5. EDSR 04-08-2013 Elk REQUEST FOR ACTION
River
TO ITEM NUMBER
Economic Development Authority 5.
AGENDA SECTION MEETING DATE PREPARED BY
April 8, 2013 Clay Wilfahrt,Assistant Director of
Economic Development
ITEM DESCRIPTION REVIEWED By
Consider Downtown Revitalization Microloan Application for Jeremy Barnhart, Deputy Director,
Blue Egg Market Community Operations and
Development
REVIEWED BY
ACTION REQUESTED
Consider and approve Downtown Revitalization Microloan Application for Blue Egg Market
BACKGROUND/DISCUSSION
The attached staff report to the EDA Finance Committee dated March 29,2013, and committee meeting
minutes provide background regarding the Micro Loan request.
The Downtown Revitalization Microloan program is available to business and property owners in the
Downtown District primarily for the rehabilitation and restoration of older buildings as well as new
business development.
Blue Egg currently occupies a location in downtown, and they are proposing to use the Microloan funds
to expand into 707 Main St. where they will offer cakes, fudge, and candy. Blue Egg Market is requesting
$74,500 to fund remodeling and equipment.
The applicant plans to attend the EDA meeting and respond to any questions about the project.
The EDA Finance Committee recommends the EDA approve the Downtown Revitalization Microloan
for Blue Egg Market with the following terms and conditions:
• $74,500 at 2%interest, 10 year term, 10 year amortization
• EDA to secure personal guarantee
• EDA to obtain second lien position on 707 N Main and 713 N Main, and first position on all
equipment
FINANCIAL IMPACT
The Micro Loan Fund has a current cash balance of$1,221,360 with$252,806 in notes receivable.
The EDA is asked to approve the Downtown Revitalization Micro Loan request for Blue Egg Market
with the following terms and conditions:
IP1 ■ E1E1 INATUREI
• $74,500 at 2%interest, 10 year amortization
• EDA to secure personal guarantee
• EDA to obtain second lien position on 707 N Main and 713 N Main, and first position on all
equipment
ATTACHMENTS
• EDA Finance Committee Meeting Minutes dated March 29,2013
• EDA Micro Loan Fund Policy and Guidelines
• Staff report to EDA Finance Committee re: Blue Egg Market Micro Loan Application dated
March 29, 2013
Action Motion by Second by Vote
Follow Up
N:\Departments\Community Development\Economic Development\EDA to move\Agenda\Year2013\48-2013\Action Requested-EDA 48-13
Blue Egg.docx
Elk REQUEST FOR ACTION
River
To ITEM NUMBER
Economic Development Authori Finance Committee
AGENDA SECTION MEETING DATE PREPARED BY
March 29, 2013 Clay Wilfahrt,Assistant Director of
Economic Development
ITEM DESCRIPTION REVIEWED By
Downtown Revitalization Program Micro Loan Application, Jeremy Barnhart,Deputy Director
Blue Egg Market Community Operations and
Development
REVIEWED BY
ACTION REQUESTED
Consider Downtown Revitalization Program Micro Loan application for Blue Egg Market and make
recommendation to the EDA with conditions as outlined in staff report
BACKGROUND/DISCUSSION
Blue Egg Bakery is a bakery and sweet shop in downtown Elk River owned and operated by Robin
DeWitt of Monticello. Blue Egg currently sells breads,pastries, cakes and donuts. The company plans to
use the microloan funds for an expansion project into 707 Main St. The expansion will allow Blue Egg to
expand its offerings to cakes, fudge and candy. The business will be a separate entity from the existing
store.
Mrs. DeWitt is experienced in baking and business ownership. She owned and operated Candy Station in
Benson,AZ and Greenstone Stables in Dayton, OH. Mrs. DeWitt is an SAE certified food service
manager and has a degree from Le Cordon Bleu.
Bruce and Robin DeWitt are requesting a Downtown Revitalization Microloan in the amount of$74,500
to help fund the project. The EDA would obtain a first position on the equipment and a second position
on the building. A personal guarantee will also be secured. Bruce DeWitt met with Tom Willett of the
Small Business Development Center. Mr. Willett raised some minor concerns regarding the financial
statement that were changed to meet his satisfaction.
In addition to the financial criteria that must be considered, the Finance Committee must also consider to
what degree the applicant satisfies the criteria set forth in the Micro Loan Fund policies outlined below:
Micro Loan Criteria-Downtown Revitalization Program
• Max. Loan Amount: $74,999
• Interest rate: Fixed at 2%
• Equity: 10% or more of project
• Term: The maximum maturity date will be determined by the useful life of the improvement and the
energy payback achieved. For projects that have a shorter length of payback (2-5) years as calculated
111 E R E I 1 r
NATURE
according to energy savings, the loans will have an initial maturity of up to 5 years from the date of
closing. Longer life improvements (6-15 years) may apply for a longer maturity of up to 10 years.
• The loans will be secured by personal and corporate guarantees, and if applicable a lien on equipment
financed and subordinate mortgage on the property
• Exempt from job creation and wage goals because the loan amount does not exceed$150,000 and
does not qualify as a business subsidy by state law
Blue Egg Market LLC
• Amount requested: $74,500
• Rate requested: Fixed at 2%
• Equity proposed: $51,500
• Term: 10-year amortization
• The EDA will obtain a second position on the mortgage of 707 Main St,a first position on the
equipment and secure a personal guaranty
The EDA will consider the Finance Committee's recommendation at their April 8 meeting.
If recommending approval, the following terms and conditions will apply:
Participation Loan: Not Applicable
Loan Amount: $74,500
Interest Rate: 2% fixed
Term: 10-year amortization
Security: First position on equipment, Second position mortgage on 707 Main St,personal
guaranty
ATTACHMENTS
• Micro Loan Application and applicable attachments
• Business Plan
Action Motion by Second by Vote
Follow Up
N:\Departments\Community Development\Economic Development\EDA to move\Agenda\Year2013\4-8-2013\Blue Egg Sweets EDA Finance
RFA 3-29-2013.docx
MEETING OF THE EDA FINANCE COMMITTEE
HELD AT THE ELK RIVER CITY HALL
FRIDAY, MARCH 29, 2013
Members Present: Chad Vitzthum,Larry Toth,Paul Motin,Nate Ovall,Cliff Lundberg,Dan Tveite
Members Absent: None
Staff Present: Assistant Director of Economic Development, Clay Wilfahrt,
Others Present: Bruce DeWitt,Blue Egg Bakery,Tim Dolan and Annie I ckert, Decklan Group,Peter
Orluck, Orluck Industries, Dan Bosshart and Lloyd Pson,Preferred Powder Coating
1. Call Meeting to Order ���
Assistant Director of Economic Development Clay Wilfahrt cad the meeting to order at 7:30am
2. Consider Downtown Revitalization Loan for Blue Egg Market
Mr.Wilfahrt reviewed the staff report.
Mr. Lundberg asked if the EDA should seek a position Blue _ existing building. Tim Dolan of
the Decklan Group who was working with the applicant s' : f iat the y would be oka y
with that.
Bruce DeWitt introduced himself and ex�':', ed about Blue E:\:, t4 ery. They just celebrated their first
anniversary. He explained that high end: :. ® ,d cakes have be° ® Ming well which led them to the
idea of expanding.
AV Av
The committee discussed the fact that the loan was a 10 y and direct loan. Mr. Oval stated that
the baker equipment lasted a ' time. The committee was okay with the term and the fact that the loan
was direct. The core ttee lik . e fact that theme'.an was fully amortized.
Several members of the c tt c mentioned that it was good to see the applicants had extensive
experience in management,.
MOVED BY MOTIN AND C�ONDED BY TVEITE TO RECOMMEND APPROVAL OF
TH\,� APPLICATION FORA 1 TOWN REVITALIZATION MICROLOAN FOR BLUE
EGIBAKERY. MOTION CAR . • 6-0.
3. Consider oan A. Dlicati t s for the For''vable Loan Pro! am—Alliance Machine Orluck Industries
Preferred P f Niti wr Coatin
Lloyd PetersOn4ad Dan Bosshart of Preferred Powder Coating introduced themselves and explained
their business and theirplans to move to Elk River.
Commissioner Vitzham noted that he is working with the applicants, and that he would abstain from
voting.
Mr.Tveite stated that the project fit exactly into what the EDA was looking for when they created the
program.
MOVED BY LUNDBERG AND SECONDED BY TOTH TO RECOMMEND APPROVAL
OF THE APPLICATION BY PREFERRED POWDER COATING FOR A FORGIVABLE
LOAN IN THE AMOUNT OF $200,000. MOTION CARRIED 5-0 WITH COMISSIONER
VITZHAM ABSTAINING.
EDA Finance Committee Minutes Page 2
January,30,2013
Page 2 of 3
Peter Orluck introduced himself and gave an overview of his business and plans for expansion.
Mr. Ovall stated that the Bank of Elk River is working with the applicant and he would abstain from
voting.
Commissioner Toth noted that the business is growing quickly and expressed concern that they may
move in the near future. He asked if the EDA had any protection against a business accepting the
forgivable loan and then moving. Mr. Wilfahrt stated that under the cit iysiness subsidy policy, any
business that accepts a subsidy and moves within five years of accepti that s`ibsidy is subject to
repayment and penalties. �� ��
Mr. Motin expressed concern with the low score on the for vale loan s� b . system. Mr. Wilfahrt
stated that the forgivable loan scoring system was designe*4 e to differen between applicants than
it was to indicate strength of the project. Mr. Wilfahrta€tded that all three app ...N7'", received would
score very highly on the abatement scoring system, •: are comp\arable to others 0>0 projects
` the
EDA has accepted in terms of job creation, taxab ,�\ye.added,*d the other meas 0 nt criteria.
-
Mr. Vitzham asked if the EDA or city accepted a state gra s ould the city or EDA be penalized by the
state if someone were to accept a forgiv; ble loan and the apps 0 t failed to go through with their
project. Mr.Wilfahrt said that he would`- with the state to : ,,hat the recourse would be in that
event. , \ \`
The committee further recommended that th'yterms ith th terms rovided by the bank.
p Y
MOVED BY TVEITE`AN\ \ECONDED \ VITZHAM TO RECOMMEND APPROVAL
OF THE REQUE� BYO ` CK INDUS' IES FOR A FORGIVABLE LOAN IN THE
�
AMOUNT OF$2v 0. mo‘, bN CARRIED; -O,WITH COMISSIONER OVALL
ABSTAINING. \
Annie D` w O\; Deckll ,\ oup info ` the committee about Alliance Machine and their
prop std expansib\\ \\\
h'
mittee expresse t1t the sclg sheet may need to be updated to better reflect the strength of
the ap tion. A\
\\
Mr.Tveite star that suppcing the Alliance project is an excellent example of how a city can support
an existing bus\iii .to encrage economic growth.
\\
Mr. Ovall stated that\\e Bank of Elk River is working with the applicant and he would abstain from
voting.
MOVED BY TVEITE AND SECONDED BY MOTIN TO RECOMMEND APPROVAL OF
THE REQUEST BY ALLIANCE MACHINE FOR A FORGIVABLE LOAN IN THE
AMOUNT OF $200,000. MOTION CARRIED 5-0 WITH COMISSIONER OVALL
ABSTAINING.
C:\Users\dhuebner\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Outlook\Q7RBTRKC\3 29 2013.doc
EDA Finance Committee Minutes Page 3
January,30,2013
Page 3 of 3
4. Consider Revisions to the Forgivable Loan Program
Mr. Wilfahrt reviewed the staff report. He noted that there are several businesses that could utilize the
forgivable loan if the requirement that businesses be in the manufacturing,high-tech, and industrial
sectors was removed.
Mr. Vitzham asked whether or not there was a provision to prevent businesses from leaving after
receiving the dollars,particularly in leased situations. Mr. Wilfahrt stated that there is a requirement that
they stay in Elk River for five years following the business subsidy, otherwise they would be subject to
repayment and penalties.
Mr. Motin and Mr. Tveite stated concern with removing the restrict e om the program after only one
round of applicants. Mr. Vitzham echoed the concern and stated at ",:t6elieved the EDA should keep
the program as is. `\�
The committee came to a consensus that no changes sld be made to the po It‘. .t this time.
\\\\ .\ \\\
\4. Closing
\
� F
The EDA Finance Committee meeting ended at 9:08 a.m.A`
\ \\
Respectfully submitted by, y� vv
Clay Wilfahrt
Assistant Director of Economic Development \��� \\\
\\
\\\,
C:\Users\dhuebner\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Outlook\Q7RBTRKC\3 29 2013.doc
City of
Elk
v
r
Powered by Nature
Economic Development
Microloan Fund Policy & Guidelines
And Application
Amended: May 2011
City of Elk River
Economic Development Division
13065 Orono Parkway
Elk River,MN 55330
763.635.1040
www.elkrivermn.gov/economicdevelopment/tools
ELK RIVER ECONOMIC DEVELOPMENT
MICROLOAN FUND POLICY & GUIDELINES
PURPOSE
The Economic Development Authority for the city of Elk River (EDA) recognizes
the need to stimulate private sector investment into manufacturing facilities and
equipment in order to create new jobs,boost productivity and retain existing jobs for
local residents.Additionally, the need exists to encourage investment in the
expansion and/or rehabilitation of commercial and retail buildings in order to
maintain the economic viability of Elk River's Downtown District. Subsequently,
the purpose of this program is to provide low interest,long-term (i.e.greater than
one year) loans as incentives for industrial development within the city of Elk River
and to encourage commercial and retail business owners in the Downtown District
to rehabilitate their existing buildings.
II. LOAN PROGRAMS
In order to meet the economic and community development objectives of the EDA,
three distinct loan programs exist within the Microloan Fund to promote business
growth in Elk River.
Industrial Incentive Program
Purpose: The purpose of the Industrial Incentive Program is to encourage
industrial and high technology business development that supports
the tax base and brings quality jobs to the city.
Amount: Up to $100,000 of secondary financing not to exceed 20% of the
project cost.
Equity: Must have private-sector commitments for 50% of the project cost.
Borrower must provide 10% or more of project financing.
Rate: Fixed;2 points below the lowest prime rate published in
the Wall Street Journal the day the loan is closed, or 3%,whichever is
greater.
Term: Financing with a balloon payment in 5-years. The balloon payment
must not be longer than the balloon payment of the participating
bank. Loans may be amortized up to the following limits:
20-years on real estate uses;
10-years on equipment uses.
Extension: In the event that the Borrower is unable to obtain conventional
financing to replace the Microloan at the end of five years,the loan
may be extended up to two additional years at a market rate of
Page 2of15 t i w E 1 1 1
NAME
interest.
Criteria: Borrower must be an industrial or high technology firm and create or
retain one new full-time job for each$20,000 loaned within 2 years.
Said jobs must pay a minimum wage of$10.00 per hour excluding
benefits required by law. Loans of$75,000 or more shall meet the city
of Elk River Business Subsidy Policy for the creation of new jobs at a
minimum wage of$15.00 per hour excluding benefits required by law,
as well as a 5-year location requirement.
In the case where the multiple sources of public financing are requested
(e.g. Microloan and Tax Increment Financing) job creation goals shall
not be double-counted.
Borrower must comply with the provisions of the city's Industrial and
Business Park zoning ordinances as applicable.
Downtown Revitalization Financing Program
Purpose: The Downtown Revitalization Financing Program is available to
business and property owners in the Downtown District(DD)
primarily for the rehabilitation and restoration of older buildings,as
well as new business development.
Amount: Up to$74,999 of secondary financing not to exceed 40% of the
project cost.
Equity: Must have private-sector commitments for 50% of the project cost.
Borrower must provide 10% or more of project financing.
Rate: Fixed at 2%.
Term: Financing with a balloon payment in up to 5-years. Loans may be
amortized up to the following limits:
20-years on real estate uses;
10-years on equipment uses.
Extension: In the event that the Borrower is unable to obtain conventional
financing to replace the Microloan at the end of five years, the loan
may be extended up to two additional years at a market rate of
interest.
Criteria: At a minimum,20% of Microloan dollars must be used for the
improvement of the building facades,with exceptions to be
considered when it appears the facade improvements are not
necessary. Financing of leasehold improvements will be considered at a
limit of$25,000.
Page 3of15 ! 1 ■ E l E 1 I t
INAURE
Borrower must be located in the Downtown District(DD).
Loans must be supported by sufficient collateral,which may include
personal assets and guarantees.
Energy Efficiency Improvement Program
Purpose: The Energy Efficiency Improvements Program is available to
property owners of commercial or industrial buildings in Elk River to
provide capital to businesses to invest in energy efficiency and
improve their profitability through reduced energy costs and enhance
their ability to retain and create jobs. In addition, the program helps
the city of Elk River use energy conservation as an economic
development tool.
Amount: Applicants may apply for the cost of improvements up to $74,999
Eligible Uses: Energy efficiency measures installed in or on a building include:
• Facility systems optimization (commissioning/re-commissioning)
• Facility systems control improvements
• Process efficiency improvements (CenterPoint Energy)
• Lighting efficiency improvements
• Heating,ventilation and air conditioning system modifications
• Exterior envelope improvements
• Motor and pump efficiency improvements
• Ground-source heat pump systems used to heat or cool a facility
• Installation of equipment or devices that use renewable energy
sources to generate electricity or heat or cool a building including
solar electricity (photovoltaic),wind turbine or solar thermal.
Equity: Must have a minimum of 10% equity provided by the borrower.
Rate: Fixed;2 points below the lowest prime rate published in the Wall S
treet Journal the day the loan is closed, or 3%,whichever is greater.
Term: The maximum maturity date will be determined by the useful life of
the improvement and the energy payback achieved. For projects that
have a shorter length of payback(2-5) years as calculated according
to energy savings,the loans will have an initial maturity of up to 5
years from the date of closing. Longer life improvements (6-15
years) may apply for a longer maturity of up to 10 years.
Criteria: Applicant must agree to energy audits conducted under the utility
company's Conservation Improvement Program (CIP). If warranted,
engineering studies then are performed on facilities with conservation
Page 4of15 1 ■ E R E I 1 1
INA1UREI
opportunities under the utility company's CIP Program.
Proposed energy efficiency improvements that do not qualify for the
utility's prescriptive rebate program will be reviewed and approved by
the utility company servicing the upgrade measures (e.g. Elk River
Municipal Utilities, Connexus,CenterPoint) along with a letter
indicating eligible utility rebates.
Utility rebates as applicable will be assigned to the Elk River EDA
and applied toward principal repayment of the loan.
An Elk River Energy City Commission member will be asked to
participate in the EDA Finance Committee review and
recommendation of the application.
The loans will be secured by personal and corporate guarantees,and
if applicable a lien on equipment financed and subordinate mortgage
on the property. Loans are not transferrable.
Installation must be certified through a licensed contractor and
electrician. New construction is eligible when participating with a
utility company rebate program. Eligible costs shall include only
incremental costs over industry design standards.
III. USES
1. Permitted Fund Uses:
a. Building construction
b. Land acquisition
c. Machinery
d. Furniture, fixtures,and equipment (FF&E)
e. Renovation and modernization of buildings
f. Exterior renovation of retail,commercial and industrial buildings
g. Public infrastructure needed for economic development expansions
h. Investment real estate with a minimum of 50% of the space pre-leased
2. Ineligible Fund Uses:
a. Expenditures for the construction and/or renovation of residential units
b. Working capital
c. Refinancing of existing debt
d. Inventory
IV. BUSINESSES ELIGIBILITY
Any project meeting the above criteria,and located or proposed to be located within
the city limits of Elk River as defined by this program,may be eligible for an
Economic Development Microloan as further defined herein:
Page 5of15 1 1 ll E a E 1 / 1
[NATUREJ
• Business must be a for-profit corporation,partnership,or sole
proprietorship.
• Business must be a small business as defined by the Small Business
Administration (SBA).
• Business must have a positive net worth.
• Religious,political,and pornographic enterprises are not eligible to use
the Economic Development Microloan Fund.
V. MICROLOAN FUND TERMS & CONDITIONS
Loan Structure
All Economic Development Microloans shall be structured as participation loans and
serviced by the project's primary lending institution,rather than as a direct loan,
unless otherwise approved by the EDA Finance Committee. Such an arrangement
allows for the central distribution and collection of funds and simplifies the financing
process for all parties involved.A participation agreement will be signed by the
borrower,primary lender and the EDA.
The EDA may require additional agreements to be signed by the borrower
(i.e. security agreement,personal guarantees,business subsidy agreement).
Simultaneous Microloans
The simultaneous use of different Microloan Fund Programs by any one borrower or
for any one project is prohibited.
Call of Loan
A loan shall become due and payable in full if a business relocates outside of the city
of Elk River prior to the maturity date of the loan.
Late Payment Charge
A late payment charge of 8% of the installment amount may be enforced.
VI. REGULATION FOR NEW CONSTRUCTION AND IMPROVEMENTS
All buildings which public funds will be used for construction or renovation are to
be brought into conformance with city ordinances and state building codes. Repairs
may include the following systems and portions of real property:
a. Mechanical heating,plumbing, and electrical
b. Structural;including the facade of the structure and energy related
improvements.
c. Hook-up to city services (i.e.water,sewer)
d. ADA (Americans with Disabilities Act) improvements
VII. LOAN SECURITY AND GUARANTEES
Applicant must be able to secure the loan by providing the EDA with a minimum of
a subordinate mortgage upon the building and/or assets or other approved collateral.
Page 6of15 R 1 u E 1 11 f 1
INALUREI
Applicant must demonstrate the financial means to repay the loans,as determined by
the Economic Development Authority.
Whenever possible,personal guarantees will be made part of any loan agreement.
Key person life insurance may be required as determined by the EDA Finance
Committee based on loan amount and company ownership partners.
VIII. TIMING OF PROJECT EXPENSES
No project should commence until the Elk River Economic Development Authority
has approved the loan application. Any costs incurred prior to the approval of the
loan application are generally not eligible expenditures.
No building construction should commence until the required city permits are
secured.
The applicant will be responsible for all legal,recording,and other fees required for
protection of a security interest in the loan,payable by a non-refundable 1%
processing fee,which is paid at the time of application. In addition to the
non-refundable 1%processing fee,all legal and filing fees shall be paid by the
borrower at loan closing.
IX. PROCEDURAL GUIDELINES FOR APPLICATION AND APPROVAL
1. All applicants shall first contact a primary lending institution to determine if
additional equity is needed,and if so,how much.
2. The applicant and the primary lender shall then meet with city staff to obtain
information about the Microloan program,discuss the project, and obtain
application forms.
3. The applicant shall complete and submit an application form to the city,along
with a processing fee of 1% of the loan request. (The fee is used to cover
processing expenses and will be returned only if application is denied.) The
applicant must provide evidence of their ability to meet the equity requirements
or provide a letter of commitment for conventional financing from the primary
lending institution.
4. The EDA is a governmental entity and as such must provide public access to
public data it receives. Data deemed by Applicant to be nonpublic data under
State law should be so designated or marked by Applicant. See Minn. Sat.
Sections 13.59, Subd. 1,respectively.
5. The application will be reviewed by the city staff to determine if it conforms to
all city policies and ordinances and to consider the following:
a. The availability and applicability of other governmental grants and/or
loan programs.
Page 7 of 15 1I ■ ERE , I ►
INALUREI
b. Whether the proposed project will result in conformance with building
and zoning codes.
c. Whether it is desirous and in the best interests of the public to provide
funding for the project.
6. With written permission granted by the applicant,the application will be
submitted by city Staff to the Small Business Development Center (SBDC) as
advisory consult for staff and EDA Finance Committee. Applicant will be asked
to execute a Release of Information form with SBDC. To make an appointment
with the SBDC, call 320.308.4842.
7. The EDA Finance Committee and EDA Commissioners will review each
application in terms of its consistency with the goals of the city's Comprehensive
Plan and Economic Development Strategic Plan and in relation to the project's
overall impact on the community's economy. Downtown Revitalization
Program applications will also be reviewed by a Housing&Redevelopment
Authority Commissioner in conjunction with the EDA Finance Committee.
Energy Efficiency Improvement Program applications will also be reviewed by
an Energy City Commissioner in conjunction with the EDA Finance Committee.
The EDA Finance Committee will evaluate the project application in terms of
the following:
a. Project Design -Evaluation of project design will include
review of proposed activities, time lines and a capacity to implement.
b. Financial Feasibility-Availability of funds,private involvement, financial
packaging and cost effectiveness.
• Appropriate ratio of private funds to Microloan funds.
• Sufficient cash flow to cover proposed debt service as demonstrated
by financial statements and projections.
• Ability to demonstrate a positive net worth.
• Letter of Commitment from applicant pledging to complete the
project during proposed project duration,if the loan application is
approved.
• Letter of Commitment from other financing sources stating terms
and conditions of their participation in the project if applicable.
• Sufficient collateral.
c. All other information as required in the application and/or additional
information as may be requested by the Economic Development
Authority.
d. Project compliance with all city codes and policies.
e. Program Objectives - In addition to quality job and wage
Page8ofl5 P S I E 1 E 0 1 1
NA E
creation/retention requirements, the applicant must meet all Microloan
Fund criteria and demonstrate how the proposed activities will meet at
least one of the following objectives:
• The project contributes to the fulfillment of the city's approved and
adopted economic development and/or redevelopment plans.
• The project prevents or eliminates slums and blight.
• The project increases the local tax base.
• The project brings a structure into compliance with an existing
building code violation.
8. A written request for an extension shall be accompanied by a copy of current
financial statements and a$500 upfront processing fee. The processing fee is
used to cover processing expenses and will be returned if request is denied. The
application for an extension beyond the original term should include a letter of
denial from a conventional lender. Refinancing will not be allowed solely for the
purpose of reducing the interest rate due to lower market interest rates.
9. The EDA Finance Committee will recommend the approval, denial,or request a
resubmission. A recommendation from the Finance Committee will be
forwarded to the EDA for final action.
X. LOAN POLICY REVIEW
The above criteria will be reviewed on an annual basis to ensure that the policies
reflected in this document are consistent with the economic development goals set
forth by the city.
XI. RIGHT OF REFUSAL
The Elk River Economic Development Authority may deny any project which it
deems inappropriate according to the guidelines established in this document.
XII. COMPLIANCE WITH MN BUSINESS SUBSIDY LAW
Each company receiving assistance in the principal amount of$75,000 or more from
the EDA Microloan Fund shall be subject to the provisions and requirements set
forth by Minnesota Business Subsidy Law Statute 116J.993 and the city of Elk River
Business Subsidy Policy.
Page 9of15 [ Matt t Y
INATUREI
ELK RIVER ECONOMIC DEVELOPMENT
MICROLOAN FUND APPLICATION
I. CONTACT INFORMATION
Legal Name of Business:
Project Site Address:
City / State / Zip
Contact Person(s)
Business Phone Fax
Home Phone Email
Check One: Proprietor Corporation Partnership
Social Security No.
Federal ID # State ID #
II. NATURE OF LOAN REQUEST
Which Micro-Loan Program are you applying for?
Industrial Incentive Program
Downtown Revitalization Financing Program
Energy Efficiency Improvement Program
Amount Requested: $ Total Project Cost: $
Type of project:
New construction for a start-up business.
New construction for an existing business.
On site expansion
Equipment purchase
Remodeling: (circle one)Commercial/ Retail / Industrial
Refinancing existing debt
Other
Page 10of15 P 1 I E 1 E 1 B 1
INA1URE
Please give a brief summary of your business and its products or service:
Please give a brief summary of the project:
Please describe how this loan will impact your project:
III. FINANCING
Project Costs
Land $
Site improvements $
Buildings (attach plans &costs) $
Equipment/Machinery/Fixtures
(attach list and estimated costs) $
Remodeling $
Industrial Inventory/Working Capital $
Other (attach description) $
Total Costs $
Comments:
Page 11of15 IPINEIEll B1
NAME
Proposed Sources of Financing
SOURCE NAME TERMS AMOUNT
Bank Loan $
Bank Loan $
Other Private Funds $
Applicant Contribution $
Other $
Fed Grant/Loan $
State Grant/Loan $
EDA Microloan $
Tax Increment Financing $
Tax Abatement $
Total Financing $
Collateral Assignments
Lien
Description of Collateral Position
To Bank 1
To Bank 2
To Private Sources
To Other Sources
To Federal Govt
To State
To EDA Microloan
Page 12of15 r1IIEBEI 1 T
INATURE
Value of Collateral
Book Value Cost Existing Liens
Land $ $ $
Buildings $ $ $
Machinery&Equip. $ $ $
Other $ $ $
Other $ $ $
IV. JOB & WAGE GOALS
Present# of Employees Total Payroll
Jobs To Be Created*
Please provide the following information on jobs you expect to create Within 2-years.
Average Are the Jobs Expected
Number Hourly Annual Permanent or Hiring
Job Title of Jobs Wage Salary Temporary? Date
*If loan is for job retention only,please explain in Business Plan.
Program Objectives
(Check all that apply)
The project contributes to the fulfillment of the city's approved and adopted
economic development and/or redevelopment plans.
The project prevents or eliminates slums and blight.
The project increases the local tax base.
The project brings a structure into compliance with an existing building code
violation.
Page 13of15 r 1 ■ 1 1 E 1 I T
INATUREI
V. PROJECT CONTACTS
Attorney
Name
Address
Phone
Accountant
Name
Address
Phone
Financing Sources (lenders,partners, etc...)
Name
Address
Phone
Name
Address
Phone
Parent Company
Name
Address
Phone
Others
Name
Address
Phone
Name
Address
Phone
Page 14of15 r111111111 I f
NAME
VI. ATTACHMENTS CHECK LIST
Please attach the following:
A) Written Business Plan:
1. Description of Business
2. Ownership
3. Management
4. Date Established
5. Products/Services
6. Future Plans
B) Financial Statements for Past Two Years
C) Financial Projections for Two Years
D) Resume of Owner/Management
E) Personal Financial Statements of Proprietor,Partners,
Guarantors
F) Letter of Commitment from Applicant Pledging to Complete
During the Proposed Project Duration
G) Letter of Commitment from the Other Sources of Financing,
Stating Terms and Conditions of their Participation in
Project
H) Fee of 1% of amount of loan request
VI. AGREEMENT
I /We certify that all information provided in this application is true and correct to the best
of my/our knowledge. I / We authorize the city of Elk River and the Finance Committee to
check credit references and verify financial and other information. I / We agree to provide
any additional information as may be requested by the city and the Finance Committee.
APPLICANT SIGNATURE
BY
DATE
Page 15of15 ► 1 ■ EiE , of