5.4. SR 04-13-1998ITEM 5.4.
Howard R. Green Oompany
QONSULTING ENGINEERS
April 6, 1998
File: 803350j
Mr. Pat Klaers
City Administrator
City of Elk River
13065 Orono Parkway
Elk River, MN 55330
RE:
1998 BITUMINOUS OVERLAY AND STREET IMPROVEMENTS
CITY OF ELK RIVER, MINNESOTA
Formerly MSA
Consulting Engineers
Dear Mr. Klaers:
In our conversation last week, you indicated that you would like the bituminous overlay and
street improvements project completed as quickly as possible. To that end, we have set up a
schedule that will "fast-track" the design and bidding of this project as much as possible. The
following schedule proposes advertising the project for bids beginning next week, conducting
the public hearing and assessment hearing together, and awarding the bid on the date of the
public hearing/assessment hearing, or soon thereafter.
The proposed schedule is as follows:
Advertise bids
Star News
Construction Bulletin
Open Bids
Accept Feasibility Study / Order Public Hearing
Present Bid / Order Preparation of Assessment Roll
Advertise for Public Hearing/Assessment Hearing
Hold Public Hearing/Assessment Hearing
Award Bid
April 15
April 27, April 24, and May 1
May 7
May 11 or May 18
May 11 or May 18
May 20 and May 27
June 8 (special meeting)
June 8 or later
If you have any questions or would like to make any changes to this schedule, please contact
me.
Sincerely,
Howard R. Green Company
~ .
Terry J. 'Maurer, P.E.
TJM/et
O:\proj\803350\350-0614.apr