4.1. ERMUSR 09-15-2010
Elk River
Municipal Utilities
13069 Orono Parkway • P.O. Box 430
Elk River, MN 55330-0430
UTILITIES COMMISSION MEETING
~.i.
Phone: 763.441.2020
Fax: 763.441.8099
TO: FROM:
Elk River Municipal Utilities Commission Troy Adams, P.E. -Director of Operations
John Dietz, Chair
Jerry Gumphrey, Vice Chair
Dar 1 Thom son, Trustee
MEETING DATE: AGENDA ITEM NUMBER:
Se tember 15, 2010 4.1
SUBJECT:
Power Su ly O tions /Resource Plannin U date
BACKGROUND:
In September 2008, Connexus Energy terminated the 10-year rolling "all requirements" power contract
with Elk River Municipal Utilities. In April 2010, the Utilities Commission authorized entering into
"Phase 1" of a resource planning study with a coalition which includes Central Minnesota Municipal
Power Agency (CMMPA) as a participant.
DISCUSSION:
Since the presentation of sensitivity assessment and portfolio options that CMMPA gave to the coalition
participants on August 4`~' in Elk River, CMMPA staff has been working on some specifically requested
sensitivity analysis and finalizing the Phase 1 analysis into an executive summary. Attached for your
review is the hard copy of the power point presentation of the executive summary for Phase 1 that will be
presented at the commission meeting.
Phase 2 of the Resource Planning Coalition analysis is scheduled to begin September 16th and finish in
mid April, 2011. This second phase covers the Request for Proposal (RFP) and the evaluations of the
RFP submittals. For Elk River Municipal Utilities, the Phase 2 cost allocation would be $19,444.44. The
results of Phase 2 may show a need for additional portfolio risk analysis prior to signing of any power
contracts. This additional work would be defined as Phase 26. The need for Phase 26 would be
determined by collective decision by the coalition committee. The projected allocation of Phase 2b costs
for Elk River Municipal Utilities is $8,334.
ACTION REQUESTED:
Staff recommends approval to execute the Resource Planning Coalition Participation Agreement
Attachment 2 -Phase 2 and proceeding into the RFP stage of the resource planning.
DRAFT Attachment 2
To the Resource Planning Coalition Participation Agreement dated May 1, 2010
Phase 2
Proposed Scope, Time Schedule, Estimated Costs and
Proposed Allocation of Costs Between the Participants
Phase 2 - Reauest For Proposal (RFPI Phase
Work Scope:
Phase 2 will consist of the following four major work activities:
Task 3: Prepare RFP Documents
A. Description of Coalition Participants
i. Type of utility, service and customer characteristics, projected load
growth
ii. Existing power supply (generating resources, purchase power contracts
and future need)
iii. Location of each Participant (geography, balancing authority, ISO, load
zone/nodes)
B. Description of Coalition future power supply need
i. Quality of Base load/Intermediate/Peaking need (capacity and energy)
ii. Desired form of service (generation unit, Utilities Plus, partial
requirements service)
iii. Desired term of service
iv. Transmission and Balancing Authority service requirements
v. Point(s) of delivery
vi. Preferred contraM terms/arrangements
C. Description of RFP minimum filing requirements and standard forms
i. Minimum bidder qualifications
ii. Request for Qualifications (RFQ)
iii. Credit requirements and/or financial security requirements
iv. Identify desired contract terms and conditions
v. Standardized quantity and pricing submittal forms
D. Formal evaluation manual
Deliverables: RFP document and forms, logging system, evaluation manual (if
required), credit risk assessment (if required).
Page 1 of 10
Attachment 2 to the Resource Planning Coalition Participation Agreement dated May 1, 2010
Task 4: Issue RFP
A. Notice and solicitation of bidder interest
8. Pre-bid meeting or conference call
C. Response to bidder questions
D. Monitor and document communications and bidder submittals
Deliverables: Issue RFP, monitor submittals and respond to bidder questions
Task 5: Evaluate Pricing of Existing Participant Power Supply Arrangements
A. Projected quality and term of existing supply sources
B. Projected incremental capital costs
C. Projected variable production costs
D. Adjustment for embedded Balancing Authority/transmission services in
existing arrangement
E. Compute and benchmark average demand and energy pricing for existing
arrangements
Deliverables: Projected Full Requirements/Partial Requirements pricing for existing
suppliers
Task 6: Evaluate RFP Submittals (Screening and Detailed RFP Evaluation)
A. Log submittals and bidder correspondence
B. Review submittals for minimum filing requirements
C. Screen and rank for qualitative considerations
D. Bus-bar economic screening analysis
E. Identify short-listed proposals
F. Select finalists for portfolio analysis
G. Basic sensitivity analysis on short-list. It is intended to be complemented
with a more rigorous Portfolio Risk Analvsis -Phase 2 B
H. Evaluation of individual Participant portfolios
I. Solicit final pricing and terms from short-listed bidders
J. Comparison of Participant portfolio to current power supply arrangements
Deliverables: Results of short screening, results of final proposals, results of
Participant portfolio analysis and results of cost comparison to current power supply
arrangements. Please see proposed Portfolio Risk Analysis details below.
Time Schedule for Completion of Phase 2:
Page 2 of 10
Attachment 2 to the Resource Planning Coalition Participation Agreement dated May 1, 2010
Assuming a September 15, 2010 start date, the completion date of Phase 2 is estimated to be
April 15, 2011.
Estimated Costs:
Total cost, including both RW Beck's and CMMPA's labor, is estimated to be $250,000 with an
approved Portfolio Risk Analysis (PRA), and $175,000 if a PRA does not prove necessary.
Cost Allocation Method:
Participants in Phase 2 agree to allocate costs as follows (pending the outcome of the initial
screening):
Allocation Participant Cost for Approval Cost for Budgeting Costs to ee Approved Later
1/9 th Elk River $19,444 $27,778 $8,334
1/9 th Dahlberg
Companies
$19,444
$27,778
$8,334
1/9 th Willmar $19,444 $27,778 $8,334
2/9 the UMMPA $38,889 $55,556 $16,667
2/9 the CMMPA $38,889 $55,556 $16,667
2/9 the Nashwauk $38,889 $55,556 $16,667
TOTAL $175,000 $250,000 $75,000
Note: Even though the Dahlberg Companies consists of three separate and distinct companies,
they are treated as one group for the purpose of this Coalition.
Phase 2 B -Portfolio Risk Analysis
At this time, the coalition participants are only authorizing the Phase 2 effort. However, it is
envisioned and expected that participants will consider a Portfolio Risk Analysis (PRA) to be a
necessary part of the evaluation, and will budget accordingly. While a basic sensitivity analysis
will in any case be part of Phase 2's portfolio evaluation, a PRA will provide a more rigorous,
comprehensive, and clear answer regarding how to balance minimizing cost and minimizing risk
in our RFP Recommendation portfolio.
Page 3 of 10
Attachment 2 to the Resource Planning Coalition Participation Agreement dated May 1, 2010
A PRA would use probabilistic methods which allow for more detailed and complete analysis
than simple sensitivities. It would use portfolio diversification strategies which balance the risk
exposure to carbon, gas, and market price risk. A PRA would precisely determine what the cost
premium should be to reduce exposure to high and extreme portfolio prices, as well as provide
"tiebreakers' between portfolios that would appear closely comparable without a risk analysis.
A PRA would provide market intelligence useful for evaluating all resources (including wind),
updates to Phase I forecasts, and possibly could consider non-fuel and non-emissions risks such
as capital cost risk. Non-physical means of risk reduction (such as changes to the structure of
gas supply contracts) would also be analyzed, so that we might verify whether an apparently
risky proposal had another means of reducing risk or cost.
A possible PRA is being treated differently from the other stages because it may not prove to be
necessary. That is, a qualitative screening of RFP responses may find a relatively limited
number of viable candidate portfolio proposals. This outcome is not expected, so if a PRA is
budgeted but not approved at the start of Phase 2 and it later is determined that it is not
necessary, no funds will have changed hands and budgets may be reduced accordingly.
Approval can be delayed until after a qualitative screening confirms that a PRA is necessary.
This qualitative screening is expected to be complete on December 15, 2010.
The referenced Phase 2 B -Portfolio Risk Analysis is therefore not approved as part of this
agreement. It is intended that there will be a colleMive decision to approve Phase 2 B. An
Attachment 2 B will be developed to define its scope, deliverables, and funding, and will be
approved separately. Approval of the PRA and any change in the cost allocation will require
consensus approval. The estimated additional cost for such an analysis is tentatively expected
to be $75,000, and the group envisions that a cost allocation similar to Phase 1 and Phase 2
would be used in Phase 2 B.
(Signatures to follow.]
Page 4 of 10
Attachment 2 to the Resource Planning Coalition Participation Agreement dated May 1, 2010
Resource Planning Coalition Participant signature approving the Phase 2 terms identified in
Attachment 2.
Elk River Municipal Utilities (ERMU)
By:
Name
Title:
Troy Adams, P.E.
Director of Operations
Date:
Page 5 of l0
Executive Summary of Phase I Results for Elk River
Phase I was designed to plan for long-term uncertainty in the electric power sector,
specifically variations in the price of natural gas and the state of carbon regulation.
Portfolios were designed both to minimize wholesale cost and to minimize the risk
associated with uncertain economic and policy variables. After each participant's overall
needs were determined, each was given a unique outline as to how each portfolio should
minimize cost, and then a basic idea of how to diversify to reduce their risks.
Your main study findines were as follows:
Build long-term plans around these ideas:
(i) There will be carbon regulation in the long-run. It will most affect coal resources.
(2) Carbon emissions will have a highly uncertain price attached to them.
(3) Coal and diesel fuel costs should increase at roughly the rate of inflation.
(4) Natural gas prices should increase slightly faster than inflation, but will also be very
uncertain.
(5) A future with wholesale costs over $100 in today's dollars is very possible with high gas
and/or carbon prices. Reducing that risk is a priority.
This means that your best portfolio should look something like this:
(1) Base load: Keep your existing landfill gas resource for your use after 2022.
(2) Bose load: Get about35 MW hydro.
(3) Intermediate load: Get 30-40 MW of combined cycle capacity.
(4) Peaking load: Get new CT (20 MW).
(5) Peaking load: Keep existing diesels (10.6 MW), and consider adding new diesel capacity (20
MW).
These can be arranged in various contract structures.
Portfolio choice is very sensitive to assumptions for base and intermediate load. A $1
difference in gas prices or a $5 difference in carbon prices will completely change which type of base
load resource is best for you and how much you should buy of it.
Consider as an example our expected future: Gas costs $7/million btu, there is carbon regulation, and
carbon costs $30/ton. What's our best choice of base load and intermediate load resources if the
future's different?
(1) If we're correct: See the above "best" portfolio. Hydro is a great option if you expect gas to
cost $7 or more and carbon to cost $30 or more.
(2) If gas is $1 cheaper: Choose 65 MW of combined cycle instead. Why? If you expect gas
prices to be roughly $S or less, gas' fuel cost is low enough that your best option is to obtain
all base load and intermediate needs from combined cycle resources.
(3) If carbon is $10 cheaper: Choose 35 MW of coal and 35 MW of combined cycle capacity.
Why? Coal is a good base load resource choice if you expect gas prices to be $7 or more and
carbon prices to be low ($20 or less).
This is why risk assessments are a necessary part of any rigorous analysis.
Portfolios should consider mixing combined cycle, coal, and hydro purchases to offset the risks
to base load of high carbon and gas prices. Hydro generation should be considered in particular for its
ability to lessen the pain of combined high fuel and carbon prices. The same is true of nuclear.
Economy energy is a good resource option for
(1) Avoiding the fixed costs for some combined-cycle capacity,
(2) Reducing expensive off-peak base load purchases;
(3) Reducing the operation of expensive intermediate and peaking gas-fired resources.
There will always be capacity and energy needs for local diesel generators, even if the EPA's
NESHAP requirements require retrofits. Each commission should begin planning for the cost of these.
satisfy your renewable standards by buying and selling all your wind energy needs (and
obtaining reliable replacement energy) through the market. You should therefore not use wind for
dependable energy and capacity needs like you would your usual sources (such as fossil fuels or hydro).
This would also mean that the problem of how to meet renewable standards is separate from how to
build our best portfolios of resources, and that issues associated with renewable energy can be handled
either as a group or individually.
Participant input is required to
(1) Determine the degree of comfort with long-term risk;
(2) Approve Phase 2 for an RFP and the choice of specific resource portfolio options.