Loading...
7.4. SR 01-06-1997~ty of ITEM ?. 4. MEMORANDUM iver Mayor and City Council FROM: Pat Klaers, City Administrator DATE: January 6, 1997 ~/~ SUBJECT: Ice Arena Update The Ice Arena project is on schedule and on budget but both situations are very tentative at this time. The Ice Arena project is scheduled for completion and to be open for skating sometime during the week of January 13, 1997. The final cost figures for the project will not be finalized for a month or so after the project is completed, but we are far enough along in order to provide the Council with a preliminary update on the financial status of the project. Besides the schedule and the financial aspects of the project, there are a number of other items related to the project that I would like to discuss and review with the Council on Monday. These items include the official hiring of City employees to manage the Ice Arena operation (one full time, one full time seasonal, and 6-8 part time seasonal employees); the high level of quality services that the City has received from its consultants (RSP Architecture, Mortenson Construction Management, and I.C.E.); the efforts of Youth Hockey in Phase I and to implement Phase II of the project (the completion of the locker rooms); the status of the contingency fund within the project budget; and what is not in the project One final update item for the Council is the threat of a work stoppage by the Carpenter Union's business agent. This is because of the carpenter work that is being claimed for the bleachers as this work is not scheduled to be completed by Union employees. The threat of a work stoppage looked very real as of 12/27/96 for the dasher board work - we got through that problem, but now the work stoppage is a real concern as it relates to the bleachers. s:Xcouncil\iarenaup.doc 13065 Orono Parkway ° P.O. Box 490 ° Elk River, MN 55330 ° (612) 441-7420 · Fax: (612) 441-7425 1-82-1997 S:~OPH FROH BARNETT ~2S 6968 MORTENSON The Conxtructi,n Orgtmi,,.ation Date: Jmmary 2., 1997 FAX TRANSMISSION BUILDING DIVISION Minneapolis Office 700 Meadow Lane North P.O. Box 710 (55440-0710) Minneapolis, Minnesota 55422-4899 Telephone: (612) 522-2100 Faosimile; (612) 520-3430 To: Bill Schiferli, Horwitz, Inc. Kelly Johnson, Reliance Electric Gene K.rieger, Arena Systems Stacey Overgaard, Rink Systems Courtney Kuch, RSP Architects Jim Schuweiler, Shaw-Lundquist Richard Gallatin, Shaw-Lundquist Cliff Skogstad, City of Elk River Pat Klaers, City Administrator Lori Johnson, Asst. City Administrator Steve Snyder, Seating & Athletic Facility Enterprises Brad Lemberg, I.C.E. Dale Martin, Elk River Hockey Association Chuck Freiberg, RSP Architects From: Pat Barnett, M. A. Mortenson Company Re: Elk River Ice Arena Meeting Minutes Wc are faxing herewith one copy of this week's meeting minutes for the above referenced project. This is lbr your information. We are sending 'four pages, including this cover sheet. If you do not receive all. of these pages, please contact "l'eri Barnett at 425-6961. P'rB/tb Encl. MinneapolisoSeattleoOenver-ColoradoSprings'Milwaukeo°Grand RaplclsoSanOiego-$an Fran¢i$oo-Honolulu-Los Angeles ELK RIVER ICE ARENA ELK RIVER, MINNESOTA Slatus Codes 0 = On Hold P = Pending Re_~od: December $1, '1996 I = In Progress ~'W~ek: ~2 8-,~ R = Resolved Person(s) Date Comments Item # Initiation Issue Status Resp, onsible/Coordinator Needed Date . 1 617196 Schedule. Will discuss Rink Systems' i5- ' Weekly Project should fir~iSh by 1112197. H¢cd to be schedule in more detail as each week making ice by 119197. RSP to punch out? )rogresses. ' Piping repairs complete Ioday. Start evacualion 112197 if pressure test holds and is appr.oved by I.C.E. or the City. 2 1213;i/96 Local carpenters' union claimed the R Rink Systems 117197 Union will not banne~' if Rink Systems dasherboard work and may banner the )rovides certified payroll by 117197. project .... 3 12118/96 Bleacher installaiion begins on Thursday, P Seating & Athlelic Facility 112197 Need to provide certified payroll for local January 2, 1997. Enterprises carpenters' union or have a union crew on site. 4 6'/13196 lce time for new arena is being solc~ for P All 1/9197 Need everyone to push fo~. this date! ' January 13, 1997 at 3:00 p.m. Looking good as of IRis meeting. Need to starl making ice no later than January 9, 1997. 5 7/10196 An i~dependent review and analysis of I I.C.E. 1/6t97 Replacement of the safety ~lves (at $1,600) Rink Systems' refurbishing of the existing was recommended. Owner questions who skid has been requested by the Owner should pay lot this. Rink Systems proceeding and completed by Gary Bye with Gartner. with verbal OK. ICE to provide written response this week regarding Rink Systems' responsibility for this cost. Page 1 6 12/18t96 Roof ventilalion and fans will be wired off P Reliance ....1113/97 Schedule with Rich Czech to minimize the new ice. hockey disruption. One roof unit has been wired. 7 10t30t96 D.M.J. presented a request for a change P Shaw 12131/96 Shaw provided revised pii~ing from DMJ order to pave the south area. tota~in~l less than $10,0~0.00. 8 10t2196 prOpoSal Request No. 4 from RSP to alt P RSP 12124t96 RSP issued draWing f'(~r reloCation of contractors. Structural working with dehumidifier and moving off the ice area this Vulcrafl Io finalize added angles, week. Hocwitz & Shaw Io relocate by 1/7/97. 9 1112719'6 New gate at existing rink. Review P Shaw 113197 -The gate will be instal'led by Rink Syslems logistics o( this work along with concrete, next week and the concrete work will .follow. stairs by the new steel stairs at existing The existing wood separation can be kept in bleachers. Gate scheduled to'be as a separation for the new concrete to keep ~nslalled !12/97. the rink operational. 10 1213~)96 Operator for coiling door al zamboni R ' Shaw, City of Elk River 12/31/96 City approved $850.00 to install operators on too m. site. 11 11113/96 New stairs fr'~)r~ mezzanine. ' .... P RSP ASAP Review storage r°~m lay(~u! aflei stairs are inslalled. May need to infili w:,th drywall. Review patching precast cut outs & bleacher supporls. RSP provided a drawing. 12 11/13196 Future locker room layout. Drawing P RSP ASAP RSP will review the mechanical design for the given to Rich Czech by RSP on 11/17/96. locker rooms and submil to the hockey The Hockey Association has contracted association Io assist them in deciding on the directly with RSP to provide mechanical most economical system for the locker room and electrical de..sicjn, in the I_on~l range. 13 ' 12/t 8/9-6 ,Verily il [here is a Freon leak detector P Rink Systems, Cily of Elk 1/6/97 Cliff Skogstad requested, the specification ,included with the skid package' or control River, RSP information on the R22 coolant in order to package? verify code requirer~enls for evacuation of the chemicals'. 14 12/18t96 Radiant heating at east bleachers. P Ho~Vitz 1117197 Approved to proceed. Refurbishing ,underway, installation will be off the ice. Page 2 15 1214196 Them Witl be an Open Skating/Open R Ali 2/2197 All contractors are invited. House on Sunday, February 2, 1996 from 12:30 P.m., to 3:45 16 12131/96 The ne~t me'ling will be at 2:(~0 p.m. on" i All ;1/8/9-~ A cost rev~'ew meeting wilt be held at the city Wednesday, January 8, 1997. offices following this scheduled meeting. A[lendees: Pat Klaers, City of Elk River $1acey Overgaard, Rink Systems Rich Czech, Elk River Arena-. Jim Schuweiler, Shaw-Lundquist Richard Ga#at[n, Shaw-Lundquisi Cliff Skogstad, City Of Elk River Pat Barnelt, M. A. Mortenson Company Bill Schilerli, Hor,witz Kelly Johnson, Reliance Electric Gene Krieger, Arena Systems Copies sent Io: Courtney Kuch, RSP Architects Lori Johnson, City of Elk River Chuck Frieberg, RSP Architects Steve Snyder, S.A.F.E. Brad Lemberg, I.C.E Dale Martin, Hockey Association Page 3