*Item 3.4.*
MEMORANDUM
Mayor and City Council
Lori Johnson, Finance Director
March 2'2, :2004
Consider Public Safety Facility and City Hall/Utilities Change
Orders
The following change orders have been requested on the city hall building project.
Bid Package Change Order Change Order
Contractor Number Number Amount
PUBLIC SAFETY BUILDING
Total
Previously Approved
Total Change Orders to Date
0.00
302,942.48
$ 3O2,942.48
Contractor
Bid Package Change Order Change Order
Number Number Amount
CITY HALL/PUBLIC UTILITIES
Spectra Contract Flooring
(Add carpet to Council Chambers)
Spectra Contract Flooring
(Council Chambers change)
Ceilings & Floors
(Ceiling changes in bathroom)
Albers Mechanical
(PR 38 & repiping 13 VAV boxes)
Regal Contractors
(PR's 31 & 33)
Reliance Electric
(Rewire room 124)
Reliance Electric
(PR 30)
21 4 4,467.27
21 5 415.00
20 1 400.00
34 3 3,550.00
9 3 1,345.00
38 5 550.00
38 6 4,300.00
Reliance Electric 38 7
(PR 28)
George Cook Construction 10 10
(PR 38 & 43)
George Cook Construction 10 11
(Council Chambers)
Roof Tech 13 3
(Garage exhaust curb relocation)
Roof Tech 13 4
(PR31)
Total
Previously Approved
Total Change Orders to Date
3,115.00
6,O75.O0
474.00
631.85
802.59
26,125.71
77,849.21
$1 O3,974.92
Action Requested
The City Council is asked to approve the change orders as noted above.