7.3. SR 06-09-2003Item # 7.3. TO: FROM: DATE: SUBJECT: MEMORANDUM Mayor and City Council Pat Klaers, City AdministrO ~ June 9, 2003 · Public Safety/City Hall/Utilities Project Update The last Council update on the building construction project was on May 12, 2003. Over the last four weeks a lot has happened as the Public Safety Facility and Utilities building near completion. One of the most visible activities and one of the work areas of most concern as it relates to access and safety is the reconstruction of the parking lot. At this time, there is a bituminous surface in and around the current Police Station and this has been signed for public parking. Since May 12, the files from the upstairs of City Hall have all been relocated to the basement of the Utilities building. Furniture is currently being installed in the Utilities building. City staff will be moving its offices into the Utilities building on Friday, June 13, 2003, and we will be open for business with a new telephone number on Monday, June 16, 2003. The front sidewalk at the City Hall entrance has been removed. The City Hall public entrance is signed for the Attorney/Cable Tv door. A public entrance to City Hall needs to remain open until after the Police move. The public safety furniture was approved on May 19. The Police are scheduled to move beginning on June 24, 2003. Once the Police have relocated, then all accesses to the former City Hall/Police Station will be closed. Entrance to City Hall for the next 8-9 months will be the Utilities front door. Remodeling of the City Hall/Police Station is scheduled to begin on July 1, 2003. The last City Council meeting in the Council Chambers is scheduled for Monday, June 16, 2003. All future meetings of the City Council, HRA, EDA, Planning Commission, and Park and Recreation Commission will be held in Lions Park Center. The Public Safety project summary has not changed substantially since the May 12, 2003 update. The project summary as of May 6, 2003 showed a project contingency balance of just under $160,000 being available. There has been some adjustments and change orders since May 12, but the total available project contingency is still in the $150,000 range. In January 2003, the City Council discussed completing part of the gun range using project contingency funds. At that time, it was the consensus of the Council to not pursue any of the gun range expenditures but to bring the issue back to the Council near the end of the project. We are now near the end of the project and we should discuss the gun range again. The gun range estimate is about $210,000. In January, the request was to do the range "guts" or "structure" for about $108,000 and to hold off on the mechanical equipment (approximately $102,000). At this time, the request for the Council to consider is just the opposite; we would like the City Council to consider installing the mechanical equipment and to hold off on the balance of the gun range. By spending about $100,000 now, we can be prepared for when funding becomes available for the balance of the project and the space then does not need any additional expenditures in order to make it usable for non-gun range activities. If neither the mechanical equipment is installed nor some improvements made in order to make the area meet code for access and usability, then the other option is to simply lock the door of the gun range. For all the same reasons that have been discussed in the past, it is important for the gun range to get completed in the not-to-distant future. By spending half of the funds for the gun range now we are then in a better position to complete the project in the future. ('Plus, this space is then useful for alternative activities until the gun range is completed.) In the meantime, the city can look for partners in the gun range project and may even fred some donations. A last alternative would be to take some money from the liquor store enterprise fund for the completion of this project. As you all know, the liquor store is doing frae financially and could afford this contribution if necessary. Recoramendation Assuming that the bid for the mechanical system are still acceptable by the contractor, it is recommended that the City Council authorize spending approximately $100,000 from the project contingency for the completion of the mechanical system associated with the gun range; if the bids are not still acceptable, it is recommended that the city go out for gun range mechanical bids. S:\COUNCIL\Pat\Updates\PublicSafety.doc New City Hall Phone Numbers Location New Phone Number Effective Date. City Hall-General Number 635-1000 June 16 Building (Permits & Inspections) 635-1060 June 16 City Prosecutor 635-1080 June 27 Fire Department (Non-Emergency) 635-1100 June 27 Ice Arena Lions Park Center (LPC) Park Maintenance 635-1140 635-1150 635-1120 Planning 635-1030 June 16 Police Department (Non-Emergency) After Hours 635-1260 635-1200 June 27 June 27 Recreation Street Department Waste Water Treatment Plant 635-1150 635-1120 635-1170 S:\ADMIN\PhoneNumStarNews.doc