MEMORANDUM
Mayor and City Council
Lori Johnson, Finance Director
September 22, 2003
Consider Public Safety Facility and City Hall/Utilities Change
Orders
The following change orders have been requested on the public safety and city hall building
projects. This list includes the change orders for the gun range which the Council has
previously approved.
Contractor
Bid Package Change Order Change Order
Number Number Amount
PUBLIC SAFETY BUILDING
Omann Brothers
(Additional base & blacktop)
Direct Digital Controls
(Atl #4 gun range mechanical system)
Sentra Sota Sheet Metal
(Alt CfA gun range mechanical system)
Multiple Concepts Interiors
(Computer room static dissipative tile)
Kelleher Construction
(Bollards)
George F. Cook Construction
(Oak wall cap)
Total
Previously Approved*
Total Change Orders to Date
3 2 $2,046.00
44 2 1,563.00
43 7 93,393.00
25 1 790.00
8 3 420.00
14 12 363.00
98,575.00
81,140.05
179,715.05
Contractor
Bid Package Change Order Change Order
Number Number Amount
CITY HALL/PUBLIC UTILITIES
Weidner's Mechanical
(fire dampers, registers, etc.)
Spectra Contract Flooring
(VCT in lieu of tile)
Empirehouse, Inc.
(158" of break metal)
George F. Cook Construction
(Case work changes)
George F. Cook Construction
(Add 2X4 window blocking)
Dryden Excavating
(Elevator pit changes & drain tile baskets)
Roof Tech
(Vestibule drainage system change)
Total
Previously Approved
Total Change Orders to Date
* Adjusted to delete change orders processed
twice.
36 1 2,252.00
21 3 485.00
18 1 696.00
10 5 (986.00)
10 6 329.00
2 1 5,000.00
13 2 1,048.30
8,824.30
28,093.42
36,917.72
Action Requested
The City Council is asked to approve the change orders as noted above.