9.3. SR 01-21-2014 �i EOty lk Request for Action River To Item Number Mayor and City Council 9.3 Agenda Section Meeting Date Prepared by Work Session January 21, 2014 Justin Femrite, P.E. City Engineer Item Description Reviewed by Discuss Wastewater Treatment Expansion Gary Leirmoe, Chief Operator Matt Stevens,Lead Operator Reviewed by Cal Portner, City Administrator Action Requested Discuss current facility expansion design status and cost estimates. Background/Discussion Work continues on the final design of the Wastewater Treatment Facility (WWTF) expansion. A number of conditions have changed with respect to options available to process and dispose of biosolids since first discussing the project. These conditions have driven our team to look at different options for biosolids processing and handling. Our consultant will give an overview of the project,liquid stream design update, evaluation of biosolids disposal options and discuss the updated cost estimate. Financial Impact The consultant will have an updated project cost estimate to review at the meeting. Attachments ■ None p 0 W I R I I a ATURE C icy of r Wastewater Treatment Facility Update January 21 , 2014 BCQLTON M P= Consulting Engineers & Surveyors Summary • Overview of Original Project • GRE Discussions • Revised Liquid and Biosolids Options • Revised Cost Estimate BCC LTC::>N 8, M I N K , I N C® Consulting Engineers & Surveyors 2 Original PrJ' ect o • Cost Estimate — Liquid Stream = $ 10. 619 million — Biosolids Stream = $0. 675 million • Total Project Cost = $ 11 . 294 million BC)LTC::>N 8, M I N K , I N C® Consulting Engineers & Surveyors 3 GRE Discussions • Met multiple times with GRE to discuss options for biosolids treatment/disposal • Four options evaluated — Injection of biosolids into boiler (liquid and cake product) — Injection of biosolids into ductwork following combustion chamber (liquid and cake product) — Use liquid biosolids as makeup to bottom ash system — Deposit biosolids on ash conveyor or ash pile BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 4 GRE Options • Injection of biosolids into boiler — Determined not feasible due to air permitting issues and minimal energy benefit • Injection of biosolids into ductwork following combustion chamber — Determined not feasible due to air permitting issues and minimal energy benefit • Use liquid biosolids as makeup to bottom ash system — Determined not feasible due to potential health and processing concerns • Deposit biosolids on ash conveyor or ash pile — Not feasible due to long term hauling costs for the City BOLTON 8, M B N K , I NC® Consulting Engineers & Surveyors 5 Revised Liquid and Bisofids Options • Abandoning GRE option impacts both liquid and biosolids stream options • Liquid stream changes — All extended aeration facility ( larger tankage) — Eliminate primary clarifiers and convert to selector basins — Eliminate trickling filters — All other processes remain the same BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 6 Biosofids Stream Options • Liquid stream changes impact biosolids stream • All aerobically digested for new process • Land application options — Liquid, cake or dry solids • Liquid application is current method (3% solids) • Cake solids (screw press or centrifuge — 18%) • Dry solids (dryer — 98%) BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 7 Biosofids Options • Cake Solids (approx. 18%) — Screw press or centrifuge — Reduce volume by 86% (compared to liquid ) — Range of costs - $2 .85 - $3 .7 million • Dry Solids (approx. 98%) — Dryer — Reduce volume by 97% (compared to liquid ) — Range of costs - $7.7 - $11.0 million BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 8 Revised Cost Estimate • Liquid stream = $ 12 . 55 million • Biosolids stream — Cake solids = $2 .85 - $3 .7 million — Dry solids = $7.7 - $11.0 million • Total Project cost = $ 15 .40 — $23 . 55 million BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 9 Phosphorous Grant • Point Source Implementation Grant • Grant only for phosphorous related items • City awarded a $3 million grant ( max. ) • Grant is reduced by Essential Project Component ( EPC) — Calculation of current loading divided by future loading — ranges from 47% to 61% • Reduces grant amount to approx. $2 . 3 to $3 .0 million — Dependent on option chosen • Final grant amount determined after bidding BCC LTC::>N 8, M I N K , I N C® Consulting Engineers & Surveyors 10 Recommendations • All extended aeration facility — Greater operational flexibility — More consistent effluent • Aerobically digested biosolids • Cake solids ( 18%) processing — Less product to haul/land apply (86% reduction ) — Greater operational flexibility • Drying option ? BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 11 Schedule • Submit P/S to MPCA - March/April 2014 • Bid Opening - May/June 2014 • MPCA certify project by June 30, 2014 • Construction start - July 2014 • Construction complete - June 2016 BOLTON 8, MENK , INC. Consulting Engineers & Surveyors 12