5.2. SR 01-11-2011Item # 5.2. MEMORANDUM xiver TO: Mayor and City Council FROM: Justin Femrite, P.E., City Engineer DATE: January 10, 201 I SUBJECT: Engineering Project Update Below is a summary of the current projects the engineering department is working on. 1) GIS Mapping Over the next two weeks the newly created GIS mapping application will be rolled out to city staff. The information contained on the application has come from all existing mapping information that the Ciry had available. The application will function similar to the Sherburne County mapping application but is tailored to the Ciry of Elk River. The application will allow staff to view all of the City produced maps from their computer. The application offers a lot of functions that will be used on a daily basis by staff including property searches, printing mass mailing labels, creating customized figures with the city logo, and much more. Schedule The next steps in improving the mapping application will happen at the department levels over the next few years. Our goal is to have the departments review their systems and start to develop more detailed sets of data on all of their components. This will allow us to implement an asset management component within the application. This asset management component will allow each department to manage their systems through the application by creating work orders and keeping maintenance records directly in the application. 2) Eastern Area Trail and Mobility Improvements This project involves the construction of the missing pieces of trail along the east side of Twin Lakes Road from the Northstar Commuter Rail Station to Trott Brook Parkway. It also provides ADA compliant sidewalks and pedestrian ramps along Line Avenue from Main Street to 3rd Street. The Transportation Enhancement Application for this project is due by January 14, 2011. Our application includes requesting 80% of the eligible project N:\Public Bodies\City Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx costs from the Federal program. Our application, which was completed in- house, will be reviewed by the District 7W Transportation Advisory Committee later this winter. Schedule If this project is selected for funding, we will begin the process to solicit proposals for the completion of the Federal Project Memorandum, plans, and specifications. This project would then be ready for construction in 2012 or 2013. 3) Pavement Management We have completed the Pavement Condition Index (PCI) evaluations on about'/a (500) of the street segments within the City. We collect and record about 30 separate pieces of information on each street segment through these evaluations. The snow has stopped our pavement evaluations for the remainder of the season. Schedule We will continue to evaluate pavements when the conditions in the spring allow. When the evaluations are complete we will begin to prioritize the maintenance, repairs and reconstruction of streets based on their PCI ranking and need in relation to all other segments within the city. Our goal is to have the segments prioritized in time for the 2012 CIP update. 4) 2011 Street and Utility Improvements This project includes the reconstruction of the streets generally located south of Main Street, east of the railroad, and west of Carson Street. The proposed improvements in this area would be a general widening of the roads to a minimum of 26-feet. Freeport and Evans, for the first block south of Main Street, would need to be wider to accommodate the on-street parking that often overflows from the commercial buildings located on Main Street. A storm sewer piping system would be extended into the area from the intersection of Main Street and Evans Avenue to pick up runoff that in the past has caused isolated flooding problems. There are no anticipated sanitary sewer improvements necessary and only minor hydrant replacement and relocations anticipated on the water system. This project was originally planned for construction in 2009 with special assessments estimated at that time to be $6,500 per single-family house. Current assessment estimates will be determined as this project moves forward. Also included in the project is the overlaying and reconstruction of Industrial Boulevard, 192"d Court, and Triangle Road. This project was originally proposed to be completed in 2010, but was not constructed due to the high cost of the assessments. We will be reevaluating the project costs along these segments. We are proposing to fund a portion of the project with State Aid funds in an effort to reduce the amount to be assessed against the benefitting properties. N:\Public Bodies\City Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx Schedule If directed by the Council to proceed, we will solicit engineering proposals for this project by March 2011. Construction could then begin by August 2011. 5) State Aid Updates Every year we are required to review and update our State Aid system in accordance with State rules. These updates assure the City of Elk River receives the proper amount of allocated funding from the State. The updates required are completed in two separate steps. At the beginning of the year every State Aid community must certify the amount of miles they have in their system and then by April every State Aid community is required to have their `needs' updated. It is a combination of our certified miles, system needs, and population that ultimately makes up the amount of State Aid funds Elk River receives. Our estimated state aid allocation for 2011 is $1,016,107. Schedule I have already completed and submitted the Certification of Miles for this year. Over the next three months I will be completing the evaluation of our system needs and or any system revisions that need to be completed. 6) TH 10 & TH 169 Preliminary Design and Environmental Assessments The Environmental Assessment (EA) documents have been through the public comment period. MNDOT and their consultant are working on addressing the comments and completing the final document. Schedule MNDOT expects the EA's will receive official final approval by June 2011. Upon approval of the documents, we will begin working with MNDOT to solicit funding for the projects. It is anticipated the ultimate funding for these projects will come from special legislation, appropriations, or a combination thereof. To generate support for this type of funding we need to continue lobbying efforts at both the State and Federal levels. 7) County Road 77 Turnback Discussion We have had discussions with Sherburne County Public Works Director John Mentor and County Engineer Rhonda Lewis about the possibility of them turning back County Road 77 to the Ciry. The segment that has been discussed includes County Road 77/Proctor Road, from County Road 1 to County Road 33. The County will be completing a $500,000 resurfacing improvement project to this segment in 2011. We originally asked the County to consider widening of the roadway to accommodate biking or pedestrian movements along the segment with their project. The improvements the County is proposing will not accommodate our request without changing the scope considerably. The additional width would alter their project to include grading into the ditches and back slopes where they have limited to no additional right-of--way. N:\Public Bodies\Ciry Council\Coundl RCA\Agenda Packet\1-10-2011\Engineer Update.docx As we discussed the limited options, the County suggested the possibility of the City taking a turnback of the roadway, thus giving us more flexibility in traffic control, speed limit, and ability to stripe the roadway to our standards and provide for a wider shoulder area for bicycles. Taking the turnback could benefit the City a number of ways. First, it allows us to increase our State Aid mileage thus increasing our State Aid allocation. Secondly, it will allow the City the opportunity to review the traffic control, lane striping, and speed limits along the segment in accordance with our standards to best serve the needs of the residents. It also gives the City control of the right-of--way along this corridor allowing us to plan for and provide utility and street network to the north if the gravel mining area were to be developed. Schedule If the Council has desire for us to pursue this idea further we will work with the County to draft an agreement and bring it back in the future for consideration. 8) Business Center Drive Trail/Sidewalk This project will complete the missing pieces of trail/sidewalk along Business Center Drive between Joplin Street and the Orono Park. When the YMCA was built, a sidewalk was constructed along the north side of Business Center Drive along the YMCA parking lot. This project will connect this segment of walk with the existing trail and sidewalk network at Joplin Street on the west and Orono Park on the east. Schedule In the spring we will solicit quotes to survey the length of the project to determine all existing conditions and limits of right-of--ways or easements. With that information we will design the project in-house and work with the City crews to have the project constructed. 9) Pond Maintenance We are currently working with the Sherburne County Board of Soil and Water (SCBSW) to determine which ponds within the older part of the City should be cleaned to have the most beneficial impacts on water quality entering the Mississippi River. We have budgeted to begin a pond maintenance program in 2011. We are taking advantage of a study the SCBSW is completing to evaluate and recommend the most beneficial areas to begin our program. Schedule We anticipate bringing this to the Council fox consideration in March or April of 2011, when the project is more defined. N:\Public Bodies\Ciry Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx 10) WWTF Pumps and Controls Over the past months the crew at the WWTF have been experiencing some operations issues with the final clarifiers and sand filter at the plant. The problem consists of a layer of sludge that has built up in the final clarifiers. This sludge then affects the effluent water by sending additional solids to the final sand filters before leaving the plant. The additional loading entering the sand filters has caused some plugging and ultimately required replacement of some sand media. The crew has exhausted methods to remove the sludge blanket from the final clarifiers. This condition is taking large amounts of staff time and requiring the replacement of the sand media in the filters. In addition if the problem is left uncorrected, the effluent water leaving the plant may exceed limits set by the MPCA for total suspended solids (TSS) by this summer. This will result in a violation letter and corrective action order from the MPCA. In working with Bill Chang, the plant design engineer from BDM, we have developed a solution to correct the problem. The solution includes adding two pumps, modifying some plumbing, and controls on the sludge discharge lines leaving the final clarifiers. This will allow the operations staff to remove the sludge blanket from the clarifiers and lower the ultimate loading on the sand filters. We have estimated the costs for completing this work will be around $80,000 and come from the Sanitary Sewer Fund. To keep costs down the City crew will be completing the required demolition and disassembly work. Gary Leirmoe has solicited two quotes for the remaining installation of pumps, plumbing, and completion of the controls work. I will bring the quotes forward for consideration at the January 10, 2011 City Council meeting. Schedule Upon approval, we will direct the selected contractor to begin the work. There is a long lead time to order the pumps and controls and thus we need to have the contractor order them now to allow for the installation by the end of Apri12011. 11) Intersection Enhancements We have been in discussion with MNDOT who will be completing a pavement rehabilitation project along TH 169 in 2012. In our discussions with MNDOT we expressed the desire to incorporate a designated right hand turn lane at the intersection. of Jackson Avenue and TH 169 for east bound to south bound traffic. MNDOT was going to complete a survey of this area to identify the existing conditions and right-of--way limits. We are also considering the extension of the right turn lane at the intersection of Main Street and TH 169 for east bound to south bound traffic. Similar to the improvements we completed along Main Street in the opposite corner of the intersection during 2010, we would extend the turn lane to the west to provide additional stacking. N:\Public Bodies\Ciry Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx We have discussed the idea of adding a right turn lane at the intersection of Proctor Road (CR 1) and TH 10 with Sherburne County. Due to a number of constraints including right-of--way, driveways, and the intersection of 6`" Street, the addition of a new separated turn lane in this location is not feasible. We are continuing to discuss options to help with the turning movements in this intersection. Schedule We will continue to work with MNDOT in securing a survey of the TH 169 and Jackson Avenue intersection. We will have a survey completed in the spring along Main Street at the intersection of TH 169 to begin evaluating the improvements and right-of--way needed to complete the project. 12) Raw Watermain Improvements (ERMU) We have been working with David Berg, the Water Superintendent with the ERMU, on developing plans for this project. ERMU has hired a surveyor to complete a topographic survey of the project area. We will use this survey to design the improvements in-house. Schedule Upon completion of the topographic survey we will begin the design of the improvements. Construction is expected to begin during the summer of 2011. 13) River Line Sanitary Sewer Abandonment This project involves the abandonment of the river line sewer between Nile Place and the Orono Dam. This sanitary sewer line was installed along the bluff line of the Elk River to serve the area back in the 1940's. The sewer line is impossible to maintain and has deteriorated to the point of no longer being reliable. We are in desperate need to abandon the old river line due to its present condition. If the line fails we could back sewage up into the basements of the connected homes and potentially directly into the Elk River. We have an emergency pumping plan developed to deal with a failure of the line but then would have to force disconnection from the line immediately without warning or planning for the connected residents. There are 24 residential properties along the Elk River, Main Street, and Nile Place that are still connected to this line. In 1988, a new sanitary sewer line was installed as part of the Main Street reconstruction project to take the place of the old river line. New sanitary sewer services were stubbed into all the properties along Main Street at that time. In 1988, the properties that were served off of the river line were not forced to hook up to the new line. They were allowed to stay connected to the old river line until it became unusable. At that time the properties would be required to hook up to the new line in Main Street. The sanitary sewer line installed in 1988 is a trunk main that serves a larger area than the adjacent properties along Main Street. As such, the entire sanitary sewer cost in 1988 was spread over all properties within the trunk sewer service area. The properties along Main Street received a sanitary sewer assessment based on their area just the same as all N:\Public Bodies\City Council\Council RCA\Agenda Packet\1-1Q2011\Engineer Update.docx other properties to the west that ultimately drain to the trunk sewer line. No additional costs were levied against the Main Street properties for the benefit of stubbing new services to the property line. Those costs were included in the total trunk assessment and spread out as a trunk cost against all properties in the service area. The project to accomplish the abandonment of the river line is expected to be completed in three phases. Phase 1 will involve the 16 properties with direct access to sewer service on Main Street. We will work with these properties to establish a timeline for them to complete service improvements on their property to get connected to the services that have been stubbed to their property off of Main Street. These improvements will be completed on private property at the direct expense of the property owners. We are not recommending a public contract to complete the improvements proposed in Phase 1 due to all of the improvements being completed on private property. Phase 2 will involve obtaining easements and constructing sewer upgrades to serve four residential properties very near the river behind the Elk River Municipal Utilities building. These improvements would be constructed within easements via a City contract and assessed against the properties. Phase 3 will involve the abandonment of the majority of the river line and slip lining one section that is to remain on the east end between Nile Place and Norfolk Avenue. The costs for this slip lining will be assessed against the four properties that will remain connected to this line. Schedule We will be beginning communication with the affected property owners during the next few months. We axe looking for direction on establishing a realistic time line to require property owners affected in Phase 1 to be disconnected from the river line. We will work on Phase 2 concurrently with Phase 1. Phase 3 will be completed only after Phase 1 and 2 have been fully completed. 14) WWTF Beneficial Reuse of Effluent Water We have completed an application fora 50% match to study the beneficial reuse of our treated effluent water. Our effluent would be used by Great River Energy in some of their plant processes. The intention of the grant is to provide funding to study, design, and construct improvements that will reduce the amount of potable water used for industrial purposes. We have conducted a meeting with Great River Energy to brainstorm some ideas that might benefit them and us. Schedule If we axe selected for the funding match we would complete a Facility Plan update to study the water effluent stream leaving the WWTF. This Facility Plan update would be complete by June of 2011 and at that time we will evaluate the findings and make a recommendation as to whether the project should be continued into final design. N:\Public Bodies\Ciry Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx 15) 1716` Area Environmental Review and Preliminary Engineering With direction received at the December 13 work session, I will be working with the planning department to solicit proposals for the completion of an AUAR over the entire project and a preliminary engineering report for Phase 1 of the development. Schedule The schedule will be defined when proposals have been received and evaluated. We are expecting to receive proposals by the end of February, 2011. 16) Transportation Plan Update An update to the transportation plan was included in the 2011 CIP. The last update completed was in 2004. A lot of things have changed since the 2004 update. Some of the changes include the planning along the TH 10 and TH 169 corridors and the updates to the Sherburne County and Anoka County transportation plans. It is appropriate we revise our plan to assure it fits with some of the plans that the other agencies have completed that affect the traffic patterns within Elk River. Schedule I would propose completing our transportation plan update after the transportation work has been completed as part of the AUAR process for the 1715` Area. The modeling and analysis completed in that plan will have a large effect on our final transportation plan. This would allow for the transportation plan update to be started late in 2011. 17) Policy Updates The previous Public Works Director was directed to develop a traffic calming policy to address the ever increasing amount of inquiries the City receives in regards to traffic concerns. It was also on the list to review and update the Special Assessment policy. These updates were never completed. Schedule We will be working on the creation of a traffic calming policy and revision of the assessment policy in the coming months. We plan to bring them to a future work session for your review. 18) Development Close Outs There remain a number of private developments that have not been closed out or completed in accordance with their development agreements. Some remaining items include final bituminous wear, turf restoration, and miscellaneous punchlist items. Schedule Cuter the winter months I will be working with the planning department to review all outstanding developments and identify all required improvements that remain to be completed. Upon our full review we will be N:\PubGc Bodies\Ciry Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx communicating with the respective developers to have the improvements completed. Our goal is by the end of 2011 we have no outstanding improvements remaining to be completed. 19) Traffic Signal System Inventorv We are currently working with Sherburne County to complete a comprehensive traffic signal system inventory and inspection for all 18 systems within the City. Upon our request, the County agreed to allow their signal technician to assist us with this task at no cost to the City. Upon completion of this project we will have a comprehensive list of all maintenance agreements and condition ratings for every signal system in one organized location. Schedule I held a meeting with Sherburne County's technician and he is currently working on this project for us. The project will be completed over the next few months as his schedule allows. We will use the information obtained through these inspections to prioritize the signal system painting budgeted for 2011. At the work session I will be prepared to discuss the above listed projects in more detail and take any comments, questions or direction. If you have any questions on the above projects before the meeting please call. N:\PubGc Bodies\Ciry Council\Council RCA\Agenda Packet\1-10-2011\Engineer Update.docx