4.1. SR 07-06-1998Item ~4.1.
Howard R. Green Oompany
CONSULTING ENGINEERS
July 1, 1998
File: 801210J (0564)
801840J (0564)
803691J (0564/0071)
CONSULTING BGINEERS
Formerly MSA
Consulting E-noineers
Honorable Mayor and City Council
City of Elk River
13065 Orono Parkway
PO Box 4901
Elk River, MN 55330
RE:
BOSTON STREET, RAILROAD DRIVE, GUARDIAN ANGELS LAKE ORONO
ASSESSMENT HEARINGS
Dear Council Members:
The assessment hearings for the three above-referenced projects are scheduled for the
July 6, 1998 City Council meeting. It would be appropriate for the City Council to deal
with each of these projects separately by having staff make a brief presentation, opening
the assessment hearing, taking public comment, closing the assessment hearing, and
then considering the attached resolution adopting the assessment roll.
At the time of this memo, City Staff has not received any formal written appeals.
Individuals may appeal their assessment to this project by presenting a signed, written
objection to the Mayor at the hearing. An individual simply standing up at the
assessment hearing indicating their objection to the project does not constitute
an assessment appeal. Following the submission of the signed, written objection, the
property owner must also serve notice of appeal upon the Mayor or City Administrator
within thirty days after the adoption of the assessment roll. They must file their notice
with the District Court within ten days of serving the Mayor or the City Administrator.
The following is a brief summary of issues pertaining to each assessment project.
1. Boston Street Utility Improvements
Based upon the Iow bid received, the proposed assessments are exactly the
same as those presented in the feasibility study. There are three individual
properties along Boston Street that would receive sanitary sewer and water
benefit, and Orono Cemetery, which would receive water benefit only. Two of
the residential properties were deemed to be large enough to further subdivide.
Those two properties were assessed two units for sanitary sewer, water, and
O:\PROJ\803691J\0564\691-0507.july.doc
1326 Energy Park Drive · St. Paul, MN 55108 ° 612/644-4389 fax 612/644-9446 toll free 888/368-4389
City of Elk River
July 1, 1998
Page 2
street restoration, however, the second unit of sanitary sewer and water, in the
amount of $6,150 per property, is proposed to be deferred with no interest. It
would become payable only if and when the properties in question were
subdivided.
It came to City staff's attention that the Karen Thomas property has sold a small
piece of property to the neighbor. This raises the question as to whether this
property could be subdivided in the future. The City Planner reviewed the
information and felt that a good case for variance could be documented,
therefore, the feasibility study recommendation to assess two units with one
deferred has been followed in the assessment roll.
At the close of the Boston Street assessment hearing, it would be appropriate to
consider the attached resolution, adopting the final assessment roll. This
resolution can be adopted with any changes to the assessment roll that the City
Council deems appropriate.
Railroad Drive Street and Utility Improvements
Again, with this project, based on the Iow bid received, the proposed
assessments are exactly as presented in the feasibility study. The amount of the
proposed assessments varies. Marty's Feed Mill is proposed to be assessed for
sanitary sewer, water, and street reconstruction at $4,000 each for a total of
$12,000. The former paint store is proposed to be assessed for sanitary sewer
and street reconstruction at $4,000 each for a total of $8,000. The lumberyard,
Eagle's Club, and former auto supply store are proposed to be each assessed for
street reconstruction only at $4,000 each. There will also be contributions from
the Elk River Municipal Utilities for the watermain improvements, based on the
watermain loop that will provide benefit to the entire water system and a
contribution from the City of Elk River, for the street reconstruction.
Again, at the close of the assessment hearing, it would be appropriate for the
City Council to consider the attached resolution, adopting the final assessment
roll. This resolution can be adopted with any changes the City Council deems
appropriate.
Guardian Angels Lake Orono Improvements
As with the other two projects, this one also is proposed to be assessed exactly
as presented in the feasibility study. Guardian Angels is being assessed for all
sanitary sewer and watermain improvements inside their property boundaries.
The Donovan Goossen property is being assessed for lateral sanitary sewer and
water, in the amount of $9,400, and the Elk Motel is being assessed for two units
each of lateral sanitary sewer and water benefit, in the amount of $18,800.
R. Green Company
CONSULTING ENGINEERS
City of Elk River
July 1, 1998
Page 3
City Staff has had several conversations with Mr. Goossen regarding the
proposed assessment. In 1993, prior to Mr. Goossen's purchase of the property,
the former owners, Timothy and Janet Harvey, actually connected the property to
sanitary sewer. At that time, they signed a petition waiving their rights to appeal
a future assessment for lateral sanitary sewer and water. The petition, a copy of
which is attached, indicates that they will pay the assessments in the future when
the lateral lines are installed, or when they sell the property. Apparently, at the
time of the Goossen purchase of the property, it was indicated that the property
was hooked up to sanitary sewer and water, and that no mention of the future
assessment was made. City Staff's position is that the property can be assessed
for lateral sanitary sewer and water benefit, based on the petition that Timothy
and Janet Harvey signed on April 8, 1993, and that Mr. Goossen's recourse is
against the Harveys.
Mr. Goossen also owns the piece of residential property located further north of
the former garage door property. This residential piece of property is not
proposed to be assessed for lateral sanitary sewer and water at this time.
However, Mr. Goossen has indicated his desire to hook up to lateral sanitary
sewer and water for the residential property, which is currently on a private well
and on-site sewer system. We have indicated to him that in order to connect that
property to the City Utilities, he will have to deal with Lori Johnson, relative to a
$9,400 lateral sanitary sewer and water assessment.
Again, at the close of the assessment hearing, it would be appropriate for the
City Council to consider the attached resolution adopting the assessment roll.
This resolution can be adopted with any changes to the assessment roll that the
City Council deems appropriate.
Bids for these three projects, together with the Jackson/Holt utility improvements and
School Street improvements west of Proctor Avenue, were opened on Wednesday, June
10, 1998. There were a total of ten bids received. The following list provides the name
of the bidder and their total bid.
Bidder Base Bid Total
Redstone Construction Co., Inc.
Richard Knutson, Inc.
Barbarossa & Sons, Inc.
Kober Excavating, Inc.
Northdale Construction Co., Inc.
R.P. Utilities, Inc.
R.L. Larson Excavating, Inc.
S.R. Weidema, Inc.
S.J. Louis Construction, Inc.
Bonine Excavating, Inc.
$373 231.40
$389 058.46
$422 312.00
$431 873.67
$439 220.08
$442 905.61
$453 274.50
$474 847.15
$489 131.50
INCOMPLETE
R. Green Company
CONSULTING ENGINEERS
City of Elk River
July 1, 1998
Page 4
Redstone Construction Company, Inc. has successfully completed similar projects in the
past, therefore we would recommend award to them as the lowest responsible bidder.
Depending on the outcome of the three assessment hearings, the Council can consider
the fourth attached resolution, which would award the project to Redstone Construction
Company, Inc. If the City Council adopts this resolution, it should be with the
contingency that the School Street schedule is not awarded until such time that the
School Board provides the City of Elk River the necessary easement for the 1999 School
Street improvement.
If you have any questions or would like any additional information regarding these three
projects, please call.
Sincerely,
Howard R. Green Company
TJM/st
Enclosures
R. Green Company
CONSULTING ENGINEERS
City of Elk River
State of Minnesota
Pk-FITION FOR LOCAL IMPROVEMENT
To the City Council of Elk River, Minnesota:
WE, THE UNOE.qSiGNE'30WNE.qS of (all) (not less than 35 percenr- in
fronr-age) of the real proper=y described as'
heresy per. ir. ion, pursuant to Minnesota Statutes, Chapter 429, for the
following public imorov~ments:
EACH OWNER FURTHER AGREES, in consideration of the City acCion aC our
request ~o cause cons~ruccion of ~he above-described improv~enC, ~o pay
such sums as may be de~ermined by ~he City ~o be a fair and reasonable
a~oorcionmenc of ~he ccs~ of said improvement..
OWNER EXPRESSLY WAIVES OBJECTION to any irregularity with regard to
the making of the im~rov~men: or assessment of the cost thereof; weives any
claim thac the amount thereof levied agains~ owner's property is excessive;
and waives all rights of a~peal in the cour:s.
7
8
i0.
Signature
Date of Owner
Print Name
of Owner
Description of
Propercy
/
Ex~mined, c,,e.ked, and found r-o be in prooer form and Co be signed by
Che owners of the above-sr-aCed quan[ir-y of property affecr-ed by ~.he making
of ~he im~rovemenr- petitioned for.
City Cl er~( " ~
A-5
RESOLUTION 98 -
A RESOLUTION FOR THE CITY OF ELK RIVER
A RESOLUTION ADOPTING FINAL ASSESSMENT ROLL
IN THE MATTER OF THE
BOSTON STREET IMPROVEMENTS OF 1998.
WHEREAS,
upon due notice properly made as required by law, the Elk River City
Council has met and heard and passed upon all objections to the
proposed assessment for the Boston Street improvement and has
determined the amount to be assessed against each individual property
as the Council deems just;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Elk River,
Minnesota:
Final assessment roll, a copy of which is attached hereto and incorporated herein
by this reference, is hereby accepted and adopted and shall constitute the
special assessment against the lands therein named. Each such tract of land in
the assessment roll is hereby found to be benefited by the improvement in an
amount not less than the amount of the assessment levied against it.
Such assessment shall be payable in equal annual installments, including both
principal and interest, amortized in such amount annually as is required to pay
the principal with interest as 6.5% over a period of up to 15 years.
The owner of any property so assessed, may, at any time prior to certification to
the County Auditor of the assessment or the first installment thereof, pay to the
City Treasurer the whole of the assessment on such property, with interest
accrued to the date of payment; except that no interest shall be charged if the
entire assessment is paid within 30 days after the adoption of this Resolution.
Prepayment may also be made after the certification of the assessment or first
installment thereof by paying to the City Treasurer/Auditor the entire amount of
the assessment remaining unpaid with interest. In the case of a payment made
before November 15, interest will be calculated through December 31 of the next
succeeding year.
The City Administrator shall transmit to the County Auditor a certified duplicate of
the attached assessment roll to be extended on the property tax lists of the
County. Such assessment shall be collected and paid over in the same manner
as other municipal taxes.
Passed and adopted this 6 day of July 1998.
ATTEST:
Henry A. Duitsman, Mayor
Sandra A. Peine, City Clerk
O:\PROJ\803691J\0564\691-0307.july. Res.doc
RESOLUTION 98 -
A RESOLUTION FOR THE CITY OF ELK RIVER
A RESOLUTION ADOPTING FINAL ASSESSMENT ROLL
IN THE MATTER OF THE
RAILROAD DRIVE IMPROVEMENTS OF 1998.
WHEREAS,
upon due notice properly made as required by law, the Elk River City
Council has met and heard and passed upon all objections to the
proposed assessment for the Railroad Drive improvement and has
determined the amount to be assessed against each individual property
as the Council deems just;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Elk River,
Minnesota:
Final assessment roll, a copy of which is attached hereto and incorporated herein
by this reference, is hereby accepted and adopted and shall constitute the
special assessment against the lands therein named. Each such tract of land in
the assessment roll is hereby found to be benefited by the improvement in an
amount not less than the amount of the assessment levied against it.
Such assessment shall be payable in equal annual installments, including both
principal and interest, amortized in such amount annually as is required to pay
the principal with interest as 6.5% over a period of 5 to 10 years.
The owner of any property so assessed, may, at any time prior to certification to
the County Auditor of the assessment or the first installment thereof, pay to the
City Treasurer the whole of the assessment on such property, with interest
accrued to the date of payment; except that no interest shall be charged if the
entire assessment is paid within 30 days after the adoption of this Resolution.
Prepayment may also be made after the certification of the assessment or first
installment thereof by paying to the City Treasurer/Auditor the entire amount of
the assessment remaining unpaid with interest. In the case of a payment made
before November 15, interest will be calculated through December 31 of the next
succeeding year.
The City Administrator shall transmit to the County Auditor a certified duplicate of
the attached assessment roll to be extended on the property tax lists of the
County. Such assessment shall be collected and paid over in the same manner
as other municipal taxes.
Passed and adopted this 6 day of July 1998.
ATTEST:
Henry A. Duitsman, Mayor
Sandra A. Peine, City Clerk
O:\PROJ\803691J\0564\691-0207.july. Res.doc
RESOLUTION 98 -
A RESOLUTION FOR THE CITY OF ELK RIVER
A RESOLUTION ADOPTING FINAL ASSESSMENT ROLL
IN THE MATTER OF THE
GUARDIAN ANGELS LAKE ORONO IMPROVEMENTS OF 1998.
WHEREAS,
upon due notice properly made as required by law, the Elk River City
Council has met and heard and passed upon all objections to the
proposed assessment for the Guardian Angels Lake Orono improvement
and has determined the amount to be assessed against each individual
property as the Council deems just;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Elk River,
Minnesota:
Final assessment roll, a copy of which is attached hereto and incorporated herein
by this reference, is hereby accepted and adopted and shall constitute the
special assessment against the lands therein named. Each such tract of land in
the assessment roll is hereby found to be benefited by the improvement in an
amount not less than the amount of the assessment levied against it.
Such assessment shall be payable in equal annual installments, including both
principal and interest, amortized in such amount annually as is required to pay
the principal with interest as 8.5% over a period of up to 15 years.
The owner of any property so assessed, may, at any time prior to certification to
the County Auditor of the assessment or the first installment thereof, pay to the
City Treasurer the whole of the assessment on such property, with interest
accrued to the date of payment; except that no interest shall be charged if the
entire assessment is paid within 30 days after the adoption of this Resolution.
Prepayment may also be made after the certification of the assessment or first
installment thereof by paying to the City Treasurer/Auditor the entire amount of
the assessment remaining unpaid with interest. In the case of a payment made
before November 15, interest will be calculated through December 31 of the next
succeeding year.
The City Administrator shall transmit to the County Auditor a certified duplicate of
the attached assessment roll to be extended on the property tax lists of the
County. Such assessment shall be collected and paid over in the same manner
as other municipal taxes.
Passed and adopted this 6 day of July 1998.
ATTEST:
Henry A. Duitsman, Mayor
Sandra A. Peine, City Clerk
RESOLUTION 98 -
A RESOLUTION FOR THE CITY OF ELK RIVER
A RESOLUTION ACCEPTING BID AND AUTHORIZING
EXECUTION OF CONTRACT IN THE MATTER OF THE
BOSTON STREET, RAILROAD DRIVE,
GUARDIAN ANGELS LAKE ORONO,
JACKSON/HOLT UTILITY AND
SCHOOL STREET IMPROVEMENT OF '1998
WHEREAS
WHEREAS
pursuant to Resolution 98-57, competitive bids were solicited and
received for the Boston Street, Railroad Drive, Guardian Angels Lake
Orono, Jackson/Holt Utility and School Street improvement as set forth in
the bid tabulation attached hereto and incorporated herein by this
reference; and
the City Council has considered the amount of the bids and the
responsibility of the bidders and determined that Redstone Construction
Company is the lowest responsible bidder;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Elk River,
Minnesota:
The Mayor and City Administrator are authorized and directed to execute, on
behalf of the City, such contract with Redstone Construction Company as is
approved by the City Attorney for the completion of the Boston Street, Railroad
Drive, Guardian Angels Lake Orono, Jackson/Holt Utility and School Street
improvement according to the approved plans and specifications designated in
Resolution 98-57.
The City Administrator is authorized and directed to forthwith return to all bidders
the deposits made with their bids upon execution of the contract above specified.
Passed and adopted this 6 day of July 1998.
ATTEST:
Henry A. Duitsman, Mayor
Sandra A. Peine, City Clerk
O:\PROJ\803691J\0564\691-0407.july. Res.doc