MEMORANDUM
Item # 6.6.
TO:
FROM:
DATE:
Mayor and City Council
Scott Harlicker, Planning Assista~
December 21, 1998
SUBJECT: Update on Northstar Corridor
Project
At the December l0th meeting of the Northstar Corridor Development
Authority discussion centered on preliminary cost estimates and ridership
forecasts.
Preliminary Capital Costs
Preliminary capital cost estimates are included in your packet of information.
Capital costs include items such as:
· vehicles
· central facilities
· terminal trackwork and layup facilities
· Minneapolis CBD station
· corridor segments
Included under vehicles are locomotives and coaches. Included under central
facilities are track work and incidentals, central shop and equipment,
operations and control center, and property acquisition. Included in the
terminal trackwork and layup facilities are the track and layup facilities and
property acquisition. The Minneapolis CBD station includes just the costs
associated with station construction. The final item included in capital costs
are the various corridor segments.
The corridor between Minneapolis and East St. Cloud was divided into
different segments based on the distance between stations. For instance, the
corridor between Elk River and Big Lake was segment F and the corridor
between Anoka/Ramsey and Elk River was segment E. The costs for each of
the segments varied because of the different track improvements and system
upgrades needed. Different parking requirements for the stations, site
development and property acquisition costs also affected segment totals.
13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330 · TDD & Phone: (612) 441-7420 · Fax: (612) 441-7425
Mayor and City Council/Northstar
December 21, 1998
Page 2
Common elements included station platforms and shelters, ticket vending
machines and public address systems.
As part of developing preliminary cost estimates for each station, BRW
needed to include information regarding parking requirements. BRW did not
have the benefit of ridership forecasts when estimating parking
requirements. The cost estimates for the Elk River station included a 500
space parking lot. This estimate is high and will be reduced once the final
ridership analysis is completed.
The preliminary capital costs associated with the Elk River station is
$3,110,000. The costs for trackwork and system upgrades has not been
determined for each individual segment. Overall preliminary capital cost
estimates are as follows:
Corridor segments (Mpls. To E. St. Cloud)
Vehicles
Central Facilities
Terminal Trackwork
Minneapolis CBD
$34,710,000
$42,875,000
$18,760,000
$12,208,000
$ 9,800,000
$115,000,000
Potential Capacity Improvements 30 to 50 Million
Total 145 to 165 million
Preliminary Operational Costs
Preliminary operational costs included the costs of operating the commuter
railroad and the costs of operating a feeder bus service to the various
stations. For Elk River, two feeder bus lines were considered, one down
Highway 169 from Princeton and one from St. Michael. The preliminary
operational costs are as follows:
Commuter Rail $9,500,000
Feeder Bus $ 651,000
Total $10,151,000
The consultants compared these preliminary costs to other start up
commuter systems in the country and found the costs for the Northstar
\\elkriver\sys\shrdoc\planning\scott\ncdadec.doc
Mayor and City Council/Northstar
December 21, 1998
Page 3
Corridor compare quite favorably. They seemed to feel the project is feasible
in terms of both capital and operational costs.
Ridership Forecast
Ridership estimates also came in favorably. Ridership at start up (2003) was
estimated at 7350 rides per day and in the year 2020, increase to 8200 rides
per day. The consultant estimated that in the year 2003, 939 people would
board the train in Elk River and go into Minneapolis. The ridership estimates
were better than average when compared to other commuter railroad
systems. The consultant estimated that 87% of the people riding the train
would be commuting to work and 97% would be commuting in the peak
direction.
CBD Visioning Process
As part of the Central Business District visioning process, the public
improvement committee will be gathering information to assist in possible
station locations and designs. During the initial meeting on October 23rd , one
of the topics that kept being brought up was the desire to have the station
downtown. Other possible locations include east Elk River along Tyler Street
and the northeast side of the Proctor Avenue railroad crossing.
\\elkriver\sys\shrdoc\planning\scott\ncdadec.doc
DEC 03 '98 12:11 T0-2412701 FROH-UCHARDS0N,R[TCti£R &ASSOC. T-660 P. 02/02 F-164
NORTHSTAR CORRIDOR DEVELOPMENT AUTHORITY
Thursday, December 10, 1998
Sherburne County Government Center
Elk River, MN
Minutes of the November 6, 1998 Meeting*
Preliminary Service Concepts*
Action Re(!_uested
Approval
Information
Ridership Forecasts (to be presented at meeting1
a. Northstar Corridor
b. Comparison to Mn/DOT Study*
c. Comparison to Existing Systems
Information
Capacity Modeling - Potential Capital
Improvements~
Information
5. Preliminary Capital Costs*
Information
6. Preliminary Operating Costs*
Information
Executive Committee Report
e. 1999 Legislative Sea,ion
b. Tour of California Commuter Rail System
c. Joint Powers Agreement - Appointments
d. Contracts for 1999 1, SRW
2. Richardson, Richter & Associates
3. Ken Stevens
Consider Committee
Reoommenclat~on8
8. Overview of Mn/DOT Phase !1 Commuter Rail Information
6tudy*
9. Other: Next Meeting
NOTE; The Legislative I~eception will follow the NCDA Meeting at 5:30 p.m.
at the Riverwood Conference Center.
DRAFT DRAFT DRAFT
NORTHSTAR CORRIDOR DEVELOPMENT AUTHORITY
Regular Meeting Minutes
November 5, 1998
The Northstar Corridor Development Authority met on November 5, 1998, at the
Sherbume County Government Center in the City of Elk River, Minnesota.
The following members, alternates and citizens were present:
Steve Billings, Hank Duitsman, Scott Harlicker, Paul Ostrow, Tom Gamec, J. Patrick
Cairns, Richard G. Turch, Jerry Leese, Ewald Peterson, John Norgren, Paul Goenner,
Lewis Stark, LeRoy Pauley, Thomas Cruikshank, Dan Erhart, Paul McCarron, Tim
Yantos, Duane Grandy, Gary Erickson, Betsy Wergin, Gerry. Donlin, Ken Paulson, Jim
Dickinson, Roger Fraser, Donald Jolly, Mike Christensen, David Mahle, Ken Stevens,
Biz Colbum, Dick Wolsfeld, Stephanie Eiler, David Loch, Jim Barton, Brian Roper, Rick
Speak, Carl Yilek, Mike Robertson, Jean Keely, Lona Schrerber, Marcia Bennett, Mary
Richardson, Lynn George
o
o
The Chairperson called the meeting to order at 3:00 p.m.
A motion was made by J. Patrick Cairns, seconded by Duane Grandy and
carded unanimously to approve the agenda of November 5, 1998, with no
additions and the meeting minutes of October 1, 1998, regular meeting minutes as
presented.
Tim Yantos provided an update on the Federal Funding indicating that Congress
did approve the $6,000,000 funding for the Northstar Corridor Development
Authority.
Tim Yantos introduced David Mahle, formerly with BNSF, who presented a
report on the initial simulation results of the BNSF capacity modeling study.
Biz Colburn, BRW, Inc. reviewed the draft Purpose and Need Statement
presented by BRW, Inc. The goal of the project is to meet the future
transportation needs of the Northstar Corridor.
A motion was made by Paul McCarron, seconded by Gerry Donlin, and carried
unanimously to approve the Purpose and Need Statement dated October 28, 1998
as amended.
o
o
Dick Wolsfeld, BRW, Inc. reviewed the steps of the federal process for the Major
Investment Study. The NCDA then preceeded to conduct the fatal flaw analysis
and eliminated transportation alternatives deemed to be too costly, infeasible or
ineffective in meeting the transportation needs of the corridor.
A motion was made by Hank Duitsman, seconded by Duane Grandy, and carried
unanimously to approve the following multimodal investment alternatives: - No Build
- Transportation Management/Bus Improvements
- Feeder Bus Improvements, Commuter Rail
- Feeder Bus Improvements, Commuter Rail, Trunk Highway 10 Minor
Upgrade
o Feeder Bus Improvements, Commuter Rail, Trunk Highway 10 Minor
Upgrade, River Crossings
Stephanie Eiler, Anoka County, updated the members on the Mn/DOT Commuter
Rail Study.
A motion was made by Paul McCarron, seconded by Scott Harlicker to request
That the Northstar Corridor Steering and Advisory Committee draft a letter to be
directed to Mn/DOT detailing the desire of the Northstar Corridor Development
Authority to communicate it's desire not to stop the commuter rail at the City of
Ramsey.
The members received a copy of the draft Implementation/Business Plan of the
Twin Cities Metropolitan Commuter Rail Study Steering and Advisory
Committees dated September 30, 1998.
General discussion was held on the governance of commuter rail. A request was
made to obtain samples of governance's of current operating commuter rail
systems.
A motion was made by Steve Billings, seconded by Tom Gamec and carried
unanimously to forward the proposed commuter rail planning and project
development process draft #3 dated October 29, 1998 to MN/DOT with a letter of
request considering this model.
Biz Colbum, BRW, Inc. presented a summary of the Commuter Rail Open House
Public Informational Meetings held in Elk River, St. Cloud and Fridley.
10.
A request was received from the Watab Township Board requesting membership
to the Northstar Corridor Authority. A motion was made by J. Patrick Cairns,
seconded by Richard Turch and carried unanimously to approve membership to
the Northstar Corridor Authority of the Watab Township Board. Mary
Richardson, Richardson, Richter & Associates, Inc. will be in contact with the
Steve Peka, Watab Township Board, to request member and alternate
appointments.'
11. Paul McCarron presented an updated on the 1999 Legislative Activities.
12.
The next meeting of the Northstar Corridor Development Authority is scheduled
for Thursday, December 10, 1998, at 3:0 0 p.m. at the Sherburne County
Government Center. At the conclusion of this meeting, legislators along the
corridor will be invited to a reception and briefing on the Northstar Corridor.
13.
Stephanie Eiler and Tim Yantos, Anoka County, distributed informational
articles on various corridors c,urrently operating.
14.
A motion was made by Richard Turch, seconded by J. Patrick Cairns and carried
unanimously to adjourn the meeting at 5:30 p.m.
Betsy Wergin, Chairperson Dated
Northstar Corridor Weekday Commuter Rail Service
Service Concept A
7:IOAM 8:I5AM
5:25 PM 5~.'35~ 6:05 PM
BRW. h~c. 12/02/98
Northstar Corridor Weekday Commuter Rail Service
Service Concept B
BRW, Inc. 12/02198
BRW, Inc. / DJM
Preliminary Capacity Modeling
and
Potential Capital Improvements
B..Rw_ .....................................
DAMES & MOORE GROGP COMPANy
MEMORANDUM
BRW
Thresher Square
700 Third Street South
Minneapolis, MN $5415
Phone: (612) 370-0700
Fax: (612) 370-1378
To: Tim Yantos
From: David Mahle
Copy: Dan Meyers File:
33935-001-0702
Date:
Subject:
December 3, 1998
NCDA/BNSF Line Capacity Simulation Results
Line capacity simulations have been performed by BNSF, using the Dispatch Planning Model, to
determine the amount of additional trackage and signaling that will be required to support
commuter rail operations while maintaining the level of freight service that is expected to exist in
the startup year 2003. To do this BNSF first developed a base case with 2003 expected traffic
levels and operational changes. Commuter service was then started on the system and various
capacity improvements were added to gauge their effect. The simulation does not give an optimal
answer automatically but rather is used in a series of iterations to determine impacts of
combinations of capacity improvements.
There are two primary statistical measures that are used by BNSF to determine the impacts of
capacity improvements. The first is freight transit time per 100 miles. This measure indicates by
train class and for all freight trains the time required by a train to go 100 miles. It includes actual
running time, delays due to congestion and meeting other trains, and dwell time at terminals. The
second measure is freight train delay per 100 miles. This is a component of transit time and is the
most important measure of congestion and lack of capacity. These measures are also developed
for Amtrak and commuter trains but are not important indicators as these trains have the highest
dispatching priority and vary little in running time or delay regardless of the number of freight
trains or level of congestion in the system.
The attached status information indicates these key measures for the 2003B base case and a
series of simulations with the commuter train schedules added to the system. Five different
combinations of upgrades are indicated together with the impact on the two key measures
discussed above.
DJM:mr
NCDA/BNSF CORRIDOR SIMULATION STATUS
SERVICE CONCEPT B
FREIGHT FREIGHT
SIMULATION MAP
TRANSIT DELAY DESCRIPTION
SCENARIO KEY
TIME (min) TIME (rain)
2003B BASE 360.9 32.5 Opening year rail traffic with no commuter rail service
NO UPGRADE 383.3 53.5 Opening year rail traffic with commuter rail service
UPGRADE I 379.2 52.1 A Double track Becker to Big Lake
B CTC Big Lake to Coon Creek
C Double crossovers at Becker, MP 51.2 and MP 45.1
D Double crossovers at Elk River, MP 32.9 and Ramsey
UPGR.~DE 2 368.5 39.8 E Double track 43rd Ave to 35th Ave (Northtown Yard)
F Double track west leg of wye at Minneapolis Junction
G Double track Minneapolis Junction to Union Yard
H Upgrade siding between Harrison St and Holden St to second main track
B CTC Big Lake to Coon Creek
I CTC Harrison St to Holden St
D Double crossovers at Elk River, MP 32.9 and Ramsey
J Double crossover at 43rd Ave
K Single crossover at MP 11.3 on Wayzata Sub
L Upgrade turnout at MP 11.7 on Wayzata Sub
M Upgrade double crossovers at MP 11.3 on Midway Sub to 30/25 mph
N Upgrade mainline between 35th Ave and Minneapolis Junction to 70/45 mph
UPGRADE 3 366.0 37.8 Combination of UPGRADE 1 and UPGRADE 2
UPGRADE 6 361.5 34.0 UPGRADE 3 with the following revisions:
O Add sidings at Anoka and Coon Creek for local trains to work off of main line
UPGRADE 7 360.1 34.3 UPGRADE 6 with the following revisions:
J No double crossover at 43rd Ave
K No single crossover at MP 11.3 on Wayzata Sub
N Upgrade mainline between 35th Ave and Minneapolis Junction to 45/45 mph (not 70/45 mph)
F No Double track west leg of wye at Minneapolis Junction - upgrade to 20 mph, including two switches
DJM/BRW 12/02/98
Sartell
Benton
Haven
Stearn,,
Clearwater
Sherburr~e
Becker
Township
Isanti
Wright
Big Lake
Township
Township
Anokai
Albertvill
Dayton
Andover
31ai~
Potential
Station Location
(~ Capacity Improvement (see attached list)
Potential Commuter Rail
Capacity Improvements
St. Cloud/Rice to Coon Rapids
Maple
Grove
Brooklyn
Park
Coon
Blaine
Mou ~ds
ViE
Brooklyn
1-694
Henne
Minnea
Potential
Station Location
Capacity Improvement (see attached list)
December 3, 1998
Potential Commuter Rail
Capacity Improvements
Coon Rapids to Minneapolis
BRW, Inc.
Preliminary Capital Cost Estimate
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SUMMARY OF CAPITAL COST ESTIMATES
POTENTIAL ADDITIONAL
COST ELEMENT COMMUTER RAIL CAPACITY CAPITAL GRAND TOTAL
BASIC ELEMENTS IMPROVEMENTS * IMPROVEMENTS (1999 DOLLARS)
MINNEAPOLIS CBD TO EAST ST. CLOUD
CORRIDOR SEGMENTS
SEGMENT A - MINNEAPOLIS CBD TO NE MINNEAPOLIS 2,086,000
SEGMENT B - NE MINNEAPOLIS TO FRIDLEY 3,220,000
SEGMENT C - FRIDLEY TO COON RAPIDS 3,696,000
SEGMENT D - COON RAPIDS TO ANOKNRAMSEY 7,602,000 -
SEGMENT E - ANOKNRAMSEY TO ELK RIVER 4,354,000 -
SEGMENT F - ELK RIVER TO BIG LAKE 2,828,000
SEGMENT G - BIG LAKE TO BECKER 2,156,000
SEGMENT H - BECKER TO CLEAR LAKE 2,156,000
SEGMENT I - CLEAR LAKE TO EAST ST. CLOUD ;~,212,000
SUBTOTAL 30,310,000
VEHICLES 42,875,000
CENTRAL FACILITIES 18,760,000 -
TERMINAL TRACKWORK & LAY-UP FACILITIES 12,208,000 -
MINNEAPOLIS CBD STATION 9,800,000
MINNE-APE~L~,~-~) EAST CLOUD TOTAL (1999 DOLLARS) $114 million $30 - 50 million $144 - 164 million
EAST ST. CLOUD TO ST CLOUD CBD TOTAL (1999 DOLLARS) $2.3 million $1.0 - 2.0 million $3.3 - 4.3 million
I~AS'F-$T. CLOUD-'F0--Ri~E-~O-'~Ai~ (~999 DOLLARS) $2.1 million $3.0- 5.0 mill-io~- - $5.1- 7.1 million
* Estimated range of capital costs for potential railroad capacity improvements.
BRW, Inc. ~ [~ u/~ ~ ~ Con-b-OI.xls[SUMMARY] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM -- SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
COMMON SYSTEM ELEMENTS
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST ELEMENT UNITCOST
QUANTITY COST QUANTITY COST QUANTITY COST
VEHICLES
LOCOMOTIVES EA 2,700,000 5 13,500,000
---'-~OACHES EA 1,300,000 9 11,700,000
.... ~O~'R~OL COACHES EA 1,820,000 5 9,100,000
- E~NGiNEER~NG' ETC. (15%) 5,145,000 _
CONTINGENCY (10%) 3,430,000
- S~U B~rOTA L 42,875,000
CENTRAL FACILITIES
TRACKWORK & INCIDENTALS LS 5,000,000 1 5,000,000
CENTRAL SHOP & EQUIPMENT LS 6,000,000 I 6,000,000
OPERATIONS CONTROL CENTER LS 2,100,000 1 2,100,000
PROPERTY ACQUISITION LS 300,000 1 300,000
ENGINEERING, ETC. (20%) 2,680,000
CONTINGENCY (20%) 2,680,000
SUBTOTAL 18,760,000
TERMINAL TRACKWORK & LAY-UP FACILITIES
TERMINAL TRACKWORK & LAY-UP FACILITIES EA 4,300,000 2 8,600,000
PROPERTY ACQUISITION LS 60,000 2 120,000
ENGINEERING, ETC. (20%) 1,744,000
---~3oN~I-N G~'Nc~-(20%) 1,744,000
SUBTOTAL 12,208,000
MINNEAPOLIS CBD STATION
.... MiNNEAPOLiS CBD STATION LS 7,000,000 1 7,000,000 ___ -
ENGINEERING, ETC. (20%) 1,400,000 ___
CONTINGENCY (20%) 1,400,000 __
--- s~UBTOTAL 9,800,000
BRW, Inc. ~) [~ ~ [~ c~ Con-b-01.xls[COMMON] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT A - MINNEAPOLIS CBD TO NE MINNEAPOLIS APPROX. LENGTH (MI): 3.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT
COST ELEMENT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (NE MINNEAPOLIS)
PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 - -
TICKET VENDING MACHINE EA 115,000 2 230,000 - -
PUBLIC ADDRESS & VMS EA 105,000 2 210,000 - -
SITE DEVELOPMENT / INCIDENTALS EA 300,000 1 300,000 - -
SURFACE PARKING SPACE 2,500 -
PROPERTY ACQUISITION ACRE 180,000 -
SUBTOTAL 1,490,000 -
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000 -
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 -
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 -
CROSSING SURFACE (NEW/UPGRADE) FT 675 -
SUBTOTAL -
CIVIL I STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS -
SUBTOTAL -
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 1,490,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 298,000
CONTINGENCY (20%) 298,000
TOTAL (1999 DOLLARS) 2,086,000
BRW, Inc E~ E~ z~ [~ c~ Con-b-01.xls[SEGA1 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT B - NE MINNEAPOLIS TO FRIDLEY APPROX. LENGTH (MI): 6.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST ELEMENT UNIT COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (FRIDLEY)
PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 _210,000
SITE DEVELOPMENT / INCIDENTALS EA 250,000 1 250,000
SURFACE PARKING SPACE 2,500 200 500,000
PROPERTY ACQUISITION ACRE 180,000 2 360,000
SUBTOTAL 2,300,000
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) Mi 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000_
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL -
CIVIL / STRUCTURES
EARTHWORK / STRUCTURES LS 2,000,000
MODIFY STRUCTURES LS 3,000,000
SUBTOTAL '
SYSTEMS
SIGNALING/CTC_(N_~_W/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 -
SUBTOTAL -
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 2,300,000 - '
ADD-ONS
-- E'NGiNEERiNG, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 460,000 -
CONTINGENCY (20%) 460,000
TOTAL (1999 DOLLARS) 3,220,000 __ _ - _____ -
BRW, Inc. [~ ~ ~/~ [~ c~ Con-b-01.xls[SEGB] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT C - FRIDLEY TO COON RAPIDS APPROX. LENGTH (MI): 5.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (COON RAPIDS)
PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
SITE DEVELOPMENT / INCIDENTALS EA 250,000 1 250,000
SURFACE PARKING SPACE 2,500 300 750,000
PROPERTY ACQUISITION ACRE 180,000 3 450,000
SUBTOTAL 2,640,000 -~ -
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL
CIVIL ! STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS
SUBTOTAL
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 -
SUBTOTAL -
RIGHT-OF-WAY SF 4.00 -
CONSTRUCTION SUBTOTAL 2,640,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 528,000
CONTINGENCY (20%) 528,000
TOTAL (1999 DOLLAR S) 3,696,000
BRW, Inc [~ [~ //~ E~ c~ Con-b-01.xls[SEGr" 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT D - COON RAPIDS TO ANOKA/RAMSEY APPROX. LENGTH (MI): 9.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST ELEMENT UNIT COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (ANOKA/RAMSEY)
-- PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 ___
TICKET VENDING MACHINE EA 115,000 I 2 230,000
PUBLIC ADDRESS & VMS EA 105,0002 210,000
- ~I~EDEVELOPMENT / INCIDENTALS EA 300,000 1 300,000
SURFACE PARKING SPACE 2,500 1,000 2,500,000
PROPERTY ACQUISITION ACRE 180,000 8 1,440,000
SUBTOTAL 5,430,000
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 __
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL
CIVIL / STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS
SUBTOTAL
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 5,430,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 1,086,000
CONTINGENCY (20%) 1,086,000
T__0_'FAL (19~99_ DOLLARS) 7,602,000
BRW, Inc, [~ [~ z~ [~ ~ Con-b-01.xls[SEGD] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT E - ANOKA/RAMSEY TO ELK RIVER APPROX. LENGTH (MI): 9.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (ELK RIVER)
PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
SITE DEVELOPMENT / INCIDENTALS EA 200,000 I 200,000
SURFACE PARKING SPACE 2,000 500 1,000,000
PROPERTY ACQUISITION ACRE 180,000 4 720,000
SUBTOTAL 3,110,000 - '
TRACKWORK
TRACK: 136# RAILJCONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000 - .~__
TURNOUT: #24 (NEW/UPGRADE) EA 185,000 ....
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675 __
SUBTOTAL -
CIVIL ! STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS
SUBTOTAL -
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 _
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 _
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 ...................
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 3,110,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 622,000
CONTINGENCY (20%) 622,000
TOTAL (1999 DOLLARS) 4,354,000
BRW, Inc I~ [~ /~ [~ c[~ Con-b-01.xls[SEGF~ 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT F - ELK RIVER TO BIG LAKE APPROX. LENGTH (MI): 9.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST ELEMENT UNIT COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (BIG LAKE)
"PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
- SITE DEVELOPMENT/INCIDENTALS EA 150,000 1 150,000
SURFACE PARKING SPACE 2,000 200 400,000
PROPERTY ACQUISITION ACRE 140,000 2 280,000
-'- SU-B-TOTAL 2,020,000
TRACKWORK ....................
' TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
..... CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL -
CIVIL / STRUCTURES _
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS _
SUBTOTAL ' ' '
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
----CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
--~ROSsiNG SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL ' ' '
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 2,020,000 -
ADD-ONS
.... i=N~INEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 404,000
.... ~;(~NTINGENCY (20%) 404,000
2,828,000 -
_T_OTAL_(_~199--9 DOLLARS) __ _
BRW, Inc. D [~ ~ ~ ~ Con-b-01.xls[SEGF] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT G - BIG LAKE TO BECKER APPROX. LENGTH (MI): 8.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT
COST ELEMENT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (BECKER)
PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000 . -
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000
SURFACE PARKING SPACE 1,500 100 150,000
PROPERTY ACQUISITION ACRE 100,000 I 100,000
SUBTOTAL 1,540,000
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL
CIVIL ! STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS
SUBTOTAL
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
(~ONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 1,540,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 308,000
CONTINGENCY (20%) 308,000
TOTAL (1999 DOLLARS) 2,156,000 -
BRW, Inc [~) E~ Z~ [~ c~ Con-b-01.xls[SEG~] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT H - BECKER TO CLEAR LAKE APPROX. LENGTH (MI): 7.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (CLEAR LAKE)
-"-P~_AT-F-O-FiM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000 ......
SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000
SURFACE PARKING SPACE 1,500 100 150,000
PROPERTY ACQUISITION ACRE 100,000 1 100,000
SUBTOTAL 1,540,000
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL
CIVIL / STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS
SUBTOTAL
SYSTEMS
.... ~I~i-ING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 1,540,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 308,000
CONTINGENCY (20%) 308,000
TOTAL (1999 DOLLAR S) 2,156,000
BRW, Inc. D [~ /~ E~ c~ Con-b-01.xls[SEGH] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT I - CLEAR LAKE TO EAST ST. CLOUD APPROX. LENGTH (MI): 11.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (EAST ST. CLOUD) __
PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
SITE DEVELOPMENT / INCIDENTALS EA 100,000 I 100,000
SURFACE PARKING SPACE 1,500 100 150,000
PROP ERTY ACQUISITION ACRE 140,000 1 140,000
SUBTOTAL 1,580,000
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000 _ '
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL -
CIVIL ! STRUCTURES
EARTHWORK / STRUCTURES LS -
MODIFY STRUCTURES LS -
SUBTOTAL -
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000 -
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 - -
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 -
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL -
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 1,580,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 316,000
CONTINGENCY (20%) 316,000
TOTAL (1999 DOLLARS) 2,212,000 -
BRW, Inc [~ ~ ~ E~ c~ Con-b-01.xts[SEG" 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT J - EAST ST. CLOUD TO ST. CLOUD CBD APPROX. LENGTH (MI): 1.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (ST. CLOUD CBD)
PLATFORM, SHELTER, LiGHTiNG, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000
SURFACE PARKING SPACE 2,000100 200,000
PROPERTY ACQUISITION ACRE 180,000 1 180,000
SUBTOTAL 1,670,000
TRACKWORK
TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
CROSSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL
CIVIL ! STRUCTURES
EARTHWORK / STRUCTURES LS
MODIFY STRUCTURES LS
SUBTOTAL
SYSTEMS
SIGNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000
SUBTOTAL
RIGHT-OF-WAY SF 4.00
CONSTRUCTION SUBTOTAL 1,670,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 334,000
CONTINGENCY (20%) 334,000
_TgT_A_L_(!999 DOLLAR~S)_ 2,33S,000
BRW, Inc. [~ E~ & [~ c~ Con-b-01.xls[SEGJ] 12/03/98
NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY
COMMUTER RAIL SYSTEM - SERVICE CONCEPT B
PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS)
SEGMENT K - EAST ST. CLOUD TO RICE APPROX. LENGTH (MI): 15.0
COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL
UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS
COST ELEMENT UNIT COST
QUANTITY COST QUANTITY COST QUANTITY COST
STATION (RICE)
--~I~F~)R-I~,~S-HELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000
TICKET VENDING MACHINE EA 115,000 _ 2 230,000
PUBLIC ADDRESS & VMS EA 105,000 2 210,000
SITE DEVELOPMENT / INCIDENTALS EA 50,000 I 50,000
SURFACE PARKING SPACE 1,500 100 150,000 __
PROPERTY ACQUISITION ACRE 100,000 I 100,000
SUBTOTAL 1,490,000
TRACKWORK
---~P~A'CK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000
TURNOUT: #20 (NEW/UPGRADE) EA 170,000
TURNOUT: #24 (NEW/UPGRADE) EA 185,000
CROSSOVER: #20 (NEW/UPGRADE) EA 345,000
C~(~SSOVER: #24 (NEW/UPGRADE) EA 378,000
CROSSING SURFACE (NEW/UPGRADE) FT 675
SUBTOTAL ' '
CIVIL I STRUCTURES
--- EA~T~W-~-~-t~ STRUCTURES ES
MODIFY STRUCTURES LS
SUBTOTAL -
SYSTEMS
$1GNALING/CTC (NEW/UPGRADE) MI 75,000
CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000
CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000
CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000
CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 - _
SUBTOTAL -
i RIGHT.OF-WAY SF 4.00 -
CONSTRUCTION SUBTOTAL 1,490,000
ADD-ONS
ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 298,000
CONTINGENCY (20%) 298,000
TOTAL (1999 DOLLARS) 2,086,000
BRW, In~ [~ ~ /r~ [~ ~ Con-b-01.xls[SEG'" ~2/03/98
Manuel Padron and Associates
Preliminary
Operations and Maintenance Cost Estimate
and
Feeder Bus Network System
I
NORTHSTAR - DIESEL C:OMMUTER RAIL O&M COST MODEL
TABLE 1. INPUT VARI.~'~BLES
VARIABLE
SYSTEM CHARACTERISTIC! NAME
Annual Train Tdps '
Peak Gallery Passenger Cars'
Fleet Gallery Passenger Cars
Peak Trainsets (Locomotives):
Fleet Locomotives
Annual Revenue Train-Hours:
Annual Train-Miles (incl. deadhead)
Annual Car-Miles (incl. deadhead)
Leased Directional Route-Mil(~s
Owned Directional Route-Miles
Total Stations
Storage & Maintenance Yard -
Layover Yard
NORTHSTARJ
CONCEPT
TRIPS 2,595
PKCAR 12
TOTCAR 14
PKLOCO 4
TOTLOCO 5
TRAINHR 7,120
TRAINMI 272,550
CARMILE 817,650
RTMILE 95.1
RTMILE2 0
STATION 11
YARD 1
LYARD 2
Prepared by Manuel Padron & Associates, In,~.
i
11/25/98 01:4-3 PM
NORTHSTAR - DIESEL COMMUTER RAIL O&M COST MODEL
Line Item Detail
CONCEPT B
i
~ASELINE PRODq'Y
COST ITEM EXPENSE FACTOR
DRIVING STAFF ESTIMATED DEPT
VARIABLE (FTEs) COST COS'F
OPERA TING AGENCY EXPENSE$
100 Director of Operations
Labor 100
Professional Services 100
Miscellaneous 100
200 Budget & Finance
Labor 200
Office space/Equip.,etc. 200
Revenue Servicing 200
Other Professional Services 200
Miscellaneous 200
Insurance (Risk Management 200
300 Marketing/Customer Service
Labor 300
Print./Promo. Matls./Postage 300
Professional Services 300
Media Placemont/Spec. Even 300
Miscellaneous 300
400 Technical Service,,
Labor
Materials & Supplies-Facilifie
PNTVM Field Maintenance
Fare Inspection
Communications 400
Diesel Fuel 400
Yard/Lead Track Maint. 400
Station & Parking Lot Maint. 400
Other Services 400
Utilities - Stations 400
Utilities - Yard 400
Miscellaneous 400
Subtotal Operating Agency
CONTRA CT OPERA TOR FUNCTIONS
500 Train Operations
Labor - Engineers 500
Labor. Conductors 500
Train Crew Expenses 500
Standby Electricty 500
600 Maintenance
Equipment Serv./Shop Exp. 600
Material, Parts & Handling 600
Services Subcontracts 600
Subtotal Conb'actor O & M
700 Contract Operator Fees
Trans. Supervision & GA 700
Overhead & Management Fe 700
Performance Payments 700
Subtotal Contract Ope/ator
PA YMEN TS TO RA ILROA D
800 Track Access/Usage Fees 800
TOTAL COST
$165,230 0.0'21
$135,000 $2,813
$16,000 $8,000
F+PKCAR 1.0 $82,615
PKCAR $33,750
#100 FTEs $8,000
$175,200
$143,950
$352,000
$30,000
$4,700
'1,800.000
0.021 F+PKCAR 2.0 $116,800
$7,576 #100-400 FTEs $90,916
$19,556 STATION $215,111
$625 PKCAR $7,500
$1,567 #200 FTEs $3,133
$1.17 CARMILE $955,754
' $313,210 0.001 F+TRIPS 5.0 $261,008
$104,000 $35 TRIPS $89,960
$205,100 $68 TRIPS $177,412
$252,000 $84 TRIPS $217,980
$14,500 $2,417 #300 FTEs $12,083
400 . $411,380 0.104 F+PKCAR 4.0 $205,690
400 $42,500 $2,125 TATION+YARD $25,500
400 $40,000 $2,222 STATION $24,444
A.~lumed to be handled by Conductors aboard trains and other agencies.
$138,500 $17,313 PKLOCO $69,250
$2.06 TRAINMI $560,090
$60,000 $20,000 YARD+LYARD $60,000
$700,000 $38,889 STATION $427,778
$ 70,000 $6.19 TRAIN H R $44,102
$100,000 $5,556 STATION $61,111
$97,000 $32,333 YARD+LYARD $97,000
$14,000 $1,750 #400 FTEs $7,000
'12. o
$80,452 940 PRODHRS 8.0 $643,617
· $68,740 940 PRODHRS 8.0 $549,921
· $122,000 $3,211 #500 FTEs $51,368
$60,000 $30,000 LYARD $60.000
02,336,800 $1.52 CARMILE $1.240,782
$648,220 $0.42 CARMILE $344,188
$554,240 $11,547 PKCAR $138,560
~: 870452.35
$492,660 7.2% of Subtotal $219,379
$798,828 8.0% of Subtotal 5242,275
$437,026 $1.32 TRAINMI $360,461
~3,346,000 $19,120 RTMILE $1,818,312
$124,365
$1,389,215
$758,443
$1,581,966
53,853.989
$1.304,907
$1,723,530
$3,028,437
S822,115
$3,850,552
$1,818.312
$9,522,853
ICost per Train-Hour:
Cost per Train-Mile:
Cost per Car-Mile:
$1,3371
$34.94
$11.65
Prepared by Manuel Padron & Associates, Inc. 11/25/98 01:52 PM
NORTHSTAR COMMUTER RAIL PROJEC,r
SCHEDULE B -- SERVICE TO ST. CLOUD
ISTA./AGE NCWRTE. 'I'
~DESCRIPTION
' Metro 10
i Metro 18,
Mel3'o 24
Metro 29
NE Minn.'(Lowry Option)
Metro 18
Metro 32
Metro 10F,U
Metro 24
Metro 879
Coon Rapids (Foley)
Anoka 889
Anoka ~05
Anoka 831
Anoka
Anoka 890
Molto 27 '
Anoka 805
Anoka 8,31
Anoka 842
Ramsay
Anoka ~91
Elk River
River R. 901
Big Lake
River R. 902
Backer
Tri-CAP 903
;leer Lake
River R. 904
S. St. CIm~d MTC Eastside
MTC Rice
St. Cloud CBD
MTC
,Provide transfer al station; no reroute necessary.
Reroute Washington St. branch via Broadway, Quincy, 15th Ave.
Provide transfer at stalio~; no reroute necessary.
P..Eovide transfer at stalfon; no reroute necessary.
Reroute Washington St. ~anch via 22nd Ave., 6th St., Lowry.
Provide transfer at stalJon; no re. route_n_ .e~e..~_s. sary.
Route via 61st Ave. to station.
Route via 61st Ave. to station.
Eliminate 4 AM Express SB trips (Iv. N'tovm @ 6:18, 7:22, 7:52, 8:22).
Eliminate 4 PM Express NB tripe (iv. 7thl3rd @ 3:40, 5:10, 5:45, 6:10).
New Rdute from Brookdale -CR sta0on - Apache Plaza via Shingle
Creek Pkwy, 1-694, University, CR 102, Main St., 61st, Un'~vereR7, 37th~'
New route from Bethel- CR station via 237th, Rt 65, Rt 14, Rt 51, Foley.
· ' · I~,7
~-'i;',~ ;,-,& ,6 G .............................. 7: :25 ........
IEliminate 5 PM NB trips (Iv. 7th/3rd @ 4:19, 4:37, 4:58, 5:03, 5:40).
Reroute via Woodcrest, 99th Ave., Foley, CR stain, Foley,.RL10.
Increase AM, PM peak pe~xl frequency to 30 minutes.
jlncresse AM, PM peak period fTequenc¥ to 30 minutas.
iNew route fm St. Francis - CR Sta via Rt 47, Industry, VoTech, Rt 10, 7ih.
Provide transfer at station; no rerc~te neoessary.
Provide ~ansfer at station; no reroute necessary.
llProvide transfer at station; no reroute necessary.. ·
j .P~_~_ovid~e~nsf_~er at _station; no rer__oute necessary. . ......
~New STV circulator via OR station, Vo'rech, Industry Ave., Nov/then,
Ramsoy Blvd., 155th, Variolite, 161st, Armstrong Blvd., Rt.10/169.
New route from Princeton - CR stalion - St. Michael via Rt.169,181st.,
_Rt.._!.69_,.R_t._3_9_/B_r_o._a~lv/a~_ St.. Rt. 1 g/La Beaux, Central Ave.
lew route from Buffalo to CR station via Rt.25.
!_e)v._r..0u. te_!r._o_m_.F_e,le_,v to CR station via Rt.25, Rt.10.
New route from I~mball - Annartdale - CR station vi~ Rt. 24.
!P~,,vide transfer at stati(~' no rerouta necessary.
route Rice - CR stati'on - MTC Transit Center via Rt.10, Rt.23.
Extend._a!!_M_T_C._r_~r{es_s_e. rving~Tr_a, nsit Center to CR station.
" SERVICE HEADWAY
PEAK BASE
NC NC
NC NC
NC NC
NC NC
~EAK
BUSES
NC
NC
NC
NC
NC NC NC
NC NC NC
NC NC
NC NC
NC NC
30 NA
NC
NC
NC
+2
60 NA +1
30 30 +1.5
30 30 +1.5
60 NA
NC NC
NC NC
NC NC
NC NC
.AI
+1
NC
NC
NC
NC
AVG. WKDY.
BUS-HR. BUS-MI.
NC NC
NC NC
NC NC
NC NC
NC
NC
X.X
X.X
NC
+12.0
+6.0
+9.0
+9.0
*6.0
NC
NC
NC
NC
NC
NC
Y-)
NC
y.y,
NC
NC
NC
NC
60 NA +1 +6.0 y.
+2' +12.0
60 NA
60 NA
60 NA
NC NC
60 6O
NC NC
+6.0
+1
+1
+6.0
+1 +6.0
NC NC
+1 +12.0
NC
NC
Y.)
y.)
Y-)
NC
Y.)
NC
NOTES:
~NC" refers to no change ~rorn e×isling.
Figure 7
PRELIMINARY RAIL RIDERSHIP RESULTS
NORTHSTAR CORRIDOR - Concept B to Downtown St. Cloud
Average Weekday Daily Ridership - Year 2005
Southbound to Minneapolis - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Downtown St. Cloud 71 40 3 15 74 54
East St. Cloud 58 40 3 15 60 54
Clear Lake 19 31 1 12 20 43
Becker 6 35 0 13 6 48
Big Lake 418 112 19 42 437 155
Elk River 466 408 21 154 487 562
Ramsey/Anoka 536 386 16 85 552 . 470
Coon Rapids 1,075 529 37 130 1,112 658
Fridley 1,218 327 75 131 1,293 458
NE. Minneapolis 0 413 0 182 0 595
Downtown Minneapolis
Total 3,867 2,321 174 779 4,041 3,099
Northbound to St. Cloud - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Downtown Minneapolis 9 10 0 4 9 14
NE. Minneapolis 0 5 0 2 0 7
Fridley 14 1 1 0 15 1
Coon Rapids 4 1 0 0 4 1
Ramsey/Anoka 4 0 0 0 4 0
Elk River 18 11 1 4 19 15
Big Lake 51 19 2 7 53 26
Becker 2 1 0 0 2 1
Clear Lake 2 8 0 3 2 11
East St. Cloud 1 1 0 0 1 1
Downtown St. Cloud
Total 105 57 5 22 110~ 79
Notes:
(1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the Anoka station.
(2) Includes driving to feeder bus station if available.
(3) Includes walking to feeder bus station.
12/08/1998
Figure 5
PRELIMINARY RAIL RIDERSHIP RESULTS
NORTHSTAR CORRIDOR - Concept B to Downtown St. Cloud
Average Weekday Daily Ridership - Year 2020
Southbound to Minneapolis - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Downtown St. Cloud 66 41 3 16 69 57
East St. Cloud 64 41 3 16 67 57!
Clear Lake 20 33 1 13 21 46
. Becker 8. 44 0 17 8 61
Big Lake 493 138 22 52 515 190
Elk River 576 508 26 192 602 700
Ramsey/Anoka 615 479 18 105 633 583
Coon Rapids 1,133 592 39 145 1,172 738
Fridley 1,244 330 76 132 1,320 461
NE. Minneapolis 0 436 0 192 0 628
Downtown Minneapolis
Total 4,219 2,643 188 879 4,407 3,521
Northbound to St. Cloud - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Downtown Minneapolis 5 10 0 4 5 14
NE. Minneapolis 0: 3' 0 1 0 4
I Fridley 16 I 1 0 17 1
Coon Rapids 5 2 0 1: 5 3
Ramsey/Anoka 5 0 0 0 5 0
Elk River 30 18 1 7 31 25
Big Lake 74 30 3 11 77 41
Becker 3 1 0 0 . 3 1
Clear Lake 2 11 0 4 2 1
5
East St. Cloud 2 2 0 1 2 3
Downtown St. Cloud
Total 142 78 6 29 148 107~
Notes:
(1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the Anoka station.
(2) Includes driving to feeder bus station if available.
(3) Includes walking to feeder bus station.
12/08/1998
Figure 8
PRELIMINARY RAIL RIDERSHIP RESULTS
NORTHSTAR CORRIDOR - Concept B to Rice
Average Weekday Daily Ridership - Year 2005
Southbound to Minneapolis - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Rice 71 2 3 1 75 2
East St. Cloud 158 41 7 15 165 56
Clear Lake 18 32 1 12 19 45
Becker 6 35 0 13. 6 48
Big Lake 417 112 19 42 436 155
Elk River 466~ 408 21 154 487 562
Ramsey/Anoka 536 386 16 85 552 470
Coon Rapids 1,075 529 37 130 1,112 658
Fridley 1,218 327 75 131 1,293 458
NE. Minneapolis 0 413: 0 182 0 595
Downtown Minneapolis -~ - -
Total 3,966 2,285 178 765 4,145 3,050
Northbound to Rice - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Downtown Minneapolis 9 10 0 4 9 14
NE. Minneapolis 0 5 0 2 0 7
Fridley 13 1 1 0 14 1
Coon Rapids 4 1 0 0 4 1
Ramsey/Anoka 4 0 0 0 4 0
Elk River 16 9 I 3 17 12
Big Lake 47 23 2 9 49 32
Becker 2 1 0 0 2 1
Clear Lake 2 9 0 3 2 12
East St. Cloud 0 0 0 0 0 0
Rice .
Total 97 59 4 22 101 81
Notes:
(1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the ^noka station.
(2) Includes driving to feeder bus station if available.
(3) Includes walking to feeder bus station.
12/08/1998
Figure 6
PRELIMINARY RAIL RIDERSHIP RESULTS
NORTHSTAR CORRIDOR - Concept B to Rice
Average Weekday Daily Ridership - Year 2020
Southbound to Minneapolis - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Rice 73 2 3 1 76 2
East St. Cloud 159 45 7 17 166 62
Clear Lake 20 33 1 13 20 46
Becker 8 44 0 17 8 61
Big Lake 493 138 22 52 5151 190
Elk River 576 508 26 192 602 700
Ramsey/Anoka 615 479 18 105 633 583
Coon Rapids 1,133 592 39 145 1,172 738
Fridley 1,244 330 76 132 1,320 461
NE. Minneapolis 0 436 0 192 0 628
Downtown Minneapolis
Total 4,320 2,607 193 865 4,513 3,472
Northbound to Rice - Boardings by Station of Origin (1)
Station Work Trip Other Trips All Trips
Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access
(2) (3) (2) (3) (2) (3)
Downtown Minneapolis 5 10 0 4 5 14
NE. Minneapolis 0 3 0 1 0 4
Fridley 15 1 1 0 16 1
Coon Rapids 5 2 0 1 5 3
Ramsey/Anoka 5 0 0 0 5 0
Elk River 26 17 I 6 27 23
Big Lake 62 31 3 12 65 43
Becker 4 1 0 0 4 1
Clear Lake 3 10 0 4 3 14
East St. Cloud 1 0 0 0 I 0
Rice - -
Total 126 75 6 28 132 103
Notes:
(1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the Anoka station.
(2) Includes driving to feeder bus station if available.
(3) Includes walking to feeder bus station.
12/08/1998