8.2. SR 12-16-2013 City of
Elk=' Request for Action
River
To Item Number
Mayor and Council 8.2
Agenda Section Meeting Date Prepared by
General Business December 16, 2013 Tim Simon, Finance Director
Item Description Reviewed by
2014-2018 Capital Improvement Plan Cal Portner, City Administrator
Reviewed by
Action Requested
Approve by motion the adoption of the 2014-2018 Capital Improvement Plan (CIP).
Background/Discussion
Over the past several months, city staff and the Council have reviewed the proposed 2014-2018 CIP.
During work sessions,we reviewed the costs, funding sources, cash flow analysis (5-year projections), and
the general purpose of the projects. The CIP is a revolving document that is re-evaluated on an annual
basis;upon each annual update some projects will be deleted,added, or even delayed,reflecting
community needs and financial ability to fund the project. The CIP is a long-term planning tool and all
purchases over$50,000 will come back to Council for approval per our financial management policies.
This update to the CIP does continue to address the beautification goal with monument signs and
boulevard improvements. In addition,the mining plan and park master plan updates are planned
Two projects that will be discussed further in the future CIP updates are the Ice Arena and Pinewood
Clubhouse projects. Both items are under review by the Park and Recreation Director.
One project planned for 2017 was Natures Edge Business Center Phase II. The Community Operations
and Development Department would like to move that up to 2014. The Economic Development
Director will review the project in work session following the meeting. See page 24 of the CIP document
for layout and funding sources.
City Administration staff recently went out for request for proposals regarding way-finding signage and
will also review with Council in work session. See page 5 of the CIP document.
Financial Impact
See various funding sources identified in the 2014-2018 CIP.
Attachments
■ 2014-2018 Capital Improvement Plan
■ 2014 equipment listing purchases (funded out of Equipment Replacement Fund)
■ Summary of capital outlay requests below$25,000
P a w E A E U s r
NaA f RE]
City of
CAPITAL IMPROVEMENT PLAN
P+6
2014 - 2018
City Of Elk River
CAPITAL IMPROVEMENT PLAN
2014-2018
Enclosed is the City of Elk River's Capital Improvement Plan (CIP) for the years 2014-
2018. The document has been prepared for the City Council and Community to
anticipate major expenditures in advance of the year they may become budget requests.
The CIP is a planning tool that forecasts the City's capital needs over a five-year period
based on the City's long-range plans, goals, and policies. City staff estimates the amount
of funding that is needed for projects to be completed in the next five years. Projects
listed in the first year are included in the budget and upon each annual update of the CIP
some projects will be deleted, added, or even delayed reflecting community needs and
financial ability to fund the project.
Approval of the CIP by Council does not authorize spending or initiation of a given
project nor allocate funding for any of the projects; it simply states that the Council's
support and acknowledgement of the Capital Improvement Plan as a planning tool.
Capital improvements to streets, parks, buildings, equipment, software, and vehicles are
included in the CIP. This plan shows the estimated project costs and the anticipated
funding source. Specific information is shown on each project within this document.
The CIP does not put specific designation on the priority of the projects. This uniqueness
of the type of project generally is associated with a funding source. Cash flow estimates
are done frequently to review cash reserve levels associated with the project funds.
City of Elk River, Minnesota
Capital Improvement Plan
2014 thm 2018
PROJECTS BY FUNDING SOURCE
Source Project# Priority 2014 2015 2016 2017 2018 Total
Capital Outlay Reserve
Vehicle extrication equipment FD-09 n/a 26,000 26,000
Annual Technology Upgrades TC-01 n/a 135,500 207,500 72,000 175,000 590,000
Capital Outlay Reserve Total 161,500 207,500 72,000 175,000 616,000
City Development Fund
Citywide Wayfinding Plan AD-05 n/a 65,000 65,000
Phase II Natures Edge Business Center 11-41 n/a 100,000 100,000
City Development Fund Total 165,000 165,000
City Wide Trunk Utilities
Mining Study Plan-01 n/a 40,000 40.000
City Wide Trunk Utilities Total 40,000 40,000
Donors
Oak Knoll Lighting Project OK-13 n/a 43,000 10,000 10,000 10,000 73.000
Donors Total 43,000 10,000 10,000 10,000 73,000
Economic Development Authority
Phase II Natures Edge Business Center 11-41 n/a 300,000 300,000
Economic Development Authority Total 300,000 300,000
Equipment Re lacement Fund
Pinewood Equipment Replacement 101 n/a 18,200 82,200 52,200 25,200 18,000 195,800
Vehicle Replacement BZ-01 n/a 27,500 27,500 27,500 27,500 110,000
Vehicle replacement CH-04 n/a 7,000 7,000
Vehicle replacement Eng-1 n/a 25,000 25,000
Vehicle Replacement FD-01 n/a 40,000 25,000 45,000 45,000 155,000
Fire Truck Replacement-Grass Rigs FD-02 n/a 50,000 50,000
Fire Truck Replacement-Engines FD-03 n/a 500,000 500,000
Fire Truck Replacement-Other FD-05 n/a 235,000 235,000
Marked Squad Replacement&Additions PD-01 n/a 108,000 108,000 72,000 108,000 72,000 468,000
Unmarked Squad Replacement&Additions PD-02 n/a 35,000 50,000 50,000 50,000 185,000
CSO Vehicle Replacement&Additions PD-03 n/a 35,000 35,000 70,000
Police Department-Other Equipment PD-04 n/a 9,000 12,000 12,000 33,000
Special Operation Truck PD-07 n/a 40,000 40,000
2014 Park Maintenance Equipment PK-14 n/a 164,900 164,900
2015 Park Maintenance Equipment PK-15 n/a 134,800 134,800
2014-2018 CAPITAL IMPROVEMENT PLAN Page 1
Source Project# Priority 2014 2015 2016 2017 2018 Total
2016 Park Maintenance Equipment PK-16 n/a 236,600 236,600
2017 Park Maintenance Equipment PK-17 n/a 193,200 193,200
2018 Park Maintenance Equipment PK-18 n/a 169,000 169,000
Vehicle Replacement-pickuptrucks ST-01 n/a 28,000 101,000 129,000
Dump Truck Replacement ST-02 n/a 205,000 205,000 410,000
Heavy Equipment Replacement ST-03 n/a 343,000 343,000
Other Equipment Replacement ST-04 n/a 77,750 65,000 26,550 11,550 180,850
Equipment Replacement Fund Total 983,350 511,500 584,850 1,253,900 701,550 4,035,150
Federal Grants
Eastern Area Trail&Mobility Imp. 11-32 n/a 320;000 320.000
Federal Grants Total 320,000 320,000
Government Buildings Reserve
Activity Center BL-07 n/a 226,557 11,040 237,597
Fire Station#1 projects BL-11 n/a 48,000 48,000
Public Safety Building maintenance PS-03 n/a 155,000 33,122 287,170 475,292
Annual Sealcoat Program SC-03 n/a 15,000 15,000 15,000 15,000 15,000 75,000
Government Buildings Reserve Total 241,557 218,000 59,162 15,000 302,170 835,889
Ice Arena
Ice Arena Equipment IA-01 n/a 120,000 120,000
Ice Arena Major Building Repair IA-02 n/a 343,950 343,950
Ice Arena Total 343,950 120,000 463,950
Li uor Fund
Northbound Building Maintenance LS-01 n/a 100,000 100,000
Liquor store fiber optics LS-03 n/a 42,000 42,000
Oak Knoll Lighting Project OK-13 n/a 62,000 62,000
Liquor Fund Total 104,000 100,000 204,000
Municipal State Aid
Pavement Management Program PM-01 n/a 2,500,000 1,000,000 3,500,000
Annual Sealcoat Program SC-03 n/a 291,721 297,555 303,506 309,576 315,768 1,518,126
Signalization of 193rd Avenue&Evans Street ST-12 n/a 250,000 250,000
Municipal State Aid Total 291,721 2,797,555 303,506 1,309,576 565,768 5,268,126
Park Improvement Fund
2014 park improvement projects PIF-14 n/a 276,000 276,000
2015 park improvement projects PIF-15 n/a 274,500 274,500
2016 park improvement projects PIF-16 n/a 268;000 268,000
2017 park improvement projects PIF-17 n/a 143,000 143,000
2018 park improvement projects PIF-18 n/a 143;000 143,000
Park Improvement Fund Total 276,000 274,500 268,000 143,000 143,000 1,104,500
2014-2018 CAPITAL IMPROVEMENT PLAN Page 2
Source Project# Priority 2014 2015 2016 2017 2018 Total
Pavement Management Fund
Pavement Management Program PM-01 n/a 1,350,000 3,180,000 4,530,000
Annual Sealcoat Program SC-03 n/a 72,929 52,644 75,876 71,692 61,388 334,529
Pavement Management Fund Total 72,929 1,402,644 75,876 3,251,692 61,388 4,864,529
Sewer Fund
Lift Station Rehabilitation WW-02 n/a 50,000 60,000 60,000 170,000
Jet(Vacuum truck WW-03 n/a 400,000 400,000
Vehicle Replacement WW-06 n/a 30,000 70,000 35,000 135,000
Replace Generators WW-15 n/a 110,000 110,000
Plant Expansion Master Plan WW-17 n/a 3,000,000 3,000,000
Sewer Fund Total 3,050,000 430,000 130,000 110,000 95,000 3,815,000
State grants
Phase II Natures Edge Business Center II-41 n/a 500,000 500,000
Plant Expansion Master Plan WW-17 n/a 3,000,000 3,000,000
State grants Total 3,500,000 3,500,000
Storm Sewer
Pavement Management Program PM-01 n/a 150;000 150,000 300,000
Storm Sewer Total 150,000 150,000 300,000
Street Improvement Reserve
Intersection Enhancements 11-00 n/a 150,000 100,000 250,000
Eastern Area Trail&Mobility Imp. 11-32 n/a 80,000 80,000
Intersection Improvements 11-33 n/a 60,000 30,000 30;000 30,000 150,000
Monument Signs 11-34 n/a 40,000 40,000 40,000 120,000
Boulevard Improvements 11-35 n/a 100,000 80,000 180,000
Quiet Zones QZ n/a 500,000 500,000
Signal Light Painting SL-09 n/a 12;000 12,000
Street Improvement Reserve Total 750,000 250,000 142,000 150,000 1,292,000
Trunk Utility Fund
Well#7 Filter 11-38 n/a 300,000 300,000
Proctor Ave water main 11-39 n/a 250,000 250,000
Highland Ave.Water Main 11-40 n/a 150,000 150,000
Phase II Natures Edge Business Center 11-41 n/a 400,000 400,000
Plant Expansion Master Plan WW-17 n/a 1,000,000 1,000,000
Trunk Utility Fund Total 1,700,000 400,000 2,100,000
lUtility Revenue Bonds
Plant Expansion Master Plan WW-17 n/a 5,619,000 5,619,000
Utility Revenue Bonds Total 5,619,000 5,619,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 3
Source Project# Priority 2014 2015 2016 2017 2018 Total
GRAND TOTAL 17,642,007 6,671,699 1,765,394 6,793,168 2,043,876 34,916,144
2014-2018 CAPITAL IMPROVEMENT PLAN Page 4
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# WY-02
Project Name Citywide dvayfinding Plan
Type Study Department Administration
Useful Life 20 years Contact City Clerk
Category city-wide development Priority n/a
Description
Adopt a comprehensive and consistent citywide plan to create a cohesive wayfinding and signage experience.
Justification
Currently,there are multiple types of signage located around the city that have little consistency. Staff does not have full expertise in design,
signage laws,and grant finding for this type of project. Consultant will provide the staff not only with design,but also plans,specifications and
knowledge to implement and maintain a comprehensive wayfinding project into the future.
Expenditures 2014 2015 2016 2017 2018 Total
Planning/Design 65,000 65,000
Total 65,000 65,000
Funding Sources 2014 2015 2016 2017 2018 Total
City Development Fund 65,000 65,000
Total 65,000 65,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 5
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# BZ-01
Project Name Vehicle Replacement
Type Vehicle Department Building&Environmental
Useful Life 10 years Contact Building&Env.Admin.
Category Vehicles Priority n/a
Description
Replacement vehicles for building inspectors/code enforcement/enviromnental division based on 10 year useful life,mileage and general condition.
2014-2003 Chevy Tahoe(Transferred in 2012 from the Fire Department)
2015-2001 Chevy pickup
2016-2004 Ford Explorer
2017-2005 Ford Explorer
Justification
The building safety department is looking at replacing the vehicle with a hybrid/smaller SUV type replacement. The 2014 vehicle replacement is
the 2003 Chevy Tahoe which was transferred from Fire in 2012.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 27,500 27,500 27,500 27,500 110,000
Total 27,500 27,500 27,500 27,500 110,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 27,500 27,500 27,500 27,500 110,000
Total 27,500 27,500 27,500 27,500 110,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 6
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# CH-04
Project Name Vehicle replacement
Type Vehicle Department City Hail Maintenance
Useful Life 15 years Contact Building Maintenance Supv.
Category Vehicles Priority n/a
Description
Replace John Deere Gator
Justification
The Gator is used for many building maintenance activities in the winter and summer months.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 7,000 7,000
Total 7,000 7,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 7,000 7,000
Total 7,000 7,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 7
Capital Improvement Plan 2014 thru 2018
City of Ells River, Minnesota
Project#
Eng-1
Project Name Vehicle replacement
Type Vehicle Department Engineering
Useful Life Unassigned Contact Engineer .
Category Vehicles Priority n/a
a
Description
Replace 2008 Dodge Nitro
Justification
Annual replacement of engineering equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2015 Total
Vehicles 25,000 25,000
Total 25,000 25,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 25,000 25,000
Total 25,000 25,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 8
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# FD-01
Project Name Vehicle Replacement w
Type Vehicle Department Firer
Useful Life 9 years Contact Fire Chiefs
Category Vehicles Priority r>/a
Description
Replace inspector vehicles as follows:
2014-New addition-Chevy Tahoe(pending deputy position hire)
2015-Fire prevention pickup(2001 F350)
2016-Duty Officer/command vehicle(2005 Ford Expedition)
2017-Inspector 2(2006 Ford Explorer)
Justification
Fire Prevention Truck originally received on a FEMA grant to be used with the FEMA trailer. Replacement truck will be more of a multi-purpose
vehicle.
2014 Chevy Tahoe for Fire Chief and 2012 Chevy Tahoe transferred to Deputy Fire Chief pending position approval.
Duty Officer vehicle is the primary response vehicle and first on the scene to assess the additional vehicles to follow. This vehicle will be 11
years old in 2016.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 40,000 25,000 45,000 45,000 155,000
Total 40,000 25,000 45,000 45,000 155,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 40,000 25,000 45,000 45,000 155,000
Total 40,000 25,000 45,000 45,000 155,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 9
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# FD-02
Project Name fire Truck Replacement- Grass Rigs
Type Equipment Department Fire
Useful Life 15 years Contact Fire Chief
Category Vehicles Priority n/a
Description
Grass Rig replacements as follows:
2018-Grass Rig 2(1988 Ford F350)
Justification
The grass rigs are 4X4 1-ton vehicles that are used during emergency response for various responses besides grass fires. The emergency response
and safety become a factor during the expected life of the vehicles.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 50,000 50,000
Total 50,000 50,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 50,000 50,000
Total 50,000 50,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 10
Capital Improvement Plan 2014 thru 2018
City of Elk Diver, Minnesota
Project# FD-03 ;
Project Name Fire Truck Replacement-Engines
Type Vehicle Department Fire
Useful Life 20 years Contact Fire Chief
Category Vehicles Priority n/a I
Y�
Description
Fire Engine replacements as follows:
2017-1997 Engine 1
Justification
Primary front-line response unit out of Station#I
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 500,D00 500,000
Total 500,000 500,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 500,000 500,000
Total 500,000 500,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 11
Capital Improvement Plan 2014 thm 2018
City of Ells Diver, Minnesota
Project# FD-05
Projeet name )Fire Truck Replacement- Other
Type Vehicle Department Fire a _
Useful Life 25 years Contact Fire Chief
Category Vehicles Priority n/a ,�
µ' i
ffi
Description
Other Fire Truck replacement as follows:
2014- 1990 Aerial Ladder/platform truck(refurbishment)
Justification
As the only aerial ladder in the fire department's fleet,it is an essential resource utilized at commercial and large residential fires in addition to
technical rescue incidents. The established replacement cycle of 25 years takes into consideration the vehicles typical usage and age,which after
25 years is requiring more regular and costly service.Advancements in aerial technology have also made newer model vehicles safer and more
versatile to better meet the needs of today's fire service.
The Fire department recommends refurbishing the vehicle to extend the life cycle another 10 plus years based on existing condition/inspection of
the current aerial ladder.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 235,000 235,000
Total 235,000 235,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 235,000 235,000
Total 235,000 235,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 12
Capital Improvement Plan 2014 thru 201
City of Elk River, Minnesota
Project# FD-09
Project Name vehicle extrication equipment
Type Equipment Department Fire
Useful Life Unassigned Contact Fire Chief
Category Equipment Priority n/a
Description
Upgrade vehicle extrication equipment
Justification
Continue replacement of hydraulic rescue equipment. In 2010,the equipment on Rescue 1 was upgraded. In 2013,the upgrade equipment was
on Engine 3. The goal for 2014 is to continue to replace old extrication equipment on fi•ont-line apparatus.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 26,000 26,000
Total 26,000 26,000
Funding Sources 2014 2015 2016 2017 2018 Total
Capital Outlay Reserve 26,000 26,000
Total 26,000 26,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 13
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# IA-01
Project Name lee Arena Equipment
Type Equipment Department Ice Arena ,-
Useful Life 10 years Contact Park&Rec.Director
Category Equipment Priority n/a
Description
2016- 1999 Electric Ice Resurfacer
Justification
The existing electric machine was purchased in 1999 and will have over 5,000 hours of use on it.By establishing an ice resurfacer replacement
plan the Arena will operate smoothly without unexpected problems arising.
Expenditures 2014 2015 2016 2017 2015 Total
Equipment 120,000 120,000
Total 120,000 120,000
Funding Sources 2014 2015 2016 2017 2018 Total
Ice Arena 120,000 120,000
Total 120,000 120,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 14
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# IA-02
Project Name lee Arena Major Building Repair
Type Building Department Ice Arena
Useful Life 20 years Contact Ice Arena Manager
Category Building Maintenance Priority n/a
Description
2014 projects include:
Replace Barn roof($117,000)
Front entrance doors($12,350)
Barn dehumidifier($185,400)
Vertical cracks to Olympic precast($16,200)
Electronic Air Quality Monitor($13,000)
Justification
The Barn's roof was installed in the early 70's and is well past its life expectancy. The arena is starting to experience several leaks on the south
end.
The interior of the Barn structure will continue to deteriorate without a dehumidifier that is sized correctly for the Barn.
Many of these projects will be prioritized based on a future facility study.
Expenditures 2014 2015 2016 2017 2018 Total
Building Maintenance 343,950 343,950
Total 343,950 343,950
Funding Sources 2014 2015 2016 2017 2018 Total
Ice Arena 343,950 343,950
Total 343,950 343,950
2014-2018 CAPITAL IMPRO VEMENTPLAN Page 15
Capital Improvement Plan 2014 thr^u 2018
City of Elk River, Minnesota
Project# II-00
Project Name Intersection Enhancements
Type Infrastructure Department Infrastructure Improvements
Useful Life 25 years Contact Engineer
Category Street Construction Priority n/a
Description
Complete enhancements of underperforming intersections within the City of Elk River. Improvements will be considered on a yearly basis and
may include costs for right-of-way acquisition and construction of intersection enhancements. Such enhancements may include the extension or
addition of turn lanes,restriping,modifications of medians,or drainage.
2014 Project:
Left turn arrows @ Proctor&CSAH I
Main/Parrish hitersection
Flashing stop signs@ Highland Road&Proctor
Justification
These proposed enhancement projects are relatively small in size and cost for the benefit they will provide to the overall transportation system.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 150,000 100,000 250,000
Total 150,000 100,000 250,000
Funding Sources 2014 2015 2016 2017 2015 Total
Street Improvement Reserve 150,000 100,000 250,000
Total 150,000 100,000 250,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 16
Capital Improvement Plan 2014 thru 2018
City of Elk Diver, Minnesota
Project# II-32
Project Name Eastern Area Trail &Mobility Imp.
Type Infrastructure Department Infrastructure Improvements
Useful Life 15 years Contact Engineer
Category Trail Improvements Priority n/a
Description
Construct the missing pieces of trail along the east side of Twin Lakes Road from the Northstar commuter rail station to Trott Brook Parkway.
Also provide ADA compliant sidewalks and pedestrian ramps along Line Avenue from Main Street to 3rd Street.
Justification
This trail/sidewalk project will provide safe connectivity of our existing off street trail and sidewalk systems in the area.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 400,000 400,000
Total 400,000 400,000
Funding Sources 2014 2015 2016 2017 2018 Total
Federal Grants 320,000 320,000
Street Improvement Reserve 80,000 80,000
Total 400,000 400,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 17
Capital Improvement flan 2014 airu 2018
City of Elk River, Minnesota
Project# II-33
Project Name Intersection Improvements
Type Improvement Department Infrastructure Improvements
Useful Life 15 years Contact Planning Manager
Category Landscaping/Boulevards Priority n/a
Description
Improve major intersection with landscaping
Justification
Beautification of School/169,Jackson/169,Proctor/10,Main/10,and 171st/10 intersections
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 60,000 30,000 30,000 30,000 150,000
Total 60,000 30,000 30,000 30,000 150,000
Funding Sources 2014 2015 2016 2017 2018 Total
Street Improvement Reserve 60,000 30,000 30,000 30,000 150,000
Total 60,000 30,000 30,000 30,000 150,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 18
Capital Improvement flan 2014 thru 2018
City of Elk Diver, Minnesota
Project# 11-34
Project Name Monument Signs
Type Improvement Department Infrastructure Improvements
Useful Life 25 years Contact Planning Manager
Category Landscaping/Boulevards Priority n/a
Description
Add entrance monument signs at southbound 169,westbound 10,and northbound 169/101
Justification
Beautification goal:
add large monument signs at city entrances to satisfy beautification goals.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 40,000 40,000 40,000 120,000
Total 40,000 40,000 40,000 120,000
Funding Sources 2014 2015 2016 2017 2018 Total
Street Improvement Reserve 40,000 40,000 40,000 120,000
Total 40,000 40,000 40,000 120,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 19
Capital Improvement flan 2014 thru 2018
City of Elk Diver, Minnesota
Project# II-35
Project Name Boulevard Improvements
Type Improvement Department Infrastructure Improvements
Useful Life 15 years Contact Planning Manager
Category Landscaping/Boulevards Priority n/a
Description
To achieve beautification goal for boulevard improvements
Justification
Several improvements to existing boulevards are planned:
Twin Lakes Road(north of 171st)
193rd(west of County Road 13,east of Xavier)
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 100,000 80,000 180,000
Total 100,000 80,000 180,000
Funding Sources 2014 2015 2016 2017 2018 Total
Street Improvement Reserve 100,000 80,000 180,000
Total 100,000 80,000 180,000
2014-2018 CAPITAL IMPROVEt14ENTPLAN Page 20
Capital Improvement Plan 2014 thru 2018
City of Ells Diver, Minnesota
Project# II-38
Project Name Well#7 Filter
Type Infrastructure Department Infrastructure Improvements
Useful Life 20 years Contact Engineer
Category Street&Utility Construction Priority n/a
Description
Add new water main connecting the well#7 filter plant to water main at Co.Rd. 12.
Justification
This project will direct water to the south including Nature's Edge Business Park increasing system capacity.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 300,000 300,000
Total 300,000 300,000
Funding Sources 2014 2015 2016 2017 2018 Total
Trunk Utility Fund 300,000 300,000
Total 300,000 300,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 21
Capital Improvement Plan 2014 rhru 2018
City of Elk Diver, Minnesota
Project# 11-39
Project Name proctor Ave water main
Type hifrastiucture Department Infrastructure Improvements
Useful Life 20 years Contact Engineer
Category Street&Utility Construction Priority n/a
Description
Add new water main connecting Highland Road to Proctor Ave near the public works building.
Justification
Increase system capacity to the north.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 250,000 250,000
Total 250,000 250,000
Funding Sources 2014 2015 2016 2017 2018 Total
Trunk Utility Fund 250,000 250,000
Total 250,000 250,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 22
Capital Improvement Plan 2014 airu 2018
City of Elk River, Minnesota
Project# 11-40
Project Name Highland Ave.Water Main
Type Infrastructure Department Infrastructure Improvements
Useful Life 20 years Contact Engineer
Category Street&Utility Construction Priority n/a
Description
New water main during City road reconstruction project for Oxford Street,Norfolk Street, 192nd Ave,Lowell Circle.
Justification
Increase system capacity.
Expenditures 2014 2015 2016 2017 2015 Total
Construction/Maintenance 150,000 150,000
Total 150,000 150,000
Funding Sources 2014 2015 2016 2017 2018 Total
Trunk Utility Fund 150,000 150,000
Total 150,000 150,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 23
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# 11_41
Project Name ease 11 Natures Edge Business Center
Type Infrastructure Department Infiastiuctirre Improvements
Useful Life 20 years Contact Engineer
Category Unassigned Priority n/a
Description
Design and construct public improvements to develop phase II of the Nature's Edge Business Center.
Justification
To provide larger light industrial/commercial lots to meet the increased demand requested by business relocating and/or expanding. The city has
experienced an increase in the number of business inquiries requiring larger foot print that can handle truck traffic,and manufacturing and
warehousing types of facilities with utilities already stubbed in.
Expenditures 2014 2015 2016 2017 2015 Total
Design/Construction 1,300,000 1,300,000
Total 1,300,000 1,300,000
Funding Sources 2014 2015 2016 2017 2018 Total
City Development Fund 100,000 100,000
Economic Development Author 300,000 300,000
State grants 500,000 500,000
Trunk Utility Fund 400,000 400,000
Total 1,300,000 1,300,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 24
tr.
I i UON LEFEBVRE SCOW ADDITION'
LEON LEFEBVRE I8 1,
' ADDITION —1 L_
J rnn AVENUE mw
OULES
CO
tM 7 p0
LARRY
ON ``� — ;C
s
t �+' .. -• t.V MORRELL
OAFA _
1
1
l F i ► •
f
f
NATURES EDGE BUSINESS CENTER 2ND ADDITION
City of
Ell
l�lver 200 0 200 400
_ SCALE IN FEET
Scale: 1 INCH = 400 FEET
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Y
Project# PM-01 �'
Project Name P
avement Management Program
Type hnprovement Department Infrastructure Improvements x
Useful Life 25 years Contact Engineer
i
Category Street&Utility Construction Priority n/a
ON
Description
Replace,overlay or rehabilitate aged and deteriorated streets,water mains,sewer mains,storm drainage,and pedestrian pathways. Projects will be
completed every other year.
Justification
hidividual street pavement conditions will dictate what pavement management technique will be utilized to extend the life of that specific street
segment. These techniques may range fi•om a full reconstruction of the surface and aggregate base to simply overlaying the existing pavement.
As they are implemented,the prescribed techniques will continually be gauged to assure their performance is proper in extending the life of our
pavements.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 4,000,000 4,330,000 8,330,000
Total 4,000,000 4,330,000 8,330,000
Funding Sources 2014 2015 2016 2017 2018 Total
Municipal State Aid 2,500,000 1,000,000 3,500,000
Pavement Management Fund 1,350,000 3,180,000 4,530,000
Storm Sewer 150,000 150,000 300,000
Total 4,000,000 4,330,000 8,330,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 25
kl IJJJ�IJ�IJbIJ �IJ�_I�_I�� � Jdlel��I��I�JJ,I�IJ .I��I � �J�� � _I �� 31JJ�I �I,I�.IJJ���I JaI �I�IPIaIJ�_I�I_IJ�aIJ:I JeI,I�I_I
\ /
b
T i-
0
A ae s Lill,
b
L 3
J
-
,e
� RECONSTRUCTION .�
F OVERLAY WITH EDGE MILL
FULL DEPTH RECLAIM WITH CURB PATCHING
WEAR COURSE PAVING ON
UNFINISHED DEVELOPMENT STREETS
I An
River � ��
a
2015 &2,2.2°,E �"���
8.
ElDRAWN BY
city STREET IMPROVEMENTS cML
R7� w1 SCALE:
iver NOT TO SCALE
kl IJJJ�IJ�IJ�IJ �IJ�_I�_I�� � Jdlel��I��I�JJ,I�IJ .I��I � �J�� � _I �� 31JJ�I �I,I�.IJJ���I JaI �I�IPIaIJ�_I�I_IJ�aIJ:I JeI,I�I_I
` 'A
F;�� 1A
Tr 11
sf.
^ i
�.�:
. � a
� RECONSTRUCTION .�
F OVERLAY WITH EDGE MILL
FULL DEPTH RECLAIM WITH CURB PATCHING
WEAR COURSE PAVING ON
UNFINISHED DEVELOPMENT STREETS
+
River .�
a
2017 &2,2.2°, �"���
8. E
ElDRAWN BY
city STREET IMPROVEMENTS cML
R7� w1 SCALE:
iver NOT TO SCALE
Capital Improvement flan 2014 thru 2018
City of Ells River, Minnesota
Project# QZ
Project Name Quiet Zones
Type hifiastructure Department Infrastructure hnprovements
Useful Life 25 years Contact Engineer
Category Street Construction Priority n/a
Description
Establish a quiet zone at all street crossings along the BNSF rail line.
Justification
This project will involve the installation of supplemental safety measures and wayside horns to qualify the entire rail corridor through Elk River as
a quite zone.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 500,000 500,000
Total 500,000 500,000
Funding Sources 2014 2015 2016 2017 2018 Total
Street Improvement Reserve 500,000 500,000
Total 500,000 500,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 26
Capital Improvement flan 2014 thru 201E
City of Elk Diver, Minnesota
Project# SC-03
Project Name Annual Sealcoat Program
Type Improvement Department Infrastructure Improvements
Useful Life 7 years Contact Street Supt.
Category Street Maintenance Priority n/a
Description
Sealcoat city streets and parking lots as identified by Street Superintendent.
Justification
Method of maintaining the surface condition of the city public facilities and streets
Expenditures 2014 2015 2016 2017 2015 Total
Construction/Maintenance 379,650 365,199 394,382 396,268 392,156 1,927,655
Total 379,650 365,199 394,382 396,268 392,156 1,927,655
Funding Sources 2014 2015 2016 2017 2018 Total
Government Buildings Reserve 15,000 15,000 15,000 15,000 15,000 75,000
Municipal State Aid 291,721 297,555 303,506 309,576 315,768 1,518,126
Pavement Management Fund 72,929 52,644 75,876 71,692 61,388 334,529
Total 379,650 365,199 394,382 396,268 392,156 1,927,655
2014-2018 CAPITAL IMPROVEMENTPLAN Page 27
Capital Improvement Plan 2014 thru 2018
City of Elk Diver, Minnesota
Project# SL-09
Project Name Signal Light fainting
Type Improvement Department Infi'astiucthu•e lmprovements
Useful Life 20 years Contact Engineer
Category Street Maintenance Priority n/a
Description
Paint signal systems
Justification
According to MNDOT/City signal agreements it is the responsibility of the City to repaint signal systems as needed.The last 2 systems will be
scheduled for painting in 2016 or as their condition requires.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 12,000 12,000
Total 12,000 12,000
Funding Sources 2014 2015 2016 2017 2018 Total
Street Improvement Reserve 12,000 12,000
Total 12,000 12,000
2014-2015 CAPITAL IMPROVEMENTPLAN Page 28
Capital Improvement Plan 2014 mru 2018
City of Elk Diver, Minnesota
Project# ST-12
Project Name Signalization of 193rd Avenue&Evans Street - � r
Type Infrastructure Department hrfrastnrcture Improvements x
Useful Life 20 years Contact Engineers
Category Street Construction Priority n/a
z
Description
Install a signal system including EVP at the intersection of 193rd Avenue and Evans Street.Because of the proximity to TH169,the signal system
must be interconnected with the existing highway signal system.
Justification
The construction of 193rd Avenue(2009)street improvement opens 193rd to CSAH 13 allowing another route to and from TH169. In
anticipation of the increased traffic flow the intersection of 193rd Avenue and Evans Street was constructed to accept a signal system.
Expenditures 2014 2015 2016 2017 2018 Total
Planning/Design 250,000 250,000
Total 250,000 250,000
Funding Sources 2014 2015 2016 2017 2018 Total
Municipal State Aid 250,000 250,000
Total 250,000 250,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 29
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# LS-01
Project Name Northbound Building Maintenance
Type Maintenance Department Liquor Fund
Useful Life 20 years Contact Liquor Store Manager
Category Building Maintenance Priority n/a
Description
Roof replacement at Northbound Liquor Store
Justification
The original roof from 1997 is starting to experience several leaks a year. We continue to perform minor roof patches,but frequency seems to be
increasing.
Expenditures 2014 2015 2016 2017 2018 Total
Building Maintenance 100,000 100,000
Total 100,000 100,000
Funding Sources 2014 2015 2016 2017 2018 Total
Liquor Fund 100,000 100,000
Total 100,000 100,000
2 014-2 018 CAPITAL IMPROVEMENT PLAN Page 30
Capital Improvement Plan 2014 thru 201
City of Elk Diver, Minnesota
Project# LS-03
Project Name Liquor store fiber optics
Type Infrastructure Department Liquor Fund
Useful Life 20 years Contact IT Coordinator
Category Tecluiology/Commmniciations Priority n/a
Description
Connect Northbound and Westbound liquor stores to City-wide fiber optic ring.
Justification
Centralized security camera monitoring;canceling extra internet service;speed enhancement between stores;connecting to enhance
communication between stores(cash registers etc.)and more options for backing up.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 42,000 42,000
Total 42,000 42,000
Funding Sources 2014 2015 2016 2017 2018 Total
Liquor Fund 42,000 42,000
Total 42,000 42,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 31
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# OK-13
Project Name Oak Knoll bighting Project
Type Improvement Department Park hmprovement Fund
Useful Life Unassigned Contact Park&Rec.Director
Category Park hnprovetnents Priority n/a
Description
The project will install athletic field lighting at the Oak Knoll Athletic Complex field#10. The project includes electrical and irrigation upgrades
needed to develop an improved lighted field at Oak Knoll.
Justification
Youth Football and Lacrosse associations entered into an agreement on December 2,2013 with the City to donate$73,000 over the next several
years. Both sports organizations and the Parks and Recreation Commission have connnented on the need in Elk River for an additional field with
lights since the city currently has one field with lights at the Youth Athletic Complex(YAC).
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 135,000 135,000
Total 135,000 135,000
Funding Sources 2014 2015 2016 2017 2018 Total
Donors 43,000 10,000 10,000 10,000 73,000
Liquor Fund 62,000 62,000
Total 105,000 10,000 10,000 10,000 135,000
2014-2018 CAPITAL IMPROVE11ENTPLAN Page 32
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# PIF-14 "
Project Name 2014 park improvement projects
Type Maintenance Department Park lrnprovement Fund s;
Useful Life Unassigned Contact Park&Rec.Director �
Category Park Improvements Priority n/a
Description
2014 projects include:
trail repairs&connections($113,000)
Orono Park improvements($51,000)
parks master plan update($65,000)
YAC complex well($35,000)
Dog park irrigation and trees($6,000)
playground safety($6,000)
Justification
Annual maintenance/repairs of our park system.
Expenditures 2014 2015 2016 2017 2018 Total
Park Improvements 276,000 276,000
Total 276,000 276,000
Funding Sources 2014 2015 2016 2017 2018 Total
Park Improvement Fund 276,000 276,000
Total 276,000 276,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 33
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# PIF-15 '
Project Name 2015 park improvement projects
Type Maintenance Department Park Improvement Fund
Useful Life Unassigned Contact Park&Rec.Director
Category Park Improvements Priority n/a
Description
2015 projects include:
trail repairs and connections($100,000)
Orono Park improvements($11,500)
Bailey Pointe kiosk($15,000)
Deerfield playground replacement($70,000)
Windsor Park improvements($20,000)
Baldwin Park improvements($15,000)
park property lines($3,000)
Upgrade irrigation to smart systems($5,000)
athletic field amenities($30,000)
playground safety($5,000)
Justification
Annual maintenance/repairs of our park system,
Expenditures 2014 2015 2016 2017 2018 Total
Park Improvements 274,500 274,500
Total 274,500 274,500
Funding Sources 2014 2015 2016 2017 2018 Total
Park Improvement Fund 274,500 274,500
Total 274,500 274,500
2014-2015 CAPITAL IMPROVEMENTPLAN Page 34
Capital Improvement flan 2014 thru 2018
City of Ells River, Minnesota
Project# PIF-16
Project Name 2016 park improvement projects
Type Maintenance Department Park Improvement Fund
Useful Life Unassigned Contact Park&Rec.Director
Category Park Improvements Priority n/a
Description
2016 projects include:
playground safety($5,000)
trail repairs and replacement($100,000)
park property lines($3,000)
Orono Park improvements($20,000)
athletic field amenities($30,000)
upgrade irrigation to smart systems($5,000)
Deerfield improvements($25,000)
Lions Park playground improvements($80,000)
Justification
Annual maintenance/repairs of our park system.
Expenditures 2014 2015 2016 2017 2018 Total
Park Improvements 268,000 268,000
Total 268,000 268,000
Funding Sources 2014 2015 2016 2017 2018 Total
Park Improvement Fund 268,000 268,000
Total 268,000 268,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 35
Capital Improvement plan 2014 airu 2018
City of Elk River, Minnesota
Project# PIF_17
Project Name 2017 park improvement projects
Type Maintenance Department Park Improvement Fund
Useful Life Unassigned Contact Park&Rec.Director
Category Park Improvements Priority n/a
Description
2017 projects include:
playground safety($5,000)
trail repairs and replacement($100,000)
park property lines($3,000)
upgrade irrigation to smart systems($5,000)
athletic field amenities($30,000)
Justification
Annual maintenance/repairs of our park system.
Expenditures 2014 2015 2016 2017 2018 Total
Park Improvements 143,000 143,000
Total 143,000 143,000
Funding Sources 2014 2015 2016 2017 2018 Total
Park Improvement Fund 143,000 143,000
Total 143,000 143,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 36
Capital Improvement flan 2014 thru 2018
City of Ells River, Minnesota
Project# PIF-18
Project Name 2018 park improvement projects
Type Maintenance Department Park Improvement Fund
Useful Life Unassigned Contact Park&Ree.Director
Category Park Improvements Priority n/a
Description
2018 projects include:
playground safety($5,000)
trail repairs and replacement($100,000)
park property lines($3,000)
upgrade irrigation to smart irrigation($5,000)
athletic field amenities($30,000)
Justification
Annual maintenance/repairs of our park system.
Expenditures 2014 2015 2016 2017 2018 Total
Park Improvements 143,000 143,000
Total 143,000 143,000
Funding Sources 2014 2015 2016 2017 2018 Total
Park Improvement Fund 143,000 143,000
Total 143,000 143,000
2 014-2 018 CAPITAL IMPROVEMENTPLAN Page 37
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# PK-14 g
Project Name 2014 Park Maintenance Equipment
Type Equipment Department Park Maintenance
Useful Life Unassigned Contact Park&Rec.Director
Category Equipment Priority n/a
Description
Replace 2006 Toro 328 front mount mower w/attachment$43,400
Replace 2002 Ski-doo Scandic$10,200
Replace 2003 CAT skid-steer with tracks$54,500
Tractor shared between Parks Maintenance and Pinewood(Hold per fleet committee)$56,800
Justification
Annual replacement of parks equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 164,900 164,900
Total 164,900 164,900
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 164,900 164,900
Total 164,900 164,900
2014-2018 CAPITAL IMPROVEMENTPLAN Page 38
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# PIC-15
Project Name 2015 Park Maintenance Equipment
Type Equipment Department Park Maintenance
Useful Life Unassigned Contact Park&Rec.Director '
Category Equipment Priority n/a
Description
2007 Toro zero turn mower$24,800
2001 Chevy S-10$31,000
2002 Dodge 2500$31,000
2008 Kromer ballfield maintenance machine$34,000
Tractor attachments$14,000
Justification
Annual replacement of parks equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 134,800 134,800
Total 134,800 134,800
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 134,800 134,800
Total 134,800 134,800
2014-2018 CAPITAL IMPROVEMENTPLAN Page 39
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project#
j PIS-16
Project Name 2016 Park Maintenance Equipment
Type Equipment Department Park Maintenance
t
Useful Life Unassigned Contact Park&Rec.Director -
Category Equipment Priority n/a
i
Description
2007 1-ton with plow$65,000
2005 Chev Silverado$31,000
2011 Toro g•oundsmaster 16ft mower$91,600
New addition;Utility Lift$49,000
Justification
Annual replacement of parks equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 236,600 236,600
Total 236,600 236,600
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 236,600 236,600
Total 236,600 236,600
2014-2018 CAPITAL IMPROVEMENT PLAN Page 40
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# PK-17
Project Name 2017 Park Maintenance Equipment
Type Equipment Department Park Maintenance
Useful Life Unassigned Contact Park&Rec.Director
Category Equipment Priority n/a
Description
1990 F350$31,000
2009 Chevy Silverado$31,000
2008 F250$37,000
2005 Ski-Doo Skandic$10,200
2011 Toro Groundsmaster wide area mower$72,500
2006 Mower trailer$7,000
New addition;tractor attachments$4,500
Justification
Annual replacement of parks equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 193,200 193,200
Total 193,200 193,200
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 193,200 193,200
Total 193,200 193,200
2014-2015 CAPITAL IMPROVEMENTPLAN Page 41
Capital Improvement Ilan 2014 mru 2018
City of Elk River, Minnesota
Project# PK-18
Project Name 2018 Park Maintenance Equipment
Type Equipment Department Park Maintenance
Useful Life Unassigned Contact Park&Rec.Director
Category Equipment Priority n/a
Description
Replace 2008 F250 pickup truck$33,000
Replace 2003 Suzuki ATV$6,000
Replace 2008 Kubota RTV$27,500
Additional 2-ton truck with dump$65,000
Tractor attachments$37,500
Justification
Annual replacement of parks equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 169,000 169,000
Total 169,000 169,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 169,000 169,000
Total 169,000 169,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 42
Capital Improvement flan 2014 rhru 2018
City of Elk Diver, Minnesota
Project# 101
Project name pinewood Equipment Replacement
Type Equipment Department Pinewood Golf Course
Useful Life Unassigned Contact Park&Rec.Director
Category Equipment Priority n/a
Description
2014-2000 Toro Greens Aerator,$18,200
2015-Replace 2006 Toro 5200-D,$40,000;Club car utility cart,$7,000;2006 Toro Sidewinder$35,200
2016-Replace 2006 Toro GM-3150,$27,000;2005 Golf carts,$25,200
2017-Replace 2005 Golf Carts,$25,200
2018-Replace 2006 Toro workman$12,000;2006 lely fertilizer spreader$6,000
Justification
Annual replacement based on age and condition of equipment at the Golf Course.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 18,200 82,200 52,200 25,200 18,000 195,800
Total 18,200 82,200 52,200 25,200 18,000 195,800
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 18,200 82,200 52,200 25,200 18,000 195,800
Total 18,200 82,200 52,200 25,200 18,000 195,800
2014-2018 CAPITAL IMPROVEMENT PLAN Page 43
Capital Improvement flan 2014 thru 2018
City of Elk Diver, Minnesota
Project# Plan-01
Project Name mining Study
Type Study Department Planning
Useful Life Unassigned Contact Planning Manager
Category Street&Utility Construction Priority n/a
Description
Major Planning Study-Gravel mining area
Justification
The Comprehensive Plan(2004)identified several areas requiring master plans,including the mining area,and the old town area. It is expected
that the revised comprehensive plan(2013)will identify areas requiring further study.
The need to do these master plans will be evident as the City experiences development pressure in the area,coupled with a desire to proactively
accommodate market goals while promoting a unified vision. It is envisioned that funds will be used to assist the private market in the
development of a plan in a cooperative effort.
Expenditures 2014 2015 2016 2017 2018 Total
Engineering 40,000 40,000
Total 40,000 40,000
Funding Sources 2014 2015 2016 2017 2018 Total
City Wide Trunk Utilities 40,000 40,000
Total 40,000 40,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 44
Capital Improvement flan 2014 thaw 2018
City of Elk River, Minnesota
Project#
PD-01
Project Name Marked S q uad Replacement&Additions
Type Vehicle Department Police 4
Useful Life 3 years Contact Police Chief
Category Vehicles Priority n/a
Description
Routine replacement of vehicles at or near 100,000 miles. Includes all equipment and setup.
2014-3 replacement
2015-3 replacement
2016-2 replacement
2017-2 replacement; 1 new
2018-2 replacement
Justification
Annual replacement(3-4 years)of vehicles with over 100,000 miles or high miles and excessive maint.cost.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 108,000 108,000 72,000 108,000 72,000 468,000
Total 108,000 108,000 72,000 108,000 72,000 468,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 108,000 108,000 72,000 108,000 72,000 468,000
Total 108,000 108,000 72,000 108,000 72,000 468,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 45
Capital Improvement Plan 2014 thru 2018
City of Ells River, Minnesota
Project# PD-02
Project Name Unmarked Squad Replacement&Additions
Type Vehicle Department Police
Useful Life 7 years Contact Police Chief dl
Category Vehicles Priority n/a
rk
r
Description
2014- 1 replacement
2015-2 replacement
2016-2 replacement
2017-None
2018-2 replacement
Justification
Annual replacement of high mileage unmarked vehicles.(100,000 plus or over 7-years old) Starting in 2012,these vehicles are being replaced
with the 2wd Chevy Tahoe's to provide more space for the Sergeant's equipment.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 35,000 50,000 50,000 50,000 185,000
Total 35,000 50,000 50,000 50,000 185,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 35,000 50,000 50,000 50,000 185,000
Total 35,000 50,000 50,000 50,000 185,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 46
Capital Improvement Plan 2014 thl-u 2018
City of Elk River, Minnesota
Project# PD-03 a
Project Name CS®vehicle Replacement&Additions
Type Vehicle Department Police
Useful Life 6 years Contact Police Chief
Category Vehicles Priority n/a
? M
Description
CSO vehicle replacement and additions as follows:
2014- 1 replacement
2016- 1 replacement
Justification
Annual replacement of vehicles with over 100,000 miles or over 6-years old.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 35,000 35,000 70,000
Total 35,000 35,000 70,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 35,000 35,000 70,000
Total 35,000 35,000 70,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 47
Capital Improvement Ilan 2014 thru 2018
City of Elk River, Minnesota
Project# PD-04
Project Name police Department- Other Equipment
Type Equipment Department Police
Useful Life Unassigned Contact Police Chief
Category Equipment Priority n/a
Description
2014-3 Mobile Computer replacement and other equipment
2015-4 Mobile Computer replacement and other equipment
2017-4 Mobile Computer replacement and other equipment
Justification
Annual replacement of computers that are over 5-7 years old.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 9,000 12,000 12,000 33,000
Total 9,000 12,000 12,000 33,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 9,000 12,000 12,000 33,000
Total 9,000 12,000 12,000 33,000
2 014-2 018 CAPITAL IMPROVEMENT PLAN Page 48
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# PD-07
Project Name Special Operation Truck
Type Equipment Department Police
Useful Life 20 years Contact Police Chief
Category Equipment Priority n/a G
Description
SWAT van to compliment the 1993 International truck transferred from the Fire Department in 2011.
Justification
The Special Operations van will be a multi-purpose vehicle used in the following circumstances:
SWAT team and Crisis Negotiators for personnel and equipment transport during critical incidents.
Mobile Command Post(police station on wheels)during Critical Incidents(see above),major incidents(storms,large fire scenes,major crashes
etc.),and major community events(4th of July,etc).
Major Crime Scene response-It is equipped with investigative supplies and equipment enabling detectives to operate more effectively at scenes
they will be at for an extended period of time.
Expenditures 2014 2015 2016 2017 2015 Total
Vehicles 40,000 40,000
Total 40,000 40,000
Funding Sources 2014 2015 2016 2017 2015 Total
Equipment Replacement Fund 40,000 40,000
Total 40,000 40,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 49
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# BL-07
Project Name Activity Center
Type Maintenance Department Public Buildings
Useful Life Unassigned Contact Park&Rec.Director
Category Buildings Priority n/a
Description
2014 projects include roof replacement,ventilation system,carpet,boilers,AC unit replacement,doors,lighting/ceiling tiles,
2016 project include replacing the exterior lighting with LED.
Justification
The activity center was built in 1975 and functioned as a library prior to it becoming the activity center. Projects will be prioritized pending
facility plan review.
Expenditures 2014 2015 2016 2017 2018 Total
Building Maintenance 226,557 0 11,040 237,597
Total 226,557 0 11,040 237,597
Funding Sources 2014 2015 2016 2017 2018 Total
Government Buildings Reserve 226,557 11,040 237,597
Total 226,557 11,040 237,597
2014-2018 CAPITAL IMPROVEMENTPLAN Page 50
Capital Improvement Plan 2014 thru 2018
City of Ells River, Minnesota
Project# BL-11
Project Frame Fire Station#1 projects
Type Maintenance Department Public Buildings
Useful Life 25 years Contact Fire Chief
Category Building Maintenance Priority n/a
Description
Concrete floor repairs at Fire Station#1 (2015)
Justification
Concrete Floor Repairs- The concrete floor around the drains is in need of repair.
Expenditures 2014 2015 2016 2017 2018 Total
Building Maintenance 48,000 48,000
Total 48,000 48,000
Funding Sources 2014 2015 2016 2017 2018 Total
Government Buildings Reserve 48,000 48,000
Total 48,000 48,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 51
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# PS-03
Project Name Public Safety Building maintenance
Type Maintenance Department Public Safety Building
Useful Life 15 years Contact Building Maintenance Supv.
Category Building Maintenance Priority n/a
Description
Carpet replacement in the Police department and remodel fire department side(2015)
Floor tile replacement in the Police department(2016)
Additional garage space(2018)
Justification
The Public Safety building was built in 2002 and the traffic volume from staff and visitors has started to wear on the carpet and tiles.
Expenditures 2014 2015 2016 2017 2015 Total
Building Maintenance 155,000 33,122 287,170 475,292
Total 155,000 33,122 287,170 475,292
Funding Sources 2014 2015 2016 2017 2018 Total
Government Buildings Reserve 155,000 33,122 287,170 475,292
Total 155,000 33,122 287,170 475,292
2014-2018 CAPITAL IMPROVEMENT PLAN Page 52
Capital Improvement Plan 2014 au,u 2018
City of Elk River, Minnesota
Project# WW-02
Project Name Lift Station Rehabilitation
Type Maintenance Department Sewer Department
Useful Life 15 years Contact Chief Wastewater Operator
Category Utilities Priority n/a
Description
2014,2016&2018 Rehab oldest lift stations this is a ongoing maintenance item.
Justification
Preventative maintenance on our oldest lift stations.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 50,000 60,000 60,000 170,000
Total 50,000 60,000 60,000 170,000
Funding Sources 2014 2015 2016 2017 2018 Total
Sewer Fund 50,000 60,000 60,000 170,000
Total 50,000 60,000 60,000 170,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 53
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# VVW-03
Project Name JetNacuuni truck
Type Equipment Department Sewer Department
Useful Life 10 years Contact Chief Wastewater Operator
Category Heavy Equipment Priority n/a
Description
Replace the current Jet/Vac truck for the sewer division
Justification
In 2015 the sewer division jet/vac truck will be 12 years old and have reached its planned replacement age. Given the miles of sewer lines that
need to be cleaned each year it is important to have dependable equipment for the sewer division to perform one of its key functions.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 400,000 400,000
Total 400,000 400,000
Funding Sources 2014 2015 2016 2017 2018 Total
Sewer Fund 400,000 400,000
Total 400,000 400,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 54
Capital Improvement Plan 2014 thi-u 2018
City of Elk River, Minnesota
Project# WW-06
Project Name Vehicle Replacement
Type Vehicle Department Sewer Department
Useful Life 10 years Contact Chief Wastewater Operator
Category Vehicles Priority n/a
Description
2015-pickup replacement
2016- 1-ton with hoist replacement
2018-pickup replacement
Justification
Annual replacement of vehicles after approximately 10 years and is adjusted based on maintenance costs and condition of vehicles.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 30,000 70,000 35,000 135,000
Total 30,000 70,000 35,000 135,000
Funding Sources 2014 2015 2016 2017 2015 Total
Sewer Fund 30,000 70,000 35,000 135,000
Total 30,000 70,000 35,000 135,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 55
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# WW-15
Project Name Replace Generators
Type Equipment Department Sewer Department
Useful Life 10 years Contact Chief Wastewater Operator
Category Equipment Priority n/a
Description
Replace 5 mobile generators.
Justification
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 110,000 110,000
Total 110,000 110,000
Funding Sources 2014 2015 2016 2017 2018 Total
Sewer Fund 110,000 110,000
Total 110,000 110,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 56
Capital Improvement flan 2014 thru 2018
City of Elk River, Minnesota
Project# WW-17
Project Name plant Expansion Master Plan
Type Improvement Department Sewer Department
Useful Life Unassigned Contact Engineer
Category Plant Expansion Priority n/a
Description
Modification to the existing WWTF. These modifications will increase the treatment capacity and meet the limits of our MPCA discharge permit.
The improvements are currently being designed according to growth projections,permit requirements and findings of the approved Facility Plan.
Justification
hi addition to the increased flow projections expected as the City grows,treatment limits of our reissued MPCA permit continue to require
additional equipment and treatment processes to meet the MPCA requirements.
Expenditures 2014 2015 2016 2017 2018 Total
Construction/Maintenance 12,619,000 12,619,000
Total 12,619,000 12,619,000
Funding Sources 2014 2015 2016 2017 2018 Total
Sewer Fund 3,000,000 3,000,000
State grants 3,000,000 3,000,000
Trunk Utility Fund 1,000,000 1,000,000
Utility Revenue Bonds 5,619,000 5,619,000
Total 12,619,000 12,619,000
2014-2018 CAPITAL IMPROVEMENTPLAN Page 57
Capital Improvement Flan 2014 thru 2018
City of Elk Diver, Minnesota
Project# ST-01
y �
o. ,
Project Name Vehicle Replacement-pickup trucks ,
Type Vehicle Department Streets
Useful Life 10 years Contact Street Supt.
Category Vehicles Priority n/a �
i
Description
Street department pickup truck replacements.
2014-Pick up$28K(replaces 2003 Ford F150 which will be transferred to parks)
2018-replace 2008 Ford F250 and 2007 Ford F550 dump box truck
Justification
Annual replacement of streets equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Vehicles 28,000 101,000 129,000
Total 28,000 101,000 129,000
Funding Sources 2014 2015 2016 2017 2015 Total
Equipment Replacement Fund 28,000 101,000 129,000
Total 28,000 101,000 129,000
2014-2015 CAPITAL IMPROVEMENTPLAN Page 58
Capital Improvement flan 2014 thru 2018
City of Elk Diver, Minnesota
Project# ST-02
Project Name Dump Truck Replacement
Type Equipment Department Streets x a
Useful Life 15 years Contact Street Supt.
Category Heavy Equipment Priority n/a t d t
Description
Dump truck replacement and additions.Includes all plow equipment.
2014- 1 Tandem Axle with plow,replaces 1987 L8000 Ford Single Axle plow truck
2018- 1 Tandem Axle with plow,replaces 2003 Tandem Axle plow truck
Justification
Annual replacement of streets equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 205,000 205,000 410,000
Total 205,000 205,000 410,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 205,000 205,000 410,000
Total 205,000 205,000 410,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 59
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# ST-03 ��
Project Name F - x
� Leavy Equipment Replacement
Type Equipment Department Streets •�` � '�
Useful Life 15 years Contact Street Supt. <<.
Category Vehicles Priority n/a
Description
Heavy Equipment replacements&additions as follows:
2017-sweeper(replaces 2005,unit#316),front-end loader(replaces 2003,unit#313)
Justification
Annual replacement of streets equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 343,000 343,000
Total 343,000 343,000
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 343,000 343,000
Total 343,000 343,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 60
Capital Improvement Tian 2014 thru 2018
City of Elk Diver, Minnesota
Project# ST-04
Project Name Other Equipment Replacement
Type Equipment Department Streets
Useful Life Unassigned Contact Street Supt.
Category Equipment Priority n/a
r.
Description
Replace other Street Department equipment as follows:
2014-John Deere tractor(replaces 1999 tractor)$57,750,loader attachments$20,000
2015-Brush Chipper(replaces 2000 chipper)$50,000,trailer replacement$15,000
2016-Wacker roller$15,000,pavement cutter$11,550
2017-None
2018-pavement cutter$11,550
Justification
Annual replacement of streets equipment based on usage,age,and reliability.
Expenditures 2014 2015 2016 2017 2018 Total
Equipment 77,750 65,000 26,550 11,550 180,850
Total 77,750 65,000 26,550 11,550 180,850
Funding Sources 2014 2015 2016 2017 2018 Total
Equipment Replacement Fund 77,750 65,000 26,550 11,550 180,850
Total 77,750 65,000 26,550 11,550 180,850
2014-2018 CAPITAL IMPROVEMENT PLAN Page 61
Capital Improvement Plan 2014 thru 2018
City of Elk River, Minnesota
Project# TC-01
Project Name Annual Technology Upgrades
Type Equipment Department Technology/Connnunications
Useful Life 5 years Contact IT Coordinator
Category Technology/Communiciations Priority n/a
Description
2014-replace enterprise backup system,hardware/enterprise switch,fiber optic enhancements,and virtualization refresh
2015-phone system replacement,fiber optic enhancements,council computer replacements,mierosoft office upgrade
2016-SQL server upgrades,hardware and enterprise switch/UPS,fiber network enhancements
2017-None
2018-hardware and enterprise switch upgrade/virtual desktop implementation
Justification
Annual replacement and upgrade of information technology software/hardware.
Expenditures 2014 2015 2016 2017 2015 Total
Equipment 135,500 207,500 72,000 175,000 590,000
Total 135,500 207,500 72,000 175,000 590,000
Funding Sources 2014 2015 2016 2017 2018 Total
Capital Outlay Reserve 135,500 207,500 72,000 175,000 590,000
Total 135,500 207,500 72,000 175,000 590,000
2014-2018 CAPITAL IMPROVEMENT PLAN Page 62
O O o o o 0 0 0 0 0 0 0 O o O o 0
N 0 0 0 0 0 0 0 0 Lo 0 0 0 O O O o 88
O 000000 C o f-0 0 0 N Lo d' N Lo a0 O
U Lo O o(D Lo M o o r co O Lo W 1- M O V O N
N N W M P')M M M Lo N N N N V Lo Lo m
N aJ
W rn
V3
R
o O
O �-
o 3 N
O
N O N
U (D E
N U O w M U
N E C MM
a) R R C a) 3 a
L'm'o o
R m m a a� E o` c 3 d R
d p U U 3 3 O U a> p 2i U
N N O E a O a)
3 N a) R R O O a) R F Y p > O R
ZXUUUo oL w �5 'E 7 E
W R R R a) Y Q U a y
~F N E O O O C N U O O
t> > > > >'6 C = a) 9 16 Z)L c L L O--p O a W aJ
V O
O V O R -9 E E Y Y
w In U U U U LL d F K cn (L cn co F
c a) m m o
O U U U U
y C o ca C
O C C C C c
p N N a a)
C E C
O N O R R R R
-ii E o o w o o m a m 3 co
a) E m O d d N 6 a) M Y Y Y Y
LL
ao¢aa�aUainu)c565 n u- a a as
N o 0 0 .2.0
d c 5 m m Tv
N (D m o 0 o d
E
R Y Y Y Y N a) a) a) a)
L Q 3:3:3:3: C C C C C
R R R R R
N N a) a) 0101,2
U U U N N N N N
a�� Y 'D Y Y Y Y
= Eu- 0-5-6-6 0 6 5 0 3 3 co R R R R
a.aaaaaao_aa
.y 3 Q O O N y y 0 0 0 Q 0 O N O O O Q
Q. Q a)Z 3 3 (C`6 (6 i = = 3 Z> > N 3 3 3 Z
•� G Q Q F F F Q Q¢ Q Q F Q Q Q
s
W l V V f o(D V N Z N O O N -Z
le T" d
(V
N UL z ch co Dmv OQ o o Lo Ln oQ
Z ( O r Z N to M Z
R'
U
Y w
U �
E
v m 0 o v p
3 Y O o N
C F R M S O U
o f E Y M °' _E
J o
C
O
R N R
O c
N O
p R O O R O O (D E U 3
(D d U U
p >> R> 0 X u)
a s c c c o o v a c o o Y o
a 3 3 3 U o m a
0 ca o o o Z a aoi ° Lo F N O a
c-)c) oU (u RC)u. o 0 co o w
m as a>i 2 c-p ° � > o FB
Q LL LL U Ll0 o-o(L - ~ U F cn U=
O O O(�W a0 O M !- O M (D N M
O Q 0 0 0 D)O Q. O O O O O Q
O 0 a o o(D p QL O O O O O O O
P Z N N N N N N Z N N N N N Z
C
D m Q O to 7 W cD (D N Q M Q M N N
O N Q
O f0 N(D O O- N f� O
�Z (D Z OJ r f- r W Z
O M V LD O r O O O N M V N O r OJ y
Z o
2
2014 CAPITAL OUTLAY-Final
Funding Source
Requested General Ice Waste Capital Outlay Liquor Gov't Department
Department Item Amount Fund Arena Water Fund Reserve Fund Bldg Fund Other Total
7
Administration Scanner Replacement 7,500 - !t� 7,500
7,500 7,500
Community Operations Office Building Out 4,600 4,500
4,500 4,500
EOC radio communication equipment 12,000 4 I 12,000
Emergency Mgmt EOC upgrades 20,000 20,000
32,000 a 32,000
Replace Virtualized Server and SAN 99,000 99,000
Enterprise Backup System 15,000 15,000
Fiber Network 10,000 10,000
IT Windows Server Upgrades 11,500 11,500
135,500 135,500
Building Maintenance City Hall space redesign(Finance area) 15,000 ( 15,000
Crack repairs public safety building 5,000 ( t 5,000
20,000 20,000
Admin/Planning/Engineering Plotter 10,000 10,000
Planning Mining Study 40,000 40,000
50,000 50,000
HVAC/Heater replacmenl(Old building) 18,000 18,000
Streets/Snow removal/Fleet Portable Brake Lathes 10,500 � � 10,500 J
28,500 28,500
Parks and Recreation Lions park warming house 7,000 (I��7,000
7,000 7,000
Fire Administration Extrication Equipment 26,000 26,000
Station#1 lighting retrofit 3,500 3,500
Replace ARMER radio consollettes 12,000 - 12,000
41,500 41,500
Subtotal General Fund Departments 326,500 233,500 53,000 40,000 326,500
Ice Arena Membrane Over the Barn's Roof(carryover 2013) 117,000 117,000
Front entrance doors 12,350 12,350
Vertical cracks to Olympic precast 16,200 16,200
Electronic Air Quality Monitor 13,000 13,000
Dehumidifier In Barn(carryover 2013) 185,400 185,400
343,950 343,950
WWTP Expansion Project 12,619,000 12,619,000
12,619,000 12,619,000
Pinewood Ride on Unit Mower(Equipment Replacement Fund) 18,200 18,200
18,200 18,200
Liquor Stores Fiber Optic installation 42,000 42,000
42,000 42,000
Total $13,349,650 $0 $343,950 $12,619,000 $233,500 $42,000 $58,200 $13,349,650
Note:Vehicle and equipment replacement for non-enterprise funds will be reviewed with the 2014-2018
equipment replacement fund.