2.2. SR 04-26-2004TO:
FROM:
DATE:
SUBJECT:
PIEMORANDUM
Mayor and City Council
Lori Johnson, Finance Director
April 26, 2004
Consider City Hall/Utilities Project Change Orders
*ltemo~.2.*
The following change orders have been requested on the city hall building project.
Bid Package Change Order Change Order
Contractor Number Number Amount
CITY HALL/PUBLIC UTILITIES
Weidner's Mechanical Contractors
(PR's 39, 42 & 44)
Steinbrecher Painting
(Additional Corridor Painting)
Albers Mechanical
(PR 30)
Regal Contractors
(Added soffits)
Regal Contractors
(PR 43)
Regal Contractors
(Patch hole in Council Chambers)
Total
Previously Approved
Total Change Orders to Date
36 3 $3,915.00
22 2 194.00
34 4 10,548.33
9 2 680.00
9 4 772.00
9 5 289.OO
16,398.33
103,974.92
$120,373.25
Action Requested
The City Council is asked to approve the change orders as noted above.