3.3. SR 06-23-2003TO: FROM: DATE: SUBJECT: Item ~ 3.3. MEMORANDUM Mayor and City Council Lori Johnson, Finance Director June 23, 2003 Consider Public Safety Facility and City Hall/Utilities Change Orders The following change orders have been requested on the public safety and city hall building projects. Contractor Bid Package Change Order Change Order Number Number Amount PUBLIC SAFETY BUILDING Sentra-Sota Sheet Metal, Inc. Sentra-Sota Sheet Metal, Inc. (PR # 9 ) Sentra-Sota ,Sheet Metal, Inc. (Delete fire dampers) Dryden Excavating, Inc. (Removal of storm sewer pipe) Custom Drywall (Add foam) Daka Metal Fabricators (Apparatus Bay) Regal Contractors (PR #13) Total Previously Approved Total Change Orders to Date 43 4 $ 83.00 43 5 2,495.00 43 6 (184.00) 5 2 2,500.00 16 1 2,464.00 13 2 480.00 13 3 890.00 8,728.00 45,110.00 53,838.00 CITY HALL/PUBLIC UTILITIES Albers Mechanical (ERMU interior/exterior changes ) RHC Construction (Vapor Barrier) Regal Contractors (Ceiling changes) George F. Cook Construction (hardware & counter top changes) Kremer & Davis, Inc. (Waterproofing) Spectra Contract Flooring (Eliminate carpet in stairs) Bartley Sales Company (Signage changes) Total Previously Approved Total Change Orders to Date 34 1 3 1 9 1 10 4 11 1 21 1 24 1 5,238.00 894.50 630.00 1,136.00 500.00 (490.00) 5,327.00 13,325.50 12,972.92 26,298.42 Action Requested The City Council is asked to approve the change orders as noted above.