5.2. PCSR 08-24-2004 ITEM it 5.2. City of Elk River MEMORANDUM TO: Planning Commission FROM: Rebecca Haug, Environmental Technician eria- DATE: August 24, 2004 SUBJECT: Conditional Use Permit for Mineral Excavation by Schuer, Inc. Inc./P.H. CU 04-23 Request: Schuer,Inc.has an existing mining permit that allows them to mine 14.81 acres of a 66.06 acres site. They are requesting approval to mine an additional 5.5 acres of the same site. This operation includes periodic crushing of gravel, but not washing. The additional 5.5 acres are proposed to be excavated 15 feet below the ground water elevation using a dragline. The site will not be dewatered to accomplish this. The site was not included in the City of Elk River's 1994 Environmental Impact Statement(EIS)on Mineral Excavation,but a discretionary Environmental Assessment Worksheet (EAW) was completed for the original request. Additional environmental review is not required. All of the 66.06 acres site is already zoned Mineral Excavation Overlay Zoning District. A request for mineral excavation by J &B Mining is also on the Planning Commission's agenda for this meeting. Although the two requests are separate, the restoration (final contours) of the sites and wetland mitigation do tie together. Further,gravel from the J&B Mining site will be hauled through the Schuer site to Elk River Bituminous. To keep this haul route open, Phase 4 of the Schuer site (the current 5.5 acres request) will is not be mined or restored for 5 to 10 years. Attachments: Included with this memo is: ➢ a vicinity map, ➢ a Conditional Use Permit Application Submittal letter, dated March 29, 2004, ➢ A letter dated,July 28, 2004 from the city's Environmental Consultant, Matt Ledvina, regarding groundwater monitoring and the proposed environmental spill plan, ➢ a development plan, which shows the proposed final contours for the additional acreage, ➢ staff memorandum on Wetland Conservation Act, and • a proposed Conditional Use Permit (CUP). Issues: Traffic - The gravel mined from the site is currently delivered to the Elk River Bituminous site via an easement across private property owned by Aggregate Industries. Traffic from the new area(Phase 4)will be accommodated the same way. Section 10 of the attached CUP has additional stipulations on traffic. Groundwater - Mining into the groundwater raises additional concerns. Matt Ledvina, City Environmental Consultant, addresses these concerns in his attached letter. Environmental Spill Plan The petitioner's Environmental Spill Plan will be revised to address Mr.Ledvina's issues, e.g. identifying refueling locations. Ground Water Monitoring Plan The Ground Water Monitoring Plan will be revised to include monitoring for pH, temperature and conductivity as well as Diesel Range Organics. Staff does disagree with Mr. Ledvina regarding monitoring all three wells at the site, however. Staff recommends that only the down gradient well located in the southeast corner on the site be monitored(MW 1). Incidents of contamination will be known. Section 17 of the attached CUP has a condition that allows additional wells and additional testing events, if needed. National Pollutant Discharge Elimination System (NPDES) The existing NPDES permit for the operation that has been revised and approved by the Minnesota Pollution Control Agency,which includes an updated Storm Water Pollution Prevention Plan(SWPPP)that reflects the proposed Phase 4 mining area. Wetlands-The Technical Evaluation Panel,charged with reviewing wetland issues for compliance with the Wetland Conservation Act is recommending approval of both the wetland impacts and wetland mitigation for the operation. Section 9d of the attached CUP requires monitoring of the wetland mitigation, which is to be secured by a letter of credit. A dollar figure to cover the restoration has yet to be determined. The proposed wetland restoration plan is based on the premise that the groundwater level incurred is not a perch water table.If information to the contrary is discovered, the Operation shall cease until new mining and restoration plans are submitted and approved by the City. Setbacks-Normal setbacks for a mining operation in the City of Elk River are 50 feet, but they can be increased if the pit is adjacent to a sensitive land use or reduced if adjacent to another mining operation. The new area proposed to be mined,Phase 4,is bordered on the north by Ernie Toth's property,which is currently being mined by Bauerly Bros. Staff is recommending the petitioner is allowed to mine to the property line and that this area is restored to 4 to 1 slopes. It may be a long time ' before the Toth's property is mined or it may never be mined. Either way the 4 to 1 slopes suffice. To the south and east, Phase 4 will tie into the proposed J & B Mining operation and restoration. To the west, Phase 4 ties into Phase 1 of the Schuer operation. Recommendation: Staff is recommending approval of this request under the conditions contained in the attached conditional use permit. Representatives of Schuer, Inc. are in agreement with those conditions. ri ii \\, , , , _____,____ ______±_, 1 , , , ir r; i ---- I SITE Y " L A C 1" Et " �Ii• IY q, it t. rrit i L 5 .i ii it I\, c) zlim ExuE 1 ♦u lit 1 i :\\ rr 1 Al ,L 1400 i E " LYI i I " 5 E A wTM j I I " TILLS j 7 Diu .� 1itI! k3• �I I , Location Map *vier N 4 Case Number CU 04-23 SCHUER www.liesch.cam - 1.1 ;ATE nECLI: oar LIE CH LIESCH ASSOCIATES, INC. 13400 15TH AVENUE NORTH MINNEAPOLIS, MN 55441 763/489-3100 FAX:763/489-3101 March 29, 2004 VIA MESSENGER Mr. Steve Rohlf Building and Zoning Administrator City of Elk River 13065 Orono Parkway Elk River, Minnesota 55330 RE: Conditional Use Permit Application Submittal, Schmidt Gravel Mine—Phase 4 Schmidt Gravel Mine, 11349 219th Street NW,Elk River, Minnesota(the Property) Dear Steve: Liesch Associates, Inc. (Liesch) is submitting this letter and accompanying Conditional Use Permit (CUP) Application submittal package (the Application) on behalf of Roger Schmidt and Schmidt Gravel Mining (Schmidt Gravel) for the above referenced Property. Figure 1 shows the location of the Property and Figure 2 shows the Existing Conditions, as of May 2003. The following documents are included with this letter and complete the Application: 1. Completed CUP Application signed by the applicant, including the application fee of $500.00 and consultant retainer fee of$500.00; 2. Plan Sheet A: Mining Area Grading Plan, Mining Area Restoration Plan, and Cross Sections, prepared by Liesch Associates, Inc., dated March 26, 2004; 3. Storm Water Pollution Prevention Plan, Schmidt Gravel Mine, Elk River, Minnesota, prepared by Liesch Associates, Inc., dated May 2003 and revised March 2004; 4. Completed Part 1: Basic Application, Minnesota Local/State/Federal Application Form for Water/Wetland Projects, signed by the applicant; and 5. Labels for property owners within 350 feet of the Property. Background Information In May 2003, the Property was rezoned for mineral extraction and a CUP was granted for operation of a gravel mine consisting of three phases. The following documents relating to the Property and existing CUP have been submitted to, reviewed, and approved by the City of Elk River: • Environmental Assessment Worksheet, Schmidt Gravel Mine, Elk River, Minnesota, prepared by Liesch Associates, Inc., dated January 2003. • Storm Water Pollution Prevention Plan, Schmidt Gravel Mine, Elk River, Minnesota, prepared by Liesch Associates, Inc., dated April 2003. • Environmental Spill Plan, Schmidt Gravel Mine, Elk River, Minnesota, prepared by Liesch Associates, Inc., dated April 2003. Page 2 Mr. Steve Rohlf March 29, 2004 • Jurisdictional Wetland Identification and Wetland Delineation for Proposed Schmidt Gravel Mine, Elk River, Minnesota, prepared by Liesch Associates, Inc., dated May 2003. • Memo to file from Leon Zeug, Liesch Associates, Inc., RE: Sediment Pond Design, Schmidt Gravel, dated May 15, 2003. • Plan Sheet 1 of 2 — Existing Conditions, Property Boundary, Watershed Boundaries and Wetlands Map, and Plan Sheet 2 of 2 —Development Phasing Plan and Details, Schmidt Gravel Mine, Elk River, Minnesota, prepared by Liesch Associates, Inc., dated May 2003. Description of Protect Schmidt Gravel is proposing to mine an additional area, Phase 4. located on the eastern portion of the Property, east of Phase 1 (see Plan Sheet A). Phase 4 consists of approximately 5.5 acres. Approximately 94,000 cubic yards of material will be removed. Mining of Phase 4 is proposed to be conducted from Phase 1 to up to the boundary of the adjacent wetland Area E to the east. Two soil borings (1A and. 2A) were completed in the area of Phase 4 on November 19, 2003. The locations of the borings are indicated on Figure 2. The boring logs indicate that soils in that area of Phase 4 consist of poorly graded sand with silt and gravel. Water levels were measured at the time of drilling however; it is not believed that they represent the actual water level. The boring logs are attached to this letter. Mining is proposed to be conducted to 15 feet below the water table or to an elevation of approximately 933 feet. It is anticipated that Phase 4 will ultimately produce 3.5 acres of Type 5 wetland (see Plan Sheet A). In the process, two small wetlands, Area F(0.10 acres) and Area G (0.09 acres), as shown on Figure 2, are located within the proposed Phase 4 and would be removed. These wetlands are unregulated due to their small size. The perimeter of the newly created wetland will be properly seeded upon completion. Due to the elevation of the water table in the area of the project (approximately 948-950 feet, based on information provided in the Environmental Assessment Worksheet prepared for the Property) it is not believed that mining of Phase 4 will significantly impact wetland Area E, as Area E is expected to be a ground water influenced wetland (elevation approximately 948 feet). Upon completion of mining activities, it is anticipated that a natural transition between the boundary of wetland Area E and the newly created Class 5 wetland of Phase 4 will occur. A "Part 1: Basic Application, Minnesota Local/State/Federal Application Form for Water/Wetland Projects" as required by the City, is included with the Application. Mining below the water table will be conducted using a drag line. No dewatering will be conducted at the site at any time. Drainage from Phase 4 will be directed to the open hole during mining (see Plan Sheet A). The Property is currently operating under a National Pollutant Discharge Elimination System (NPDES) Permit MNG490000 and a Storm Water Pollution Prevention Plan (SWPPP) and will continue to do so during Phase 4 mining. As indicated in the SWPPP, surface water runoff and erosion controls are proposed to control surface water discharge off site. The proposed controls will include installation of silt fence/hay bales, rip-rap placement in drainageways, and phased topsoil replacement and seeding of completed phases. Silt fence/hay bales and rip-rap will be placed in areas deemed necessary during mining operations. The SWPPP has been updated to include Phase 4 and is included with the Application. THE LIESCH COMPANIES MINNEAPOLIS. MN MADISON, WI SCOTTSDALE, AZ Page 3 Mr. Steve Rohlf March 29, 2004 The mined material will be hauled to Elk River Bituminous located approximately 1/4-mile south of the Property using a private access road, as approved as part of the original CUP. Mining operations be conducted between the hours of 7:00 AM and 7:00 PM as required by the City of Elk River. All mitigative measures currently in place at the Property as part of the previous CUP for Phases 1-3, (i.e dust control, noise control, and spill prevention and response), will be followed as part of Phase 4 mining. If you have any questions or comments regarding the enclosed, please call me at (763) 489-3178 or Glen Johnson, Site Manager at (320) 252-8817. Thank you for your time and assistance with this project. Sincerely, LIESCH ASSOCIATES, INC. Jon Blaha Environmental Geologist Enclosures Cc: Roger Schmidt Glen Johnson John Lichter—Liesch w:\env\64480\CUP submittal Itr.032904.doc THE LIESCH COMPANIES MINNEAPOLIS, MN MADISON, WI SCOTTSDALE, AZ NATURAL RESOURCE GROUP, INC. MEMO TO: Steve Rohlf COMPANY: City of Elk River FROM: Matthew Ledvina, P.E. DATE: July 28, 2004 RE: Schuer, Inc./Schmidt Gravel Mine — Groundwater Monitoring Plan and Environmental Spill Plan Review NOTES/COMMENTS: As requested, I have reviewed the above referenced documents for the Schuer, Inc./Schmidt Gravel Mine. The following comments are provided in support of Conditional Use Permit (CUP) development for the Site. Groundwater Monitoring Plan Ground water elevations were measured in June and July 2004. An interpretation of the groundwater flow with a water table contour map should be provided from this data. The consistency of the groundwater level data should be assessed. The groundwater flow interpretation for the site should be assessed in relation to the regional hydrogeology. The monitoring schedule should identify that all three monitoring wells on the property be initially monitored for the listed parameters for two sampling events within a four week period to provide baseline of data for ongoing monitoring at the site. The annual groundwater sampling should include the sampling of, at a minimum, one of the upgradient wells in addition to MW-1. This will enable comparisons of water quality between upgradient and downgradient points at the site. Field parameters of pH, temperature and conductivity should be reported and interpreted with the analytic monitoring results for groundwater sampling. The City of Elk River should be notified ASAP if water quality monitoring data indicates the potential occurrence of environmental release. Water quality for groundwater sampling for the J&B monitoring should be incorporated into the assessment provided with the annual monitoring report. Environmental Spill Plan The Plan has been developed with an acceptable general outline. The existing SWPP should be reviewed and updated as necessary to reflect the Phase 4 mining • 0 0 0 0 MINNEAPOLIS HOUSTON DENVER PROVIDENCE ANCHORAGE 1000 IDS Center Suite 200 Tower One,Suite 580 Suite 2020 Key Bank Plaza,Suite 301 80 South Eighth Street 520 Post Oak Boulevard 1515 Arapahoe Street One Financial Plaza 601 W.Fifth Avenue Minneapolis, MN 55402 Houston,TX 77027 Denver,CO 80202 Providence, RI 02903 Anchorage,AK 99501 612.347.6789 432.203.1492 720.956.5300 401.278.4300 907.777.5300 Schuer, Inc./Schmidt Gravel Mine Page 2 activities. The Plan should state that there will be no maintenance of the equipment on the site. The Plan should identify to.contents and capacity of the spill kit that is provided with the refueling vehicle. A specific refueling location(s) should be identified in the Plan in an area(s)where spill response can be effectively implemented. The refueling location(s) would ideally be an area(s) with a relatively impermeable surface, closed contours and minimal slope. Q:W-C\CER\2004-511\Correspondence\ShuerReview.doc 2 M w-r[ee - 1.\.n.\e«eo\wc\frfFF*z or x A 2OO4 F . . 5 2 -.1:: ,6 `E 1:1"&F i"°b�j14\'1,r - . � � \1% "v .l� 1111 l\�qIA�,v \\v A 4:e a \vv� a Nl�h v el 1 r II'tI �l V� vv A 4 __—..—.._ // ,k"O \V �1 x; \ V 111 II},I II�,I 1,l. ` a F - I /� - Vv I`lllll��IiTiii i•• ili{I'��4��v �: d .-0 / . _ \\ �l ai)• - 11 (I' 1 1111 /iN 5 w /I `vim 1 \�AwA '°W �l ��yl �I� I��llH�iµ ���I�II)1�1 A - _ I' �(� l "vim VA\� ^Ktiw ,� /..�NfI11111111�1ui1�Ih1 ' e rn i. i 7 .--< _ / / `ii 11i1i1i11/1641i 111411Ii1� $ m n v �' i' iilj/11111 n1IIi�Ipllrlhd \ £ v n 'a . I zr" ` \\`y-\w \ \- / / ////// Itl"III III 1 -1 i t7 I °a / I \ \ \\`t';��c S�i ji%'/i �Illllljll�llllj c / 1 yq o . c I C a/% %i�r/% i///1%ii1U1�IIIIilOi � 9 Z a 1 ! \ • S ."s / /�/ / //III III ��, ri /// // / ll I I / J F - ._I_. _ ! 2 a //// //'v'i/i II i lfl\/11111 r I qv I E N �1 aa:_ -r -. v� G7 %, ' ,it I 1,0, �/ 9�H �4A 11 Y� /% `f /r l 1 1 II �C e' e I ,�\ 1,{1r } ��-� /,, /,/ ///i -911„\\1\,,„ 1 k \` 0 0 4 I/ N �?�a\ t< ^-�G` \ 1 / _�'d \IAyV� v�'�'A 1 ° l / D ��,><1. - 'r^.F i , - 1 ” p .R�• [{�,I 1,1 v v`'�n 01-- `�1..$; R \ _ __.- -m11is_.- \\ //itir \ \ ,��hh_"R z \$s\,H \\\ /{15}/'11'5.,.eL l�'I/I 1 O m � 11 - \ �.y:. .1 �AvAA �oMx$T x lip - Y v v `vv�1 / l li/J�ll - i 3 °, �� — z I A,v VA vv� / F I -S'1, - - z-i�pil I A tvy;y`���',_ v'ifib� "gtil L� q 81 o> I \ 1,1 II0 ( \ .y �A \�..� F= - g =i, `-� IT /;,�;�II_ y). ' `„�C �..� `� .1 <��11) �j y .C' \ \ \NIH/I) v° ' III # ft vvvv IvII� R' I \�2v�i-. g \. ! Nit RR` . I 111111 r 5 i \`\\\\a \`\`\\ \\.` - \ F �� \� el�r4nw.rrn R v-� f \ I / \ \ \ \ tr r Bev - - 22�, o '" 1 4 I1tp 11 / \i p��„��v�V v� 1\1 I • .1 e F F $ $ a 1 F $ A � .m \ ma$ IIA O�_ _ -Nr" 1 Jill A. ' / .1cc '1., Z v.2R 'Iv RR,, 0 ___ �� vv`11� �1A\��ryj 1��-.. 'a v ° -.42 I \,.,, N=8 I 3 �, ions lllmh, r 1k 4 11(11 v �.'' .. r�fifP r\. 2 "v; ¶* a/2a 1 /' fIi°NiI II!i�i1°il :�l',_ - � �1 T.� i 8 — - \� \` -C -_` / —5 00'15'43' E 85973-- -_, GS° I \ \�\: , � � $ ��_ �i/ r e.4yca Fue MFV.I sec. w 0C0A V�'', - g _ a ,, it T° > A i 9 pl ac a to �p $ e a\ �1�\`\\\\��\`\ f/A \ - - _ �z,�,"X'z�. \ \\ � \\\ O a f s I_-. _ 1 A ��✓/ ' ,: AX� ii111i1111 /// �.- - vv \�A✓ ,: - (/ iii F - €� / / j r �� M V 6p a 11 11111111 rya/////// AA 1h v ��,/ c , v �, vVIB- v 4 �v '*1' . 110 1111,1111 i i/1/111// .\\Vw� F I�9 >ia i:_� � .v"'V A AA *'C a • . III nII IIII 111�1p�� V• - 3 1 �AV� �yIII�I���II I11111i1 1111111/u/ AV� F y _� O --,- / , v \ V A4¢t 1 411 111111 1111110/ A A s A _. � - - 0 - 1v^' �A V , * �. Ti1111111111I111 blll II s 1, W "VAI wv 1 \ 1111 11111 411 iil�iiill �� o O m V �. / //// / I III 1 .- b V A / // l 1,/1, 1 111 1111 Wm z j i�V '\^ : V A _ d /,///////// 1 1111 IIilUI V A A - /////q///i//////,.y1I1111111111111 �m ti / \ ,////////////// III 11 I a.���'`� // / / /// //Igll 111111 I / ��: �i o I I A A18 / / //////////// //4111111111111 I �#[ / �o - -y. ///� /'/ / //11111 sn _ .r.. A �{ f'//�///i/�/i/i// ////IIIIIj11111/ 1 �� -n+z � -� f V A S'� -_ a /i , U/I/11 III 1A A 1� 1 ""� \ a //G //// l 1 � 4 1'ir �.' ] \ v A / /� ///// II 1 1 1 e __1 : v. /i:'/ /':ii�/ ulivvli�vllvwVv zA '! it °I - a-L \ r �/�//7%%'- I, ∎∎',V\ll... > I I l 00 .Z 0/ I IIII �_ _-� i a //iii!/i/iii i �IIIiJ glln / t !__-_ Z Z ``4.' .11,11 11-�_�= `--`- _ 211/i/i';%;0 11\4111\\\1\ 1 �r / - mz \\ \nIi 1111 _` //// ///// \a \\\\\\��\\\\�\ yc \ f,I11 _ _,±.-ti_-, 0 c \ / _J i - \� 1111 _ � / /71 �- \\\\\\\\\\\\\ - ,T\ \ 1 • zA - '1111`a i - c ;;_o:/G�/� / _ \\�\\\\\\\\ \ \ �� D 0z -• , y v �I I �!� 111411v11 `' "t�'<17,. N no /� .• •S• > ql II VI II I _ zo ...t.1•i••. I,.,y{ E- a 111111;;A ,1 ,1 qq '$. z i • /W •••• •••••• i 1111 1 n C I x p z r••mv�v ••a• '4 1 1 1 � 6 � __�� u 9 a z ' � w Yi••iiiiii••i•$iii• .. j b�� ////////� � " , �/ / $': In N zm p ••• •••••• •.• ,\,� o//////� m 1n x iA•• •• •••435 u•SS• IN///Un �' p ••• �i l/ll///l/nl (� / O c y " 1�i•i i••iiiiSSii�isi�p!•�i�Jy• ">ti �l m ///////////, /. / N y ° A4St•} i�i•Y•Yi%•►♦' ♦•.• \. \ /ll l/l/1111 ,. .Zl F� M O or a •lid • iiini�gilm _-_•;�V....� // // // -.. O a p7 1/ / -" y° / 0 d ••••• • .11111\ . 1 1 t \+// / i 1/1 / 9 �� O p v o p ••••ti c.c•••E• \ �:\r-- ���C\� � i/iii%• ///i/ii " . / S fn � I / 7 z r � �x �i•�ii iii��0►�• �` � \\ � � ��\ /// / /�/iu/ _' -/ (�� m 1 \ _ y i \ •••••u u ♦ \ \ \ I 1 1,l//U//iu//� (A 1� J z 5 a •••••• .S• T _-;y\ \\ ` \ \ \. . /11,1111 III,1111 / -\ \ � � m o iiiisie�} /4v�1 III 1111 III.. 1 II `\ �`y. t /!fll li/�/ II I !-`-..` n ��� Q n> �•S•NV4r;�� 1111y I \\\ M. I f III \11r1 ° m �� J O >r iitar,to, II I I III,,,,i, III 1/1%11 \`\\Y,`, ,\1111'---„44�T,1 1 1 1 1 11 1,m / ♦1` ��"1���� �I 0 o I 2 •s: •Y l�ljl ,I,I,I,I,IIUI l //�/, b r \.,,, t 1 ; / m N S z •• • 1 1 ♦ 1 ';illl vvv��� �v���I��il; � o 1 A••711/I 17 ♦'I / // a ��vv• �.yA V ilil 4 to - 'C` 3 I' ••• I/y1 ♦ ♦ 1, 1 1, III M VA;A,,,,A� 1 ,4.1,,V i-J m O 2 •11.11 }/1,k S 'mm41 IIII e, ., vwvv .Y A� \. 1v\�� O o > vR y ►♦ ♦ z1 VIII vv1p �. AA v� 111.1 qtl ♦ ♦♦ II 11 VAVVV�Yi\vAVA`A� ,11ir }.�. 1 �` z z _ I _.M \ NMI III 1111 I��� 1►♦►111 111\\I\ \\`�����``.\ \\!��1\ r) \- m+ m oy O '` '- •Sin 1111111 I►� ►►•J 11 I 1 \`C-__-- -- ,i / \\\,`'\ '0, 1113 1 ))rte\ m a z 1 1 \ \ : %�. \1111 111,m -m�Yl 1\ 1\ \__ _ \\ti \\ \\11\1 - \�.\� r- -- •• III I I► ♦♦ 1 \ t, \ ), O T r ♦�mN I I A A ��a �1 V 0 O 0 m ./� 4♦♦♦♦Y i AI 1 A w p � o AV 1 A� I I I 1 I �m♦�►m♦�♦�� I I I I I I I 1 1�A � 1 ` D v> �`Y't �1 I_... N ml 1,r 1 ►��***♦St.4∎ r 1, I'1,1 111 V I I I I I i IIII 1 r 11 P 1111�I \ \:v m m �y �r u° vl Zy AI�I 1 m♦i♦.♦�: 111111 11111 n'P 0411 11r 111 rI1 I \� 3 W t .2 11, I ��♦► �11•�♦♦��.111111 11111 �Q WF 1 1 r 1111111 11 �i 1 i�) �AA \� 1 I'' 111 1 MmG J ♦����♦ 1,r 1 III 1 1 1,1 N0: 1 , III/ I I�1I 1 ���� A� m .. I �.p R 'V A 1 11' A� 1 1 1, 1111 !V /�}t 1 A VA ))) ,m 5 1 � . 1� YI IIIIIIIIIIIII II A� . - �_- 4 D I Y 1 1 1 /. ' N I �V A . E - -�- 1. i6 B �T AV_m- 5 00'1643° E 859.73 n ,1,u\\V_1CA\ 2 W , , '� / /� 5 V A�� �.. T a, p / N > s g )%* of Memorandum akTO: Planning Commission River FROM: Rebecca Haug, Environmental Tech. 13065 Orono Parkway Elk River,MN 55330 DATE: August 24, 2004 SUBJECT: Wetland Conservation Act Decision — Schuer, Inc. -WCA 04-07 Proposal— Schuer, Inc. is proposing to impact 8,280 square feet of Type 2 wetland, all in one location, to accommodate the excavation of gravel. A map showing the proposed wetland impact and replacement is attached as part of the Planning Commission's memo on the Conditional Use Permit for this same request (see Development Plan). The Elk River City Council is the Local Unit of Government charged with decision- making authority for the Wetland Conservation Act (WCA). The wetland information has been provided to the Planning Commission so they have all relative information that may affect this project. Schuer, Inc. is proposing to expand a gravel mining operation adjacent to the J & B Mining site, which also has wetland impacts. The wetland restoration for the two projects ties together. Wetland restoration can't be deemed complete for either project until both are finished. Further, J & B Mining is purchasing some of the excess wetland credits from the Schuer site. FINDINGS Liesch Companies prepared a Wetland Delineation Report for the property. Combined notification of the proposed wetland impact and replacement plan was mailed out to the appropriate governmental agencies on June 2, 2004. The Technical Evaluation Panel (TEP) reviewed the delineation and replacement plan on May 5, 2004 and June 8, 2004. The minutes of these meetings are attached. The comment period on this issue ended on June 23, 2004. The appeal period for this issue is 15 working days after the Council's decision. RECOMMENDATION Staff recommends approval of the filling and mitigation plan for this project with the following stipulations: Phone: 763.635.1000 Fax:763.635.1090 www.ci.elk-riveunn.us 1. A restrictive covenant and drainage and utility easement be recorded over the mitigation and buffer areas. 2. The petitioner secures letter of credit in favor of the City of Elk River,which covers the cost of the mitigation work. 3. Monitoring of the wetland mitigation will commence as soon as restoration is completed on both this site and the Schuer, Inc. site and continue for a period of 3 to 5 years, as needed, as determined by city staff. The petitioner shall submit a written monitoring report on the replacement wetlands to the city after the first year of monitoring. Upon approval of this report by city staff the letter of wetland credit may be released. TEP Minutes — June 8, 2004 Attending: Brad Wozney, BWSR; Paul Diedrich, DNR-Fisheries; Yvonne Berner, ACOE; Terry Mauer, City Engineer; Roger Schmidt & Glen Johnson, Schmidt Gravel Mine; Jon Blaha and Warren Tuel, Liesch Assoc, Inc; Wayne Jacobson, Applied Environmental Services; Jason Bebeau & Michelle Christensen, J & B Mining; Donald Wester, Bill Saaranen, Duane Betker, Dean Mealhouse, Trout Brook Farms; Rebecca Haug and Steve Rohlf, City of Elk River Schuer Gravel Mine Leisch Assoc, Inc installed three monitoring wells and took soil borings. The information collected supports their earlier opinion that the wetlands at the site are supported by a shallow water table and not due to perched conditions. However, Bill Bronder is unsure if they have enough information to make that determination. It was discussed that the letter of credit guarantees that the wetland is supported by a shallow water table and not perched. If the plan doesn't work, the City will require them to fix it. Some of the additional wetland credits that this mine will have will be given to J & B Mining. Yvonne Berner explained that the ACOE may not accept these credits since they do not approve deep water habitats. It was discussed that there would be no dewatering at the site. The CUP for will need to be written in such a way to make sure the water levels are working. Monthly data for the monitoring wells will need to be provided to the City for the first year and quarterly data for the monitoring wells will need to be provided to the City for the second year. There may be a potential for bounce. Benchmarks will need to be established so a person can take elevations. GRO and DRO will need to be addressed. The wetland mitigation will be accomplished by removing the gravel deposits to a depth of 15 to 16 feet. Then fill will be brought back in up to grade in the Type 5 area, and 1 ft below the grade in the Type 3 area. Muck will be used to line the Type 3 area in preparation for planting. The second mitigation will be completed by removing the top 0.5 ft of existing reed canary grass and then replanting with natives. The slopes will be no greater than 5:1. A buffer area will be created averaging 25 ft in width. The Type 2 replacement is the only area that credit is wanted for. BWSR and ACOE are unsure they will be able to accept the credits because it is connected to deep water habitat. The TEP is satisfied with the wetland application for this project. J & B Mining Yvonne Berner emphasized to the applicant the importance of keeping their impacts under 2 acres. Also, the setbacks on the north, east and south sides for the mine will need to be changed. The setback adjoining the Schmidt mine may be already but the others will have to be 50 ft back. The setback changes will affect the wetland impacts so this will be looked at again at the next TEP meeting. There is still the issue of transportation for this project. Trott Brook Farms Homeowner's Association The Trott Brook Farms Homeowner's Association was in to discuss what can be done about the vegetation in and around their sedimentation ponds. It was discussed that barley straw can be added to the ponds in April to control the algae growth. It was also discussed that some of the cattails can be removed but the majority should remain because they absorb the nutrients that cause the algae bloom in the pond. It was also discussed that the association should talk to the lawn mowers about mowing the grass clippings away from the ponds. At this time, there are no rules restricting vegetation removal from sedimentation basis only recommendations. Bill Bronder gave them his card so they could further discuss options for vegetation. TEP Minutes — May 5, 2004 Attending: Paul Wozney, BWSR; Paul Diedrich, DNR-Fisheries; John Norgren, Sherburne County Ditch Inspector; Yvonne Berner & Marge Thompson, ACOE; Terry Mauer, City Engineer; Paul Cherne, Pioneer Engineering; Bill Blackwen, Pioneer Engineering; Roger Schmidt, Schmidt Gravel Mine; Jon Blaha and Warren Tuel, Liesch Assoc, Inc; Wayne Jacobson, Applied Environmental Services; Rebecca Haug and Steve Rohlf, City of Elk River Schuer Gravel Mine The applicant is proposing to mine gravel adjacent to an existing Type 2 wetland, which may or may not be a perched wetland. Liesch Assoc., Inc has been hired by the applicant to make this determination. They will be installing three monitoring wells. The applicant is proposing to restore the wetland and get credit for wetland banking. It was discussed as to whether or not the ACOE would approve a wetland bank for this type of project. Trout Brook Estates At the previous TEP meeting several changes were requested. The proposed trail at the end of Becker Trail has been relocated. Street has been shortened but the Park and Recreation Commission would like to see the trail to connect to Street E causing wetland impacts. Terry Mauer commented on the lack of accessibility to the sedimentation ponds by Outlot G. This will cause a change in Street E and the trail. Yvonne Berner stated that the ACOE is developing new criteria for trails. She also commented that if the project exceeds 10,000 sq. ft. (over 2 acres) of wetland impacts, the approval process will require a public notice and will be more difficult to receive approval. Lots 8 & 9, Block 20 were looked at since the City doesn't allow wetland fill for building sites. The road may be redesigned or the house made smaller to fit the sites. The same concerns were discussed for Lots 4 & 5, Block 15. A narrower house and retaining wall were discussed for Lot 9, Block 15. A new plan will be submitted; however, the TEP will not be discussing this project again. Robert Droen This homeowner is requesting a permit to dig out a wetland on his property and place the spoils on an upland area of his yard. ACOE does not regulate this activity. It was discussed that the slopes would be 4:1 and no deeper than 4 — 5'. (Bill Bronder and Rebecca Haug inspected the site on May 7, 2004. During the inspection it was determined that the wetland is a Type 2, 6 and he is exempt under WCA for his project.) CITY OF ELK RIVER AGREEMENT FOR ISSUANCE OF CONDITIONAL USE PERMIT FOR MINERAL EXCAVATION THIS AGREEMENT, made and entered into this day of , 2004, by and between the CITY OF ELK RIVER, a municipal corporation organized under the laws of the State of Minnesota (City), and Schuer, Inc., a Minnesota corporation, hereinafter referred to as (Operator); WITNESSETH: WHEREAS, Operator has made application to City for approval of a conditional use permit to operate a gravel mining operation within the City on property legally described as follows: The Northwest Quarter of the Northeast Quarter (NW 114 of NE 1/4), the North Half of the Northeast Quarter of the Northeast Quarter (N ' of NE 1/4 of NE '/s), and the North 200 feet of the South Half of the Northeast Quarter of the Northeast Quarter (N 200 ft. of S '/ of NE 1/4 of NE '/4), all in Section 10, Township 33, Range 26, Sherburne County, Minnesota. (the Property); and WHEREAS, the City of Elk River Planning Commission and City Council have held hearings on Operator's request for a conditional use permit, at which hearings all citizens of the City of Elk River and other interested parties have had the opportunity to be heard on the application; and WHEREAS, the City Council by motion adopted September 7, 2004, approved a conditional use permit for the operation of a gravel mining operation (the Operation) on the Property, subject to certain conditions, including that Operator enter into a conditional use permit agreement with City so as to fully comply with the City's Mineral Excavation, Zoning, and other applicable ordinances; and WHEREAS, the City's Zoning Ordinance requires that a conditional use permit be issued and that a conditional use permit agreement for mineral excavation be entered into. NOW, THEREFORE, in consideration of the premises and the mutual promises and conditions hereinafter contained, it is hereby agreed as follows: 1.) Entire Agreement- Except as otherwise provided herein, this Agreement shall constitute the Conditional Use Permit for the Property and, to be executed by City and Operator, shall govern the parties rights, responsibilities, and obligations with respect to the operation, subject to the compliance by all parties with applicable city ordinances and state and federal laws. 2.) Warranty of Operator- Operator hereby warrants and represents to the City, as inducement to the City's entering into this agreement, that the Operator is the fee owner of the subject property or has a valid lease for the operation and the fee owner of the subject property shall also enter into this agreement. 3.) Conditions-The following general conditions shall apply to the Operation: (01) This Conditional Use Permit authorizes mineral excavation (gravel) from the Property. (02) All mineral excavation and processing operations on the property shall comply with the City's Mineral Excavation, Zoning and other applicable ordinances; with the terms of this Conditional Use Permit agreement and the license agreement to be executed by the City and Operator; with the City of Elk River's Environmental Impact Statement on Mineral Excavation; and with the application materials and plans submitted by the Operator, which plans and materials are the basis for the City's approval of the Conditional Use Permit. (03) The Operator shall orally notify the City of any violations of this permit within 24 hours and follow this with notification in writing within four (4) working days of the violation. The Operator shall notify the City annually in writing of the total area and amount of material mined and projected estimates of area and amount of material to be mined in the following year. This is to be done at time of license renewal. (04) The license shall be renewed annually and shall run from June 1" through May 31". The annual license fee is that which is specified by the Elk River City Council at time of renewal. This license fee is not in lieu of gravel tax collected by the County, a portion of which the City receives. (05) Violations of this Conditional Use Permit may result in suspension or revocation. (06) The City Building and Environmental Administrator and/or his/her agents shall be permitted to inspect the Operation for compliance with the conditions of this permit during normal hours of operation. (07) The City's approval of this Conditional Use Permit is subject to the approval of appropriate permits by other governmental agencies. (08) No explosives shall be allowed for this operation. (09) Reclamation a. Reclamation shall be implemented on an annual basis pursuant to the reclamation plans submitted by the Operator. b. Each year a plan for that year's reclamation shall be approved by the Building and Environmental Administrator prior to issuance of the mineral excavation license. c. Upland reclamation shall include topsoil from the site being preserved and put back into place after mining and seeded as per the approved plans. The vegetation established for the reclamation must be maintained until it is self-sufficient. d. Wetland restoration shall be in compliance with the approved wetland mitigation plan. The Operator shall provide a letter of credit in favor of the City for wetland restoration in the amount of$ . A formal wetland monitoring plan shall be submitted for City approval one year after wetland restoration has been completed on the Property and the J & B Mining site. The wetland letter of credit may be released upon approval of the first year monitoring report, but monitoring shall continue for an additional 2 to 4 years after, as determined by city staff. e. Contours, finished grades, details of erosion control methods, and settling ponds, shall comply with the plans submitted and the City ordinance at the time of reclamation. Additional measure as determined by city staff may be required. (10) Traffic a. Material mined as part of this Operation shall be hauled directly to the Elk River Bituminous site via easements, not accessing any public road. Access to Highway 169 at 219th Avenue will be eliminated when frontage roads leading to interchanges are developed. b. All portions of drives shared by this Operation and another business or residence shall be a minimum of twenty feet wide and hard surfaced. The Operator shall provide the City with executed copies of all agreements concerning the ability to make improvements to these drives and their maintenance prior to the Operation commencing. c. The sale of product from the Operation shall only take place from the Elk River Bituminous site and then only after receiving authorization from the Minnesota Department of Transportation and completing all required improvements to the access for that site prior to commencing said sales. (11) Dust Control a. A permit from MPCA regarding air emissions shall be obtained when required and particulate emission standards shall be met by the Operation. This permit and all other correspondence between the Operator and MPCA shall be copied to the City. b. All equipment shall be located as to reduce dust to adjacent • properties. c. A water truck shall be on site at all times when mining activities are taking place to control dust as necessary. Chemicals shall not be use for dust control. d. The City reserves the right to require additional measures to be taken, if warranted by dust problems, including but not limited to reducing stock pile heights. (12) Hours of Operation All mineral excavation, processing, and sales activities shall be conducted between the normal hours of 7:00 a.m. to 7:00 p.m., Monday through Saturday, except the hours may be extended by the Building and Environmental Administrator for special cases. (13) Noise a. As deemed necessary by city staff, noise from screening and crushing associated with this Operation shall be controlled by equipment location on site, the erection of sound barriers, the placement of stockpiles, and the type of equipment used. b. Noise levels associated with this Operation shall at no time exceed State standards. c. The City reserves the right to require additional measures be taken, if warranted by noise. (14) Lighting Lighting from the Operation shall be directed away from adjacent residential property. Glare, whether directed or reflected as different from general illumination, shall not be visible beyond the limits of the immediate site. All sources of artificial light shall be so fixed, directed, designed, or sized that the minimum subtotal of their illumination shall not increase the level of the illumination on nearby residential property by more than .1 foot candles in or within twenty-five (25) feet of a dwelling, or more than .5 foot candles on any part of the adjacent property. (15) Debris The piling, storing, or keeping of old machinery, junk, debris, or abandoned motor vehicles, shall be prohibited on this site, with the exception that reusable parts may be stored on the mineral excavation site provided that it is in a location that cannot be viewed from adjacent properties or is totally screened. (16) Vibration Mining activities shall not cause excessive vibration off site. If excessive vibration becomes an issue, the City reserves the right to take appropriate measures to alleviate the problem. (17) Groundwater Protection Measures • a. The Operator shall file with the City an Environmental Spill Plan and a Storm Water Pollution Prevention Plan. The Operator shall adhere to these plans in the event there is a spill. b. The Operator shall provide the Fire Department with a copy of their flammable or hazardous materials. c. Refueling shall take place only at designated locations. d. All incidences that have the potential to adversely affect groundwater, including but not limited to spills, shall be verbally reported to the City within 24 hours. This verbal notification shall be followed up in writing within four (4) working days. e. The appropriate storm water permits (NPDES) shall be obtained by the Operator from MPCA and copied to the City. f. Prior to commencing mining, the monitoring well located at the site shall be monitored for diesel range organics (DRO), pH, temperature and conductivity to establish baseline data. The reference parameters shall be monitored a minimum of once each mining season thereafter. In the event of a spill, the City may require additional testing events, parameters and monitoring wells, as well as the cessation of operations until the spill is deemed clean by the City. g. Gravel washing operations are prohibited at this site and will require an amendment to this permit to be allowed in the future. h. Except for minor repairs, maintenance of vehicles and equipment shall take place in the shop at the Elk River Bituminous site.. The Operator shall have an approved hazardous waste license for this facility and properly dispose of all waste. i. Temporary sedimentation ponds, as indicated on the plans submitted, shall be constructed and maintained until deemed to be no longer necessary by City staff. j. The Operator shall provide the City updated groundwater data as it becomes available. k. The proposed wetland restoration plan is based on the premise that the groundwater level incurred is not a perch water table. If information to the contrary is discovered, the Operation shall cease until new mining and restoration plans are submitted and approved by the City. (18) Signage Signage for the operation shall be that which is permitted for an industrial operation in a medium industrial zone, with the exception that billboards are not allowed. (19) Fencing All cut faces with slopes greater than 3 to 1 shall be fenced on the high sides to provide a clear warning of the potential danger until properly sloped. (20) Oakwilt Cutting of trees between April 15 and July 15 is prohibited. The Operator shall take other measures deemed appropriate by the Sherburne County Forester to control oakwilt, such as, but not limited to: debarking or destroying fallen diseased trees prior to April 15th, not leaving roots exposed and avoiding mechanical damage on remaining trees. (21) Blanding's Turtles Department of Natural Resources flyers with an illustration of a Blanding's Turtle shall be distributed to all site workers. If observed, turtles in imminent danger shall be removed to a safe location and turtles not in danger shall be left undisturbed. All construction areas shall be surrounded by silt fence to keep turtles from entering and no wetlands shall be altered as a result of the work authorized in this permit. (22) Other Permits The Operator shall obtain all state and federal permits appropriate to their operation and file copies of said permits with the City. 4.) General Provisions- (01) Permits- Operator agrees to comply with all of the provisions hereof and agrees to save and hold the City harmless from any and all claims or actions arising from the operations of the Operator on the Property. (02) Binding Effect- The terms and provisions hereof shall be binding upon, and inure to the benefit of the hens, representatives, successors, and assigns of the parties hereto and shall be binding upon all future owners of all or any part of the Operation and shall be deemed covenants running with the land. This Agreement shall be placed of record so as to give notice hereof to subsequent purchasers and encumbrances of all or any part of the Property, and all recording fees, if any, shall be paid by the Operator. (03) Severable- In the event that any portion of this Agreement shall be held invalid for any reason, the same shall not affect in any respect whatsoever the validity of the remainder of this Agreement. (04) Waiver- Any waiver, whether express or implied, by any party of a breach of any provision of this Agreement will not operate as or be construed to be a waiver of any subsequent breach of this Agreement. (05) Notices- All notices and demands specified herein shall be deemed appropriately and timely given when delivered personally or deposited in the United States mail to the addresses hereinafter set forth by certified mail (return receipt requested). The addresses of the parties hereto are as follows until changed by written notice given as above: If to the City at: City of Elk River ATTN: Building& Environmental Adm. 13065 Orono Parkway Elk River,Minnesota 55330 If to the Operator at: Schuer, Inc. Elk River Bituminous ATTN: Glenn Johnson 1200—29th Ave. NE Sauk Rapids, Minnesota 56379 (06) Incorporation by Reference- All plans, special provisions, proposals and specifications, submitted pursuant to this Agreement shall be and hereby are made a part of this Agreement by reference as fully as if set forth herein in full. IN WITNESS WHEREOF, the City and Operator have caused this Agreement to be duly executed on the day and year first above written. CITY OF ELK RIVER OPERATOR/FEE OWNER: Schuer, Inc. By: By: Its: Mayor Its: By: Its: City Clerk STATE OF MINNESOTA ss. COUNTY OF SHERBURNE The foregoing instrument was acknowledged before me this day of , 2004, by Stephanie A. Klinzing, the Mayor of THE CITY OF ELK RIVER, a Minnesota municipal corporation, on behalf of the corporation. Notary Public STATE OF MINNESOTA ss. COUNTY OF SHERBURNE The foregoing instrument was acknowledged before me this day of , 2004, by Joan Schmidt, City Clerk of THE CITY OF ELK RIVER, a Minnesota municipal corporation, on behalf of the corporation. Notary Public STATE OF MINNESOTA ss. COUNTY OF The foregoing instrument was acknowledged before me this day of , 2004, by , the of Schuer, Inc., a Minnesota corporation, on behalf of the corporation, fee owner of a portion of the subject property and Operator on the subject property. Notary Public This instrument was drafted by: City of Elk River Building and Environmental Dept. 13065 Orono Parkway Elk River,MN 55330