4.3C SR 07-15-2013 �i
EOty lk Request for Action
River
To Item Number
Mayor and City Council 4.3C
Agenda Section Meeting Date Prepared by
Consent my 15, 2013 Justin Femrite, P.E., City Engineer
Item Description Reviewed by
Pay Estimate 1 - Bailey Point Nature Preserve Cal Portner, City Administrator
Parking Lot Reviewed by
Action Requested
Approve by motion the pay estimate as described below.
Background/Discussion
Listed below is a pay estimate that has been submitted for approval. I have reviewed this pay estimate
and find it to be accurate and in accordance with the contract documents.
Financial Impact
PROJECT PAY EST. # CONTRACTOR AMOUNT
Bailey Point Nature Preserve Parking Lot I Brenteson Companies,Inc. $23,347.68
Attachments
■ Pay Estimate I
P 0 W I R I I a
N:APublic Bodies\Agenda Packets\7-15-2013\Fina1\x4.3.0 st.docx [NA T-- UR
CITY OF ELK RIVER PAY ESTIMATE NO. 1
13065 Orono Parkway FROM: June 1, 2013
Elk River, MN 55330 TO: June 30, 2013
Bailey Point Nature Preserve Parking Lot CONTRACTOR: Brenteson Companies, Inc.
July 9th, 2013 20300 166th Street
Big Lake , MN 55309
CONTRACT ITEMS THIS PERIOD
ITEM
NO. DESCRIPTION UNIT QTY. UNIT QTY. AMOUNT
PRICE
1 Mobilization LS 1 $3,440.00 1 $3,440.00
2 Rock Construction Entrance EA 1 $1,222.50 0 $0.00
3 Remove/Salvage Fence LF 50 $4.80 20 $96.00
4 Silt Fence LF 600 $4.00 0 $0.00
5 Inlet Protection EA 2 $542.00 2 $1,084.00
6 Bio Rolls LF 20 $5.40 415 $2,241.00
7 Sawcut Concrete or Bituminous pavement LF 60 $3.50 60 $210.00
8 Bituminous Pavement removal,replace,reshape SF 100 $17.80 0 $0.00
9 Common Excavation LS 1 $1,400.00 1 $1,400.00
10 Salvage/Respread topsoil LS 1 $1,360.00 1 $1,360.00
11 Swale Grading LS 1 $100.00 1 $100.00
12 B612 Concrete Curb and Gutter LF 550 $14.30 540 $7,722.00
13 Concrete Pedestrian Ramp EA 1 $770.00 1 $770.00
14 Rip Rap with Membrane LS 1 $575.00 0 $0.00
15 Place C17 Agg. CY 381 $15.55 350 $5,442.50
16 Turf Establishment SY 630 $0.90 0 $0.00
17 Erosion Control Blanket SY 630 $1.00 0 $0.00
18 Sub grade Ex CY 1300 $1.85 60 $111.00
19 Granular Borrow(cv) CY 1300 $10.00 60 $600.00
Total $24,576.50
TOTAL THIS PERIOD
AMOUNT EARNED $ 24,576.50
AWARDED CONTRACT AMOUNT $ 45,081.05
AMOUNT RETAINED(5%) $ 1,228.83
PREVIOUS PAYMENTS $ -
AMOUNT DUE $ 23,347.68
I hereby certify that all items and amounts shown by this pay estimate are correct for the work completed to date.
CONTRACTOR: ENGINEER:
Brenteson Companies,Inc. Justin Femrite,P.E.
BY: BY:
DATE: DATE:
Approved by Owner/Commission
CITY OF ELK RIVER,MINNESOTA