3.4. SR 01-26-2004TO: FROM: DATE: SUBJECT: *Item 3.4.* MEMORANDUM Mayor and City Council Lori Johnson, Finance Director January 26, 2004 Consider Public Safety Facility and City Hall/Utilities Change Orders The following change orders have been requested on the public safety and city hall building projects. Bid Package Change Order Change Order Contractor Number Number Amount PUBLIC SAFETY BUILDING Century Fence Co. (Provide mid and bottom rails for fence) Total Previously Approved Total Change Orders to Date 6 3 $ 2,465.00 2,465.00 286,437.98 $288,9O2.98 Contractor Bid Package Change Order Change Order Number Number Amount CITY HALL/PUBLIC UTILITIES George Cook Construction (Council Chamber Dias PR 20) George Cook Construction (Council Chamber Dias PR 20) Total Previously Approved Total Change Orders to Date 10 7 $1,376.00 10 9 3,884.00 Action Requested The City Council is asked to approve the change orders as noted above. 5,260.00 72,589.21 $77,849.21