5.7. SR 11-10-2003River
MEMORANDUM
Item # 5.7.
TO:
Mayor and City Council
FROM:
Pat Klaers, City Administrator
DATE:
November I 0, 2003
SUBJECT: Public Safety/City Hall Update
The last City Council update on the public safety - city hall - utilities construction project was given
at the October 13, 2003 meeting. Since that time, the monthly meeting with the Construction
Manager (Kraus-Anderson), the Architect (Tushie Montgomery), and city staff was held on October
28, 2003.
The city received good news regarding the status of the public safety building at the October 28,
2003 meeting. The elliptical wall repair work has been successfully completed. Also, progress
continues to be made with the gun range and we can expect that shooting activities will begin
around the first of the year; the impound lot is under construction and should be completed by the
end of November; and finally, the EOC cabinets are on site and are being installed.
Attached for your information are two memos from Chief of Police Beahen regarding activities at
the public safety facility. It goes without saying that we are very pleased to have received a safety
grant to help with the expenses associated with the gun range. Of all the items remaining on the
punch list, the ceiling lights seem to be the biggest nuisance issue. Gary Lore, in charge of building
maintenance for the city, is working with Kraus-Anderson to get this problem corrected.
The utilities building punch list is being worked on and progress continues to be made. Gary Lore is
also working with Kraus-Anderson on problems with lights in the utilities building. Both buildings
have the same issue where the lights are burning out much too quickly. Other issues with the utility
building that are being worked on include the heat distribution throughout the building and the
masonry work near some of the windows where we experienced small water leaks.
The remodeling of the old city hall and police station is moving forward without any major
problems. We are still waiting for the official change order of approximately $31,000 for the HVAC
system. In this regard, we needed to add a number of the smaller individual heating/cooling units
that are spaced throughout the building and also some ductwork. Another unplanned issue that
needs to be addressed during this remodeling project is the removal of some mold that was found in
S:~CouncilkPat~ Updates~PublicSafety.doc
the kitchen area. This appears to be a somewhat minor financial issue. I~raus-Anderson believes that
the remodeling is ahead of schedule and that we will be relocating into the facility earlier than
originally anticipated.
Both the Chief of Police and the Finance Director will be m attendance at the November 10, 2003
City Council meeting and will be available to help answer questions the City Council may have
regarding the construction project.
S:~Council~Pat~Updates~PublicSafety.doc
City of
,3ver
Police Department
MEMORANDUM
TO:
FROM:
DATE:
SUBJECT:
Mayor and City Council
Jeffrey A. Beahen, Chief of Police
November 2, 2003
Building Updates
The Public Safety, Building is very close to final completion with just a few minor details left
to be completed. Some of these issues unresolved are signage, caulking, clean-up and cabinet
work. I am pleased that overall progress has been better over the past few weeks and it
appears that the end is finally near.
The upper walt was tested with over 6,000 gallons of water last week and no interior leaks
xvere found anywhere in the building. One thing noted was that the exterior portion of the
wall was coated with a sealant so that at this point, no water is penetrating the brick. That
was not as true a test of the wall and the new internal membrane that we would have liked. It
should be noted however that the week prior, the wall was power washed under high
pressure, which should have revealed leaks as this was prior to the sealant being applied. I
am happy to report that no leaks were found that day either.
Regardless, we have a ten-year guarantee on the wall so should any leaks develop in the
future we have full assurances that they will be taken care of.
There are still some minor drainage issues to be resolved at the rear of the fire station, but
these are being taken care of, hopefully by snowfall.
The exterior fence at the impound lot including all gates and entrances is scheduled to be
installed this week. Other than parking signs that will take care of most of the exterior work.
We are working with Phil Hals to get signs up prior to the end of this corning week which
will designate visitor parking, employee parking and squad parking.
Iklver
Police Department
MEMORANDUM
TO:
FROM:
DATE:
SUBJECT:
Mayor and City Council
Jeffrey A. Beahen, Chief of Police
November 2, 2003
Gun Range Update
The internal portion of the gun range ventilation system has been installed. Installation of
the external heater and fan is scheduled for install during the next two weeks. Caswell is
planning to install the internal portion of the range starting December 1't.
Investigator Fduntz through our Safety Coordinator applied for and received a $10,000 grant
to help defray the cost of the ventilation system. $800 of the grant is earmarked for hearing
protection with the remaining portion of the grant to be applied to the ventilation
equipment. The paperwork has arrived and has been completed and returned to OSHA.
Payment will be made when the equipment is installed.
Inv. K3untz and Dave Berggren are commended for their work on obtaining this grant.