5.7. SR 10-13-2003HEHORANDUH
Item
~5.7.
TO:
FROM:
DATE:
SUBJECT:
Mayor and City Council
Pat Klaers, City Adminstr~.~./~,.
October 13, 2003
Ice Arena Floor Discussion
Hopefully the floor in the barn will be able to handle ice for this upcoming skating season without a
major delay or expense. However, as outlined in the memo from Ice Arena Manager Rich Czech,
this may not happen. In this regard, we are moving forward on a "dual track" as if: (1) the floor is
not going to work this year and we need to do a major reconstruction ASAP, or (2) that ice will be
available in the not-to-distant future.
Rich is doing everything he can in order to try to get ice on the barn floor this season. In trying to be
prepared if this does not work, we have advertised for bids for the reconstruction of the floor and
planned for this work to begin in November.
Funding for this floor has previously been discussed in a preliminary fashion. The city can either pay
for this project with liquor store funds and/or NSP funds, or these funds by can be used way of an
internal loan and this project can be funded with the government building monies (landfill host fee
dollars) when they become available in 2005.
The funding for the floor-dasher board project can be discussed later with the capital improvement
program review. The key issue or question is whether or not the City Council wants to fund this
project with government building reserves and part of the answer to this question is what other uses
(and when) are there for the government building reserves. The list of possible uses for the
government building reserve is quite lengthy and the decision by the City Council will depend on
needs and priorities. If government building funds are not to be used for this project, then as noted
in the previous paragraph, funding will come from the liquor store enterprise fund and/or the NSP
reserve fund with a (likely?) possible combination of these two funds being used for the project.
S:~Council~Pat~2003~icearenafloor.doc
ELK RIVER ARENA
1000 SCHOOL STREET N.W.
ELK RIVER, MN 55330
(763) 635 - 1141
Fax (763) 635 - 1144
To: Pat Klaers, Elk River City Administrator
From: Rich Czech, Arena Manager
Date: October 9, 2003
Subject: The Barn's Rink Repairs
As I stated in my last memo, we were not able to pull the temperature down during the
start up procedures. This was due to moisture in the system that was freezing once the
temperature of the refrigerant got below freezing.
Since 1988, pipes in the floor have needed to be repaired. Every summer we check the
floor for leaks and then repair the leaks that were found. This year was no exception; we
made over 30 repairs to the floor this past summer.
During this year's start up we have been dealing with two different problems, moisture in
the system, and excessive leaks in the pipes in the floor.
The moisture in the system was caused from years of opening the floor for repairs and
from this past year when a pipe was sheared while the concrete was being sawed,
introducing water in the pipes.
The excessive leaks in the pipes in the floor this season were caused by all the times the
floor was opened for repairs. The best way I can describe this is to compare it to a cancer.
Since 1988 we have gone into the floor to repair leaks (cancer). For many years we were
able to stay ahead of the leaks. Eventually, the cancer in the floor has spread to where the
floor might be beyond repair.
From my understanding, there are three issues that occur when the pipes in the floor are
repaired. First, once the refrigerant and oil in the pipes were exposed to the atmosphere, it
created acids and alkalis that continue to rust the pipes in the floor at an accelerated rate.
Second, the piping in the floor has a natural electrical current. This current is changed
when the new piping is installed. The new pipe and the fittings that were used to repair
the leaks creates a different current that actually removes material from the existing pipes,
starting corrosion on the existing pipes in the floor that eventually results in the pipes
failing. Third, the jack hammering that we use to get at the leaks has loosened the
concrete around other pipes exposing them to the water when flooding the rink, which
starts corrosion on the pipes.
With all of this in mind, here is a summary of what has been done to correct the problem
and what still needs to happen before the system can be operating.
Over the last three weeks we have made over 70 repairs in the pipes that are in the fink
floor. These repairs were needed not only to hold the refrigerant in the pipes, but also to
hold a vacuum on the floor.
We have introduced over 24,000 pounds of nitrogen into the pipes in the floor to remove
moisture and any other impurities from the pipes in the floor.
A vacuum has been put on the pipes in the floor to remove any other moisture that still
may remain in the floor. This will take about a week, until approximately October 16th. A
micron gauge will be used to determine how much vacuum is on the floor. A new floor
should be able to hold a vacuum of about 500 microns over a 48 hour period, a floor that
is in relatively good shape should be able to hold a vacuum between 1,200 -1,500
microns in a 48 hour period. We are hoping that the Barn's floor holds a vacuum between
2,000 and 2,500 microns in a 24-hour period.
If the vacuum works, we will then install dryer cores in the system and start the ice plant.
The refrigerant will be kept above freezing while the dryer cores remove additional
moisture and impurities from the refrigerant. Once we feel that we have done the best we
can to remove the moisture and impurities from the refrigerant, we will then start
lowering the temperature of the refrigerant to start cooling the floor. If this works, we
should be able to start making ice about October 21 st, and have ice available to skate on
by October 24th or 25th. This could vary depending on if we experience any problems
along the way.
The costs for the repairs to get the rink running are close to $12,000.00. If we are able to
get the Barn running by the 24th of October, we will have lost close to $20,000.00 in ice
sales due to the delay. If a new floor is needed and is approved this fall we will loose
about $113,000.00 in ice sales, prior to the new floor being ready for use in January. If the
Barn does not operate at all this season we will loose about $170,000.00 in ice sales,
admissions, and programs.
There are two scenarios that could prevent us from getting the system started this year.
First, if we cannot get the floor down to a vacuum below 2,500 microns, we will know
that there are too many leaks in the floor to start up the system. At this point it may be
unfeasible to try to fix any more leaks in the pipes in the floor. If we could find all the
leaks we would be looking at November, early December before we could possibly try to
start the system. At that time there would be no guarantees that we would be able to get
the system operating correctly.
The other scenario is that there is still be too much moisture and impurities in the system
to have it operate correctly. We will know more once we start bringing the temperature
of the refrigerant towards the freezing point.
Either scenario would force us to move forward on a new floor or to not have ice until the
fall of 2004, when the floor is scheduled to be repaired.
With your approval, I moved forward in the process of getting bids to replace the floor.
In the bidding documents there is a base bid that moves the project forward to this fall
and an alternative bid that moves the project forward next spring. This will give the
council the options of rejecting the base bid if the repairs we've made worked and we're
able to operate this year. If they choose to reject the base bid, they could then award the
alternative bid for next spring. If the repairs do not work, they could award the base bid if
they choose. If the repairs are needed this fall, we would be looking at a completion date
of about January 17th with ice time being ready January 22nd.