGOMERY ARCHITECTS Revisions ~ Addendums l FLOG 'f~ PLAN5 Features [] 28,150 total sq. ft. 8,275 s.f. - Administration 8,275 s.fi -- Police Department 2,500 s.f. Police Garage 9,100 s.fi open space (Council Chamber, training room, wellness area, hallways, etc.) [] Larger lobby area.to better serve the public. [] A 40-seat training/conference room. This room is available for public use and is equipped to serve as an emergency operations center. [] Wellness/fitness room and locker room facilities available to all c!ty employees. [] A Folice Department interview room equipped with the latest in audio/video recording technology. Sherburne County Social Services assisted in the funding of this room. Garage space capable of housing all primary squad cars and the Emergency Response Unit van. [] A fuming chamber used for process- ing latent fingerprints on a variety of material types. [] A booking room with future intOxilyzer area for testing drivers suspected of being under the influence of alcohol. [] The facility includes a Council Chamber that will seat approxi- mately 75 people. The Chamber is cable-ready with state-of-the-art video equipment which was paid for by the Sherburne/Wright County Cable Commission. [] The facility is fully accessible to disabled persons. [] The City has started its first paved trail system on the City Hall property following the Lake Orono shoreline ' and connecting up to Orono Park. The system will eventually link to other areas. ELK RIVER CITY HALL COMPLEX EXPANSION ELK RIVER, MINNESOTA PROJECT SCHEDULE T U $ H [ E MONTGOMERY May 22, 2001 A R C H I T E C T S 200t 2001 2002 zuu.~ 2004 ACTIVITY June Jul~ Aug Sept Oct Nov Dec Jan-Apr May-Jne Jly-Sept Oct-Nov Dec Jan-Apr May-Jne July-Sep Oct-Dec Jan Feb PHASE I ~ves TMI Contract ~ ..... ~ ~ ConstnJction Budgeting Financing Options __ Pre re Final Re rt PHASE, Preliminary Design PHASE III ~Phase I r ...... ! ~repare Construction ~:~ment~ Updat~ Constm~on Budget [] Financing Gp;.~o,~s/Secure Submittal for Building Permit · Value Engineering E~idding i Award Construction Contracts ,ewo ~t~on ............ gompl~t~ Punchlist Items Owner Move - In Cit7 Staff Review/Approvals · I I · I I I I I I I Cit~ Council Review/Approvals Design TeamMeetings I I · · · I · · · · I · · · I I · · · Planning Commission Review/Approval I · ·