Loading...
5.4. SR 11-30-1998ity of River MEMORANDUM Item 5.4. TO: FROM: DATE: SUBJECT: Mayor & City Council Pat Klaers, City Adm~or November 30, 1998 East Elk River The trunk sewer and water bids have been received and are being evaluated. The bids are higher than the engineer's estimate as included in the July 1997 feasibility report. The trunk sewer and water assessment public hearing is scheduled for a special city council meeting on Thursday, December 3, 1998, at 6 p.m. in the City Council Chambers. On December 3 it is expected that the City Council will assess the benefited property owners in the trunk sewer and water project area $6,000 per acre, and other City Council action (on the bid award) is possible. The purpose of this November 30 agenda item it to try to get everyone prepared for the 12/3 assessment public hearing. In this regard, on Monday evening, staff plans to review the bids with the Council, discuss the shortage between the bids and the assessment amountsl review funding options for the shortage, and most importantly, discuss cash flow issues with making bond payments. Additionally, we will discuss the anticipated property owner comments, requests, and assessment appeals. The agenda and background material for the assessment public hearing will be distributed Monday evening. The trunk sewer and water project is only part of the entire eastern Elk River public improvement project. In order to adequately prepare for the 12/3 meeting, the Council also needs to look at the other components of the east Elk River project. After federal grant paper work is completed, the city anticipates bidding out the street and storm sewer components of the east Elk River project. There are less financial shortage concerns related to the street project because of the number of funding sources available (grant, developer payments, TIF, MSA funds, etc.). However, there are significant 13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330 · TDD & Phone: (612) 441-7420 · Fax: (612) 441-7425 East Elk River November 30, 1998 Page 2 concerns about the shortage in the storm drainage component of the project and the lack of funding sources to eliminate this shortage. Additionally, when we look at the big picture out east, we also have to take into consideration the anticipated acquisition of the Brown and Kirkeide properties, along with the city assuming the Brown assessments. Last July, when staff met with the City Council to review this project, I noted that the trunk sewer and water numbers were getting closer and that this project was less of a financial concern than previously indicated. These comments were based in part on the TIF redevelopment project financing the sanitary sewer lift station. Now that the bids have been opened, we have a different situation to discuss with the City Council. The funding shortage has gotten larger as the low bid is about 10 percent above the July 1997 estimate. After financing the lift station with TIF 19 funds, and after assessments are levied, the water and sewer components are underfunded by about $1 million. We knew the trunk sewer and water project was underfunded, but we did not know it would be to this extent. (Inflation and demand are part of the reason for higher bids. Additionally, the city is still working on obtaining the trunk utility easements and necessary right-of-way so there may be some additional costs.) TIF 19 could finance all of the trunk water and sewer shortage as it is an eligible activity, but a more likely source of funds is for the water department and sewek department to each fund their shortages. This is based on the goal of keeping the total number of years in TIF District No. 19 as small as possible, along with the fact that the city has some other needs for TIF 19 funds such as financing as much of the storm drainage component as possible. In spite of reviewing a $1 million shortage in the trunk utility project after TIF 19 fund finances the lift station, I need to indicate to the City Council that the biggest concern with the trunk sewer and water project is the cash flow of receiving assessments in order to make bond payments. How to structure the bond repayment schedule when considering assessment and/or interest deferrals is the issue. Dave MacGillivray, the city's bond consultant from Springsted, will present information on this issue on Monday. As previously noted, the trunk sewer and water project at a cost of about $6 million, is only part of the total east Elk River proposal. The other two components of the overall proposal are the street and storm drainage improvements. Also as previously noted, the street improvement is not as big of a financial concern as the storm drainage improvement, due mainly to the East Elk River November 30, 1998 Page 3 federal grants that have been obtained. Additionally, we have municipal state aid funds which are eligible to be used on this street project, some TIF money that can be used ff necessary, and some developer participation from the Trott Brook Farms project is anticipated. Based on the July 1997 feasibility study, the most underfunded improvement in this project is the storm drainage component. There are limited funding resources that can be used for this improvement and we are concerned about depending heavily on the surface water management (SWM) tax levy. This is because the SWM tax levy available for new debt is very limited, and also there will be future SWM projects that are not'known at this time. Accordingly, it is most appropriate to try to have TIF 19 finance as much of the storm drainage improvements as possible. However, this is in conflict with the goal of keeping the TIF 19 total years small. Additional financial issues related to the overall project include a desire to acquire the Brown property and the Kirkeide property and, ff this takes place, then the city has to deal with financing the assessments associated with the Brown property. Two other financial considerations that everyone needs to keep in mind are the grant matching requirements placed upon the city and the TIF penalty or participation requirement. At this time staff believes there are viable options for the TIF penalty or participation and also the grant matching requirement, but these are additional pieces of the puzzle that need to be put into place, and with any puzzle, these pieces are interrelated with the whole. On Monday evening we will visit with the City Council about the options for funding this project, the goal of keeping the TIF District as short as possible while at the same time not depleting all of our other funding sources (i.e. MSA funds, SWM funds, development funds), and the issue of meeting all of our bonding debt and cash flow requirements. EAST ELK RIVER PROJECT Proiect Costs Construction Overhead Total Costs November 17 Bid Water Sewer Lift Station Total 1,929,269 2,623,684 492,201 5,045,153 540,195 734,631 137,816 1,412,643 2,469,464 3,358,315 630,017 6,457,796 Revenues Trunk Assessments Hohlen Lateral Assmts Trott Brook Oversizing Cr. Trott Brook Addl Trunk Assmt. Total Identified Revenues 1,395,460 2,790,920 4,186,380 103,500 103,500 207,000 (99,000) (176,000) (275,000) 270,887 436,088 706,975 1,670,847 3,154,508 4,825,355 798,617 203,807 630,017 1,632,441 Balance to be Funded 3ther Financin,q Sources TIF 19 Water Fund Sewer Fund XXX XXX 630,017 630,017 XXX XXX Financing to be Identified (amounts from above sources not yet determined) 1,002,424 July estimated shortfall (without TIF for Liftstation) was $964,745. November bid shortfall (without TIF for Liftstation) is $1,632,441 Budget Actual (Less Trott Brook Request) Adjusted Actual Variance (Over Budget) Budget vs Actual Construction Water Sewer Lift Station Total Only 1,809,313 2,473,206 800,606 5,083,125 3,971,191 2,469,464 3,358,315 630,017 6,457,796 5,045,153 165,120 541,775 706,895 552,262 2,304,344 2,816,540 630,017 5,750,901 4,492,891 (495,030) (343,334) 170,588 (667,775) (521,700) 11/24/98 Page 1 EAST ELK RIVER PROJECT July 1998 Construction Estimates Storm Proiect Costs Construction Overhead Land Acquisition South of CR 12 North of CR 12 Railroad Crossing Total Costs Revenues High Priority Project $ TEA 21 Trott Brook Farms Assessment MSA Funds (Land N of 12) Total Identified Revenues Balance to be Funded Other Financin.q Sources TIF 18 TIF 19 SWM Tax Levy Tax Levy Other Financing to be identified (amount from above sources not yet determined) Streets Sewer TOTAL 1,976,598 1,621,527 3,598,126 553,448 454,028 1,007,475 458,500 458,500 300,000 300,000 508,992 508,992 3,797,538 2,075,555 5,873,093 2,400,000 2,400,000 264,320 183,680 448,000 295,764 264,457 560,220 300,000 300,000 3,260,084 448,137 3,708,220 (537,454) (1,627,418) (2,164,873) 508,992 508,992 (1,65S,881) 11/24/98 Page 2 EAST ELK RIVER PROJECT PROJECT SUMMARY Projected Shortfall Other Funding Sources TIF FUNDING TO BE IDENTIFIED Water Sewer Lift Station Streets* Storm Sewer* TOTAL 798,617 203,807 630,017 537,454 1,627,4'18 3,797,313 630,017 508,992 1,139,009 798,6'17 203,807 28,462 1,627,4'18 2,658,304 Possible Sources include: Additional TIF 19'* Tax Levy SWM Tax Levy Water and Sewer Funds MSA Other *Based on July Estimates **TIF 19 projections assume including some City costs. 11/24/98 Page 3