4.6. SR 12-21-1998'ity of iver MEMORANDUM Item # 6.6. TO: FROM: DATE: Mayor and City Council Scott Harlicker, Planning Assista~ December 21, 1998 SUBJECT: Update on Northstar Corridor Project At the December l0th meeting of the Northstar Corridor Development Authority discussion centered on preliminary cost estimates and ridership forecasts. Preliminary Capital Costs Preliminary capital cost estimates are included in your packet of information. Capital costs include items such as: · vehicles · central facilities · terminal trackwork and layup facilities · Minneapolis CBD station · corridor segments Included under vehicles are locomotives and coaches. Included under central facilities are track work and incidentals, central shop and equipment, operations and control center, and property acquisition. Included in the terminal trackwork and layup facilities are the track and layup facilities and property acquisition. The Minneapolis CBD station includes just the costs associated with station construction. The final item included in capital costs are the various corridor segments. The corridor between Minneapolis and East St. Cloud was divided into different segments based on the distance between stations. For instance, the corridor between Elk River and Big Lake was segment F and the corridor between Anoka/Ramsey and Elk River was segment E. The costs for each of the segments varied because of the different track improvements and system upgrades needed. Different parking requirements for the stations, site development and property acquisition costs also affected segment totals. 13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330 · TDD & Phone: (612) 441-7420 · Fax: (612) 441-7425 Mayor and City Council/Northstar December 21, 1998 Page 2 Common elements included station platforms and shelters, ticket vending machines and public address systems. As part of developing preliminary cost estimates for each station, BRW needed to include information regarding parking requirements. BRW did not have the benefit of ridership forecasts when estimating parking requirements. The cost estimates for the Elk River station included a 500 space parking lot. This estimate is high and will be reduced once the final ridership analysis is completed. The preliminary capital costs associated with the Elk River station is $3,110,000. The costs for trackwork and system upgrades has not been determined for each individual segment. Overall preliminary capital cost estimates are as follows: Corridor segments (Mpls. To E. St. Cloud) Vehicles Central Facilities Terminal Trackwork Minneapolis CBD $34,710,000 $42,875,000 $18,760,000 $12,208,000 $ 9,800,000 $115,000,000 Potential Capacity Improvements 30 to 50 Million Total 145 to 165 million Preliminary Operational Costs Preliminary operational costs included the costs of operating the commuter railroad and the costs of operating a feeder bus service to the various stations. For Elk River, two feeder bus lines were considered, one down Highway 169 from Princeton and one from St. Michael. The preliminary operational costs are as follows: Commuter Rail $9,500,000 Feeder Bus $ 651,000 Total $10,151,000 The consultants compared these preliminary costs to other start up commuter systems in the country and found the costs for the Northstar \\elkriver\sys\shrdoc\planning\scott\ncdadec.doc Mayor and City Council/Northstar December 21, 1998 Page 3 Corridor compare quite favorably. They seemed to feel the project is feasible in terms of both capital and operational costs. Ridership Forecast Ridership estimates also came in favorably. Ridership at start up (2003) was estimated at 7350 rides per day and in the year 2020, increase to 8200 rides per day. The consultant estimated that in the year 2003, 939 people would board the train in Elk River and go into Minneapolis. The ridership estimates were better than average when compared to other commuter railroad systems. The consultant estimated that 87% of the people riding the train would be commuting to work and 97% would be commuting in the peak direction. CBD Visioning Process As part of the Central Business District visioning process, the public improvement committee will be gathering information to assist in possible station locations and designs. During the initial meeting on October 23rd , one of the topics that kept being brought up was the desire to have the station downtown. Other possible locations include east Elk River along Tyler Street and the northeast side of the Proctor Avenue railroad crossing. \\elkriver\sys\shrdoc\planning\scott\ncdadec.doc DEC 03 '98 12:11 T0-2412701 FROH-UCHARDS0N,R[TCti£R &ASSOC. T-660 P. 02/02 F-164 NORTHSTAR CORRIDOR DEVELOPMENT AUTHORITY Thursday, December 10, 1998 Sherburne County Government Center Elk River, MN Minutes of the November 6, 1998 Meeting* Preliminary Service Concepts* Action Re(!_uested Approval Information Ridership Forecasts (to be presented at meeting1 a. Northstar Corridor b. Comparison to Mn/DOT Study* c. Comparison to Existing Systems Information Capacity Modeling - Potential Capital Improvements~ Information 5. Preliminary Capital Costs* Information 6. Preliminary Operating Costs* Information Executive Committee Report e. 1999 Legislative Sea,ion b. Tour of California Commuter Rail System c. Joint Powers Agreement - Appointments d. Contracts for 1999 1, SRW 2. Richardson, Richter & Associates 3. Ken Stevens Consider Committee Reoommenclat~on8 8. Overview of Mn/DOT Phase !1 Commuter Rail Information 6tudy* 9. Other: Next Meeting NOTE; The Legislative I~eception will follow the NCDA Meeting at 5:30 p.m. at the Riverwood Conference Center. DRAFT DRAFT DRAFT NORTHSTAR CORRIDOR DEVELOPMENT AUTHORITY Regular Meeting Minutes November 5, 1998 The Northstar Corridor Development Authority met on November 5, 1998, at the Sherbume County Government Center in the City of Elk River, Minnesota. The following members, alternates and citizens were present: Steve Billings, Hank Duitsman, Scott Harlicker, Paul Ostrow, Tom Gamec, J. Patrick Cairns, Richard G. Turch, Jerry Leese, Ewald Peterson, John Norgren, Paul Goenner, Lewis Stark, LeRoy Pauley, Thomas Cruikshank, Dan Erhart, Paul McCarron, Tim Yantos, Duane Grandy, Gary Erickson, Betsy Wergin, Gerry. Donlin, Ken Paulson, Jim Dickinson, Roger Fraser, Donald Jolly, Mike Christensen, David Mahle, Ken Stevens, Biz Colbum, Dick Wolsfeld, Stephanie Eiler, David Loch, Jim Barton, Brian Roper, Rick Speak, Carl Yilek, Mike Robertson, Jean Keely, Lona Schrerber, Marcia Bennett, Mary Richardson, Lynn George o o The Chairperson called the meeting to order at 3:00 p.m. A motion was made by J. Patrick Cairns, seconded by Duane Grandy and carded unanimously to approve the agenda of November 5, 1998, with no additions and the meeting minutes of October 1, 1998, regular meeting minutes as presented. Tim Yantos provided an update on the Federal Funding indicating that Congress did approve the $6,000,000 funding for the Northstar Corridor Development Authority. Tim Yantos introduced David Mahle, formerly with BNSF, who presented a report on the initial simulation results of the BNSF capacity modeling study. Biz Colburn, BRW, Inc. reviewed the draft Purpose and Need Statement presented by BRW, Inc. The goal of the project is to meet the future transportation needs of the Northstar Corridor. A motion was made by Paul McCarron, seconded by Gerry Donlin, and carried unanimously to approve the Purpose and Need Statement dated October 28, 1998 as amended. o o Dick Wolsfeld, BRW, Inc. reviewed the steps of the federal process for the Major Investment Study. The NCDA then preceeded to conduct the fatal flaw analysis and eliminated transportation alternatives deemed to be too costly, infeasible or ineffective in meeting the transportation needs of the corridor. A motion was made by Hank Duitsman, seconded by Duane Grandy, and carried unanimously to approve the following multimodal investment alternatives: - No Build - Transportation Management/Bus Improvements - Feeder Bus Improvements, Commuter Rail - Feeder Bus Improvements, Commuter Rail, Trunk Highway 10 Minor Upgrade o Feeder Bus Improvements, Commuter Rail, Trunk Highway 10 Minor Upgrade, River Crossings Stephanie Eiler, Anoka County, updated the members on the Mn/DOT Commuter Rail Study. A motion was made by Paul McCarron, seconded by Scott Harlicker to request That the Northstar Corridor Steering and Advisory Committee draft a letter to be directed to Mn/DOT detailing the desire of the Northstar Corridor Development Authority to communicate it's desire not to stop the commuter rail at the City of Ramsey. The members received a copy of the draft Implementation/Business Plan of the Twin Cities Metropolitan Commuter Rail Study Steering and Advisory Committees dated September 30, 1998. General discussion was held on the governance of commuter rail. A request was made to obtain samples of governance's of current operating commuter rail systems. A motion was made by Steve Billings, seconded by Tom Gamec and carried unanimously to forward the proposed commuter rail planning and project development process draft #3 dated October 29, 1998 to MN/DOT with a letter of request considering this model. Biz Colbum, BRW, Inc. presented a summary of the Commuter Rail Open House Public Informational Meetings held in Elk River, St. Cloud and Fridley. 10. A request was received from the Watab Township Board requesting membership to the Northstar Corridor Authority. A motion was made by J. Patrick Cairns, seconded by Richard Turch and carried unanimously to approve membership to the Northstar Corridor Authority of the Watab Township Board. Mary Richardson, Richardson, Richter & Associates, Inc. will be in contact with the Steve Peka, Watab Township Board, to request member and alternate appointments.' 11. Paul McCarron presented an updated on the 1999 Legislative Activities. 12. The next meeting of the Northstar Corridor Development Authority is scheduled for Thursday, December 10, 1998, at 3:0 0 p.m. at the Sherburne County Government Center. At the conclusion of this meeting, legislators along the corridor will be invited to a reception and briefing on the Northstar Corridor. 13. Stephanie Eiler and Tim Yantos, Anoka County, distributed informational articles on various corridors c,urrently operating. 14. A motion was made by Richard Turch, seconded by J. Patrick Cairns and carried unanimously to adjourn the meeting at 5:30 p.m. Betsy Wergin, Chairperson Dated Northstar Corridor Weekday Commuter Rail Service Service Concept A 7:IOAM 8:I5AM 5:25 PM 5~.'35~ 6:05 PM BRW. h~c. 12/02/98 Northstar Corridor Weekday Commuter Rail Service Service Concept B BRW, Inc. 12/02198 BRW, Inc. / DJM Preliminary Capacity Modeling and Potential Capital Improvements B..Rw_ ..................................... DAMES & MOORE GROGP COMPANy MEMORANDUM BRW Thresher Square 700 Third Street South Minneapolis, MN $5415 Phone: (612) 370-0700 Fax: (612) 370-1378 To: Tim Yantos From: David Mahle Copy: Dan Meyers File: 33935-001-0702 Date: Subject: December 3, 1998 NCDA/BNSF Line Capacity Simulation Results Line capacity simulations have been performed by BNSF, using the Dispatch Planning Model, to determine the amount of additional trackage and signaling that will be required to support commuter rail operations while maintaining the level of freight service that is expected to exist in the startup year 2003. To do this BNSF first developed a base case with 2003 expected traffic levels and operational changes. Commuter service was then started on the system and various capacity improvements were added to gauge their effect. The simulation does not give an optimal answer automatically but rather is used in a series of iterations to determine impacts of combinations of capacity improvements. There are two primary statistical measures that are used by BNSF to determine the impacts of capacity improvements. The first is freight transit time per 100 miles. This measure indicates by train class and for all freight trains the time required by a train to go 100 miles. It includes actual running time, delays due to congestion and meeting other trains, and dwell time at terminals. The second measure is freight train delay per 100 miles. This is a component of transit time and is the most important measure of congestion and lack of capacity. These measures are also developed for Amtrak and commuter trains but are not important indicators as these trains have the highest dispatching priority and vary little in running time or delay regardless of the number of freight trains or level of congestion in the system. The attached status information indicates these key measures for the 2003B base case and a series of simulations with the commuter train schedules added to the system. Five different combinations of upgrades are indicated together with the impact on the two key measures discussed above. DJM:mr NCDA/BNSF CORRIDOR SIMULATION STATUS SERVICE CONCEPT B FREIGHT FREIGHT SIMULATION MAP TRANSIT DELAY DESCRIPTION SCENARIO KEY TIME (min) TIME (rain) 2003B BASE 360.9 32.5 Opening year rail traffic with no commuter rail service NO UPGRADE 383.3 53.5 Opening year rail traffic with commuter rail service UPGRADE I 379.2 52.1 A Double track Becker to Big Lake B CTC Big Lake to Coon Creek C Double crossovers at Becker, MP 51.2 and MP 45.1 D Double crossovers at Elk River, MP 32.9 and Ramsey UPGR.~DE 2 368.5 39.8 E Double track 43rd Ave to 35th Ave (Northtown Yard) F Double track west leg of wye at Minneapolis Junction G Double track Minneapolis Junction to Union Yard H Upgrade siding between Harrison St and Holden St to second main track B CTC Big Lake to Coon Creek I CTC Harrison St to Holden St D Double crossovers at Elk River, MP 32.9 and Ramsey J Double crossover at 43rd Ave K Single crossover at MP 11.3 on Wayzata Sub L Upgrade turnout at MP 11.7 on Wayzata Sub M Upgrade double crossovers at MP 11.3 on Midway Sub to 30/25 mph N Upgrade mainline between 35th Ave and Minneapolis Junction to 70/45 mph UPGRADE 3 366.0 37.8 Combination of UPGRADE 1 and UPGRADE 2 UPGRADE 6 361.5 34.0 UPGRADE 3 with the following revisions: O Add sidings at Anoka and Coon Creek for local trains to work off of main line UPGRADE 7 360.1 34.3 UPGRADE 6 with the following revisions: J No double crossover at 43rd Ave K No single crossover at MP 11.3 on Wayzata Sub N Upgrade mainline between 35th Ave and Minneapolis Junction to 45/45 mph (not 70/45 mph) F No Double track west leg of wye at Minneapolis Junction - upgrade to 20 mph, including two switches DJM/BRW 12/02/98 Sartell Benton Haven Stearn,, Clearwater Sherburr~e Becker Township Isanti Wright Big Lake Township Township Anokai Albertvill Dayton Andover 31ai~ Potential Station Location (~ Capacity Improvement (see attached list) Potential Commuter Rail Capacity Improvements St. Cloud/Rice to Coon Rapids Maple Grove Brooklyn Park Coon Blaine Mou ~ds ViE Brooklyn 1-694 Henne Minnea Potential Station Location Capacity Improvement (see attached list) December 3, 1998 Potential Commuter Rail Capacity Improvements Coon Rapids to Minneapolis BRW, Inc. Preliminary Capital Cost Estimate NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SUMMARY OF CAPITAL COST ESTIMATES POTENTIAL ADDITIONAL COST ELEMENT COMMUTER RAIL CAPACITY CAPITAL GRAND TOTAL BASIC ELEMENTS IMPROVEMENTS * IMPROVEMENTS (1999 DOLLARS) MINNEAPOLIS CBD TO EAST ST. CLOUD CORRIDOR SEGMENTS SEGMENT A - MINNEAPOLIS CBD TO NE MINNEAPOLIS 2,086,000 SEGMENT B - NE MINNEAPOLIS TO FRIDLEY 3,220,000 SEGMENT C - FRIDLEY TO COON RAPIDS 3,696,000 SEGMENT D - COON RAPIDS TO ANOKNRAMSEY 7,602,000 - SEGMENT E - ANOKNRAMSEY TO ELK RIVER 4,354,000 - SEGMENT F - ELK RIVER TO BIG LAKE 2,828,000 SEGMENT G - BIG LAKE TO BECKER 2,156,000 SEGMENT H - BECKER TO CLEAR LAKE 2,156,000 SEGMENT I - CLEAR LAKE TO EAST ST. CLOUD ;~,212,000 SUBTOTAL 30,310,000 VEHICLES 42,875,000 CENTRAL FACILITIES 18,760,000 - TERMINAL TRACKWORK & LAY-UP FACILITIES 12,208,000 - MINNEAPOLIS CBD STATION 9,800,000 MINNE-APE~L~,~-~) EAST CLOUD TOTAL (1999 DOLLARS) $114 million $30 - 50 million $144 - 164 million EAST ST. CLOUD TO ST CLOUD CBD TOTAL (1999 DOLLARS) $2.3 million $1.0 - 2.0 million $3.3 - 4.3 million I~AS'F-$T. CLOUD-'F0--Ri~E-~O-'~Ai~ (~999 DOLLARS) $2.1 million $3.0- 5.0 mill-io~- - $5.1- 7.1 million * Estimated range of capital costs for potential railroad capacity improvements. BRW, Inc. ~ [~ u/~ ~ ~ Con-b-OI.xls[SUMMARY] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM -- SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) COMMON SYSTEM ELEMENTS COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST ELEMENT UNITCOST QUANTITY COST QUANTITY COST QUANTITY COST VEHICLES LOCOMOTIVES EA 2,700,000 5 13,500,000 ---'-~OACHES EA 1,300,000 9 11,700,000 .... ~O~'R~OL COACHES EA 1,820,000 5 9,100,000 - E~NGiNEER~NG' ETC. (15%) 5,145,000 _ CONTINGENCY (10%) 3,430,000 - S~U B~rOTA L 42,875,000 CENTRAL FACILITIES TRACKWORK & INCIDENTALS LS 5,000,000 1 5,000,000 CENTRAL SHOP & EQUIPMENT LS 6,000,000 I 6,000,000 OPERATIONS CONTROL CENTER LS 2,100,000 1 2,100,000 PROPERTY ACQUISITION LS 300,000 1 300,000 ENGINEERING, ETC. (20%) 2,680,000 CONTINGENCY (20%) 2,680,000 SUBTOTAL 18,760,000 TERMINAL TRACKWORK & LAY-UP FACILITIES TERMINAL TRACKWORK & LAY-UP FACILITIES EA 4,300,000 2 8,600,000 PROPERTY ACQUISITION LS 60,000 2 120,000 ENGINEERING, ETC. (20%) 1,744,000 ---~3oN~I-N G~'Nc~-(20%) 1,744,000 SUBTOTAL 12,208,000 MINNEAPOLIS CBD STATION .... MiNNEAPOLiS CBD STATION LS 7,000,000 1 7,000,000 ___ - ENGINEERING, ETC. (20%) 1,400,000 ___ CONTINGENCY (20%) 1,400,000 __ --- s~UBTOTAL 9,800,000 BRW, Inc. ~) [~ ~ [~ c~ Con-b-01.xls[COMMON] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT A - MINNEAPOLIS CBD TO NE MINNEAPOLIS APPROX. LENGTH (MI): 3.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT COST ELEMENT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (NE MINNEAPOLIS) PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 - - TICKET VENDING MACHINE EA 115,000 2 230,000 - - PUBLIC ADDRESS & VMS EA 105,000 2 210,000 - - SITE DEVELOPMENT / INCIDENTALS EA 300,000 1 300,000 - - SURFACE PARKING SPACE 2,500 - PROPERTY ACQUISITION ACRE 180,000 - SUBTOTAL 1,490,000 - TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 - CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 - CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 - CROSSING SURFACE (NEW/UPGRADE) FT 675 - SUBTOTAL - CIVIL I STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS - SUBTOTAL - SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 1,490,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 298,000 CONTINGENCY (20%) 298,000 TOTAL (1999 DOLLARS) 2,086,000 BRW, Inc E~ E~ z~ [~ c~ Con-b-01.xls[SEGA1 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT B - NE MINNEAPOLIS TO FRIDLEY APPROX. LENGTH (MI): 6.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST ELEMENT UNIT COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (FRIDLEY) PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 _210,000 SITE DEVELOPMENT / INCIDENTALS EA 250,000 1 250,000 SURFACE PARKING SPACE 2,500 200 500,000 PROPERTY ACQUISITION ACRE 180,000 2 360,000 SUBTOTAL 2,300,000 TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) Mi 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000_ TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL - CIVIL / STRUCTURES EARTHWORK / STRUCTURES LS 2,000,000 MODIFY STRUCTURES LS 3,000,000 SUBTOTAL ' SYSTEMS SIGNALING/CTC_(N_~_W/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 - SUBTOTAL - RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 2,300,000 - ' ADD-ONS -- E'NGiNEERiNG, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 460,000 - CONTINGENCY (20%) 460,000 TOTAL (1999 DOLLARS) 3,220,000 __ _ - _____ - BRW, Inc. [~ ~ ~/~ [~ c~ Con-b-01.xls[SEGB] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT C - FRIDLEY TO COON RAPIDS APPROX. LENGTH (MI): 5.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (COON RAPIDS) PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 SITE DEVELOPMENT / INCIDENTALS EA 250,000 1 250,000 SURFACE PARKING SPACE 2,500 300 750,000 PROPERTY ACQUISITION ACRE 180,000 3 450,000 SUBTOTAL 2,640,000 -~ - TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL CIVIL ! STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS SUBTOTAL SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 - SUBTOTAL - RIGHT-OF-WAY SF 4.00 - CONSTRUCTION SUBTOTAL 2,640,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 528,000 CONTINGENCY (20%) 528,000 TOTAL (1999 DOLLAR S) 3,696,000 BRW, Inc [~ [~ //~ E~ c~ Con-b-01.xls[SEGr" 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT D - COON RAPIDS TO ANOKA/RAMSEY APPROX. LENGTH (MI): 9.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST ELEMENT UNIT COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (ANOKA/RAMSEY) -- PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 ___ TICKET VENDING MACHINE EA 115,000 I 2 230,000 PUBLIC ADDRESS & VMS EA 105,0002 210,000 - ~I~EDEVELOPMENT / INCIDENTALS EA 300,000 1 300,000 SURFACE PARKING SPACE 2,500 1,000 2,500,000 PROPERTY ACQUISITION ACRE 180,000 8 1,440,000 SUBTOTAL 5,430,000 TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 __ CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL CIVIL / STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS SUBTOTAL SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 5,430,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 1,086,000 CONTINGENCY (20%) 1,086,000 T__0_'FAL (19~99_ DOLLARS) 7,602,000 BRW, Inc, [~ [~ z~ [~ ~ Con-b-01.xls[SEGD] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT E - ANOKA/RAMSEY TO ELK RIVER APPROX. LENGTH (MI): 9.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (ELK RIVER) PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 SITE DEVELOPMENT / INCIDENTALS EA 200,000 I 200,000 SURFACE PARKING SPACE 2,000 500 1,000,000 PROPERTY ACQUISITION ACRE 180,000 4 720,000 SUBTOTAL 3,110,000 - ' TRACKWORK TRACK: 136# RAILJCONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 - .~__ TURNOUT: #24 (NEW/UPGRADE) EA 185,000 .... CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 __ SUBTOTAL - CIVIL ! STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS SUBTOTAL - SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 _ CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 _ CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 ................... CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 3,110,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 622,000 CONTINGENCY (20%) 622,000 TOTAL (1999 DOLLARS) 4,354,000 BRW, Inc I~ [~ /~ [~ c[~ Con-b-01.xls[SEGF~ 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT F - ELK RIVER TO BIG LAKE APPROX. LENGTH (MI): 9.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST ELEMENT UNIT COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (BIG LAKE) "PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 - SITE DEVELOPMENT/INCIDENTALS EA 150,000 1 150,000 SURFACE PARKING SPACE 2,000 200 400,000 PROPERTY ACQUISITION ACRE 140,000 2 280,000 -'- SU-B-TOTAL 2,020,000 TRACKWORK .................... ' TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 ..... CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL - CIVIL / STRUCTURES _ EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS _ SUBTOTAL ' ' ' SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 ----CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 --~ROSsiNG SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL ' ' ' RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 2,020,000 - ADD-ONS .... i=N~INEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 404,000 .... ~;(~NTINGENCY (20%) 404,000 2,828,000 - _T_OTAL_(_~199--9 DOLLARS) __ _ BRW, Inc. D [~ ~ ~ ~ Con-b-01.xls[SEGF] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT G - BIG LAKE TO BECKER APPROX. LENGTH (MI): 8.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT COST ELEMENT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (BECKER) PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 . - PUBLIC ADDRESS & VMS EA 105,000 2 210,000 SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000 SURFACE PARKING SPACE 1,500 100 150,000 PROPERTY ACQUISITION ACRE 100,000 I 100,000 SUBTOTAL 1,540,000 TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL CIVIL ! STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS SUBTOTAL SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 (~ONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 1,540,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 308,000 CONTINGENCY (20%) 308,000 TOTAL (1999 DOLLARS) 2,156,000 - BRW, Inc [~) E~ Z~ [~ c~ Con-b-01.xls[SEG~] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT H - BECKER TO CLEAR LAKE APPROX. LENGTH (MI): 7.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (CLEAR LAKE) -"-P~_AT-F-O-FiM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 ...... SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000 SURFACE PARKING SPACE 1,500 100 150,000 PROPERTY ACQUISITION ACRE 100,000 1 100,000 SUBTOTAL 1,540,000 TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL CIVIL / STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS SUBTOTAL SYSTEMS .... ~I~i-ING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 1,540,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 308,000 CONTINGENCY (20%) 308,000 TOTAL (1999 DOLLAR S) 2,156,000 BRW, Inc. D [~ /~ E~ c~ Con-b-01.xls[SEGH] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT I - CLEAR LAKE TO EAST ST. CLOUD APPROX. LENGTH (MI): 11.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (EAST ST. CLOUD) __ PLATFORM, SHELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 SITE DEVELOPMENT / INCIDENTALS EA 100,000 I 100,000 SURFACE PARKING SPACE 1,500 100 150,000 PROP ERTY ACQUISITION ACRE 140,000 1 140,000 SUBTOTAL 1,580,000 TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 _ ' CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL - CIVIL ! STRUCTURES EARTHWORK / STRUCTURES LS - MODIFY STRUCTURES LS - SUBTOTAL - SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 - CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 - - CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 - CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL - RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 1,580,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 316,000 CONTINGENCY (20%) 316,000 TOTAL (1999 DOLLARS) 2,212,000 - BRW, Inc [~ ~ ~ E~ c~ Con-b-01.xts[SEG" 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT J - EAST ST. CLOUD TO ST. CLOUD CBD APPROX. LENGTH (MI): 1.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL COST ELEMENT UNIT UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (ST. CLOUD CBD) PLATFORM, SHELTER, LiGHTiNG, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 SITE DEVELOPMENT / INCIDENTALS EA 100,000 1 100,000 SURFACE PARKING SPACE 2,000100 200,000 PROPERTY ACQUISITION ACRE 180,000 1 180,000 SUBTOTAL 1,670,000 TRACKWORK TRACK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 CROSSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL CIVIL ! STRUCTURES EARTHWORK / STRUCTURES LS MODIFY STRUCTURES LS SUBTOTAL SYSTEMS SIGNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 SUBTOTAL RIGHT-OF-WAY SF 4.00 CONSTRUCTION SUBTOTAL 1,670,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 334,000 CONTINGENCY (20%) 334,000 _TgT_A_L_(!999 DOLLAR~S)_ 2,33S,000 BRW, Inc. [~ E~ & [~ c~ Con-b-01.xls[SEGJ] 12/03/98 NORTHSTAR CORRIDOR MAJOR INVESTMENT STUDY COMMUTER RAIL SYSTEM - SERVICE CONCEPT B PRELIMINARY CAPITAL COST ESTIMATE (1999 DOLLARS) SEGMENT K - EAST ST. CLOUD TO RICE APPROX. LENGTH (MI): 15.0 COMMUTER RAIL POTENTIAL CAPACITY ADDITIONAL CAPITAL UNIT BASIC ELEMENTS IMPROVEMENTS IMPROVEMENTS COST ELEMENT UNIT COST QUANTITY COST QUANTITY COST QUANTITY COST STATION (RICE) --~I~F~)R-I~,~S-HELTER, LIGHTING, FURNISHINGS, ETC. EA 375,000 2 750,000 TICKET VENDING MACHINE EA 115,000 _ 2 230,000 PUBLIC ADDRESS & VMS EA 105,000 2 210,000 SITE DEVELOPMENT / INCIDENTALS EA 50,000 I 50,000 SURFACE PARKING SPACE 1,500 100 150,000 __ PROPERTY ACQUISITION ACRE 100,000 I 100,000 SUBTOTAL 1,490,000 TRACKWORK ---~P~A'CK: 136# RAIL/CONCRETE TIES (NEW/UPGRADE) MI 623,000 TURNOUT: #20 (NEW/UPGRADE) EA 170,000 TURNOUT: #24 (NEW/UPGRADE) EA 185,000 CROSSOVER: #20 (NEW/UPGRADE) EA 345,000 C~(~SSOVER: #24 (NEW/UPGRADE) EA 378,000 CROSSING SURFACE (NEW/UPGRADE) FT 675 SUBTOTAL ' ' CIVIL I STRUCTURES --- EA~T~W-~-~-t~ STRUCTURES ES MODIFY STRUCTURES LS SUBTOTAL - SYSTEMS $1GNALING/CTC (NEW/UPGRADE) MI 75,000 CONTROL POINT: 1-SWITCH (NEW/UPGRADE) EA 563,000 CONTROL POINT: 2-SWITCH (NEW/UPGRADE) EA 703,000 CONTROL POINT: 4-SWITCH (NEW/UPGRADE) EA 849,000 CROSSING SIGNALS (NEW/UPGRADE) EA 270,000 - _ SUBTOTAL - i RIGHT.OF-WAY SF 4.00 - CONSTRUCTION SUBTOTAL 1,490,000 ADD-ONS ENGINEERING, PROJ MGMT, ADMIN, START-UP, INSURANCE (20%) 298,000 CONTINGENCY (20%) 298,000 TOTAL (1999 DOLLARS) 2,086,000 BRW, In~ [~ ~ /r~ [~ ~ Con-b-01.xls[SEG'" ~2/03/98 Manuel Padron and Associates Preliminary Operations and Maintenance Cost Estimate and Feeder Bus Network System I NORTHSTAR - DIESEL C:OMMUTER RAIL O&M COST MODEL TABLE 1. INPUT VARI.~'~BLES VARIABLE SYSTEM CHARACTERISTIC! NAME Annual Train Tdps ' Peak Gallery Passenger Cars' Fleet Gallery Passenger Cars Peak Trainsets (Locomotives): Fleet Locomotives Annual Revenue Train-Hours: Annual Train-Miles (incl. deadhead) Annual Car-Miles (incl. deadhead) Leased Directional Route-Mil(~s Owned Directional Route-Miles Total Stations Storage & Maintenance Yard - Layover Yard NORTHSTARJ CONCEPT TRIPS 2,595 PKCAR 12 TOTCAR 14 PKLOCO 4 TOTLOCO 5 TRAINHR 7,120 TRAINMI 272,550 CARMILE 817,650 RTMILE 95.1 RTMILE2 0 STATION 11 YARD 1 LYARD 2 Prepared by Manuel Padron & Associates, In,~. i 11/25/98 01:4-3 PM NORTHSTAR - DIESEL COMMUTER RAIL O&M COST MODEL Line Item Detail CONCEPT B i ~ASELINE PRODq'Y COST ITEM EXPENSE FACTOR DRIVING STAFF ESTIMATED DEPT VARIABLE (FTEs) COST COS'F OPERA TING AGENCY EXPENSE$ 100 Director of Operations Labor 100 Professional Services 100 Miscellaneous 100 200 Budget & Finance Labor 200 Office space/Equip.,etc. 200 Revenue Servicing 200 Other Professional Services 200 Miscellaneous 200 Insurance (Risk Management 200 300 Marketing/Customer Service Labor 300 Print./Promo. Matls./Postage 300 Professional Services 300 Media Placemont/Spec. Even 300 Miscellaneous 300 400 Technical Service,, Labor Materials & Supplies-Facilifie PNTVM Field Maintenance Fare Inspection Communications 400 Diesel Fuel 400 Yard/Lead Track Maint. 400 Station & Parking Lot Maint. 400 Other Services 400 Utilities - Stations 400 Utilities - Yard 400 Miscellaneous 400 Subtotal Operating Agency CONTRA CT OPERA TOR FUNCTIONS 500 Train Operations Labor - Engineers 500 Labor. Conductors 500 Train Crew Expenses 500 Standby Electricty 500 600 Maintenance Equipment Serv./Shop Exp. 600 Material, Parts & Handling 600 Services Subcontracts 600 Subtotal Conb'actor O & M 700 Contract Operator Fees Trans. Supervision & GA 700 Overhead & Management Fe 700 Performance Payments 700 Subtotal Contract Ope/ator PA YMEN TS TO RA ILROA D 800 Track Access/Usage Fees 800 TOTAL COST $165,230 0.0'21 $135,000 $2,813 $16,000 $8,000 F+PKCAR 1.0 $82,615 PKCAR $33,750 #100 FTEs $8,000 $175,200 $143,950 $352,000 $30,000 $4,700 '1,800.000 0.021 F+PKCAR 2.0 $116,800 $7,576 #100-400 FTEs $90,916 $19,556 STATION $215,111 $625 PKCAR $7,500 $1,567 #200 FTEs $3,133 $1.17 CARMILE $955,754 ' $313,210 0.001 F+TRIPS 5.0 $261,008 $104,000 $35 TRIPS $89,960 $205,100 $68 TRIPS $177,412 $252,000 $84 TRIPS $217,980 $14,500 $2,417 #300 FTEs $12,083 400 . $411,380 0.104 F+PKCAR 4.0 $205,690 400 $42,500 $2,125 TATION+YARD $25,500 400 $40,000 $2,222 STATION $24,444 A.~lumed to be handled by Conductors aboard trains and other agencies. $138,500 $17,313 PKLOCO $69,250 $2.06 TRAINMI $560,090 $60,000 $20,000 YARD+LYARD $60,000 $700,000 $38,889 STATION $427,778 $ 70,000 $6.19 TRAIN H R $44,102 $100,000 $5,556 STATION $61,111 $97,000 $32,333 YARD+LYARD $97,000 $14,000 $1,750 #400 FTEs $7,000 '12. o $80,452 940 PRODHRS 8.0 $643,617 · $68,740 940 PRODHRS 8.0 $549,921 · $122,000 $3,211 #500 FTEs $51,368 $60,000 $30,000 LYARD $60.000 02,336,800 $1.52 CARMILE $1.240,782 $648,220 $0.42 CARMILE $344,188 $554,240 $11,547 PKCAR $138,560 ~: 870452.35 $492,660 7.2% of Subtotal $219,379 $798,828 8.0% of Subtotal 5242,275 $437,026 $1.32 TRAINMI $360,461 ~3,346,000 $19,120 RTMILE $1,818,312 $124,365 $1,389,215 $758,443 $1,581,966 53,853.989 $1.304,907 $1,723,530 $3,028,437 S822,115 $3,850,552 $1,818.312 $9,522,853 ICost per Train-Hour: Cost per Train-Mile: Cost per Car-Mile: $1,3371 $34.94 $11.65 Prepared by Manuel Padron & Associates, Inc. 11/25/98 01:52 PM NORTHSTAR COMMUTER RAIL PROJEC,r SCHEDULE B -- SERVICE TO ST. CLOUD ISTA./AGE NCWRTE. 'I' ~DESCRIPTION ' Metro 10 i Metro 18, Mel3'o 24 Metro 29 NE Minn.'(Lowry Option) Metro 18 Metro 32 Metro 10F,U Metro 24 Metro 879 Coon Rapids (Foley) Anoka 889 Anoka ~05 Anoka 831 Anoka Anoka 890 Molto 27 ' Anoka 805 Anoka 8,31 Anoka 842 Ramsay Anoka ~91 Elk River River R. 901 Big Lake River R. 902 Backer Tri-CAP 903 ;leer Lake River R. 904 S. St. CIm~d MTC Eastside MTC Rice St. Cloud CBD MTC ,Provide transfer al station; no reroute necessary. Reroute Washington St. branch via Broadway, Quincy, 15th Ave. Provide transfer at stalio~; no reroute necessary. P..Eovide transfer at stalfon; no reroute necessary. Reroute Washington St. ~anch via 22nd Ave., 6th St., Lowry. Provide transfer at stalJon; no re. route_n_ .e~e..~_s. sary. Route via 61st Ave. to station. Route via 61st Ave. to station. Eliminate 4 AM Express SB trips (Iv. N'tovm @ 6:18, 7:22, 7:52, 8:22). Eliminate 4 PM Express NB tripe (iv. 7thl3rd @ 3:40, 5:10, 5:45, 6:10). New Rdute from Brookdale -CR sta0on - Apache Plaza via Shingle Creek Pkwy, 1-694, University, CR 102, Main St., 61st, Un'~vereR7, 37th~' New route from Bethel- CR station via 237th, Rt 65, Rt 14, Rt 51, Foley. · ' · I~,7 ~-'i;',~ ;,-,& ,6 G .............................. 7: :25 ........ IEliminate 5 PM NB trips (Iv. 7th/3rd @ 4:19, 4:37, 4:58, 5:03, 5:40). Reroute via Woodcrest, 99th Ave., Foley, CR stain, Foley,.RL10. Increase AM, PM peak pe~xl frequency to 30 minutes. jlncresse AM, PM peak period fTequenc¥ to 30 minutas. iNew route fm St. Francis - CR Sta via Rt 47, Industry, VoTech, Rt 10, 7ih. Provide transfer at station; no rerc~te neoessary. Provide ~ansfer at station; no reroute necessary. llProvide transfer at station; no reroute necessary.. · j .P~_~_ovid~e~nsf_~er at _station; no rer__oute necessary. . ...... ~New STV circulator via OR station, Vo'rech, Industry Ave., Nov/then, Ramsoy Blvd., 155th, Variolite, 161st, Armstrong Blvd., Rt.10/169. New route from Princeton - CR stalion - St. Michael via Rt.169,181st., _Rt.._!.69_,.R_t._3_9_/B_r_o._a~lv/a~_ St.. Rt. 1 g/La Beaux, Central Ave. lew route from Buffalo to CR station via Rt.25. !_e)v._r..0u. te_!r._o_m_.F_e,le_,v to CR station via Rt.25, Rt.10. New route from I~mball - Annartdale - CR station vi~ Rt. 24. !P~,,vide transfer at stati(~' no rerouta necessary. route Rice - CR stati'on - MTC Transit Center via Rt.10, Rt.23. Extend._a!!_M_T_C._r_~r{es_s_e. rving~Tr_a, nsit Center to CR station. " SERVICE HEADWAY PEAK BASE NC NC NC NC NC NC NC NC ~EAK BUSES NC NC NC NC NC NC NC NC NC NC NC NC NC NC NC NC 30 NA NC NC NC +2 60 NA +1 30 30 +1.5 30 30 +1.5 60 NA NC NC NC NC NC NC NC NC .AI +1 NC NC NC NC AVG. WKDY. BUS-HR. BUS-MI. NC NC NC NC NC NC NC NC NC NC X.X X.X NC +12.0 +6.0 +9.0 +9.0 *6.0 NC NC NC NC NC NC Y-) NC y.y, NC NC NC NC 60 NA +1 +6.0 y. +2' +12.0 60 NA 60 NA 60 NA NC NC 60 6O NC NC +6.0 +1 +1 +6.0 +1 +6.0 NC NC +1 +12.0 NC NC Y.) y.) Y-) NC Y.) NC NOTES: ~NC" refers to no change ~rorn e×isling. Figure 7 PRELIMINARY RAIL RIDERSHIP RESULTS NORTHSTAR CORRIDOR - Concept B to Downtown St. Cloud Average Weekday Daily Ridership - Year 2005 Southbound to Minneapolis - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Downtown St. Cloud 71 40 3 15 74 54 East St. Cloud 58 40 3 15 60 54 Clear Lake 19 31 1 12 20 43 Becker 6 35 0 13 6 48 Big Lake 418 112 19 42 437 155 Elk River 466 408 21 154 487 562 Ramsey/Anoka 536 386 16 85 552 . 470 Coon Rapids 1,075 529 37 130 1,112 658 Fridley 1,218 327 75 131 1,293 458 NE. Minneapolis 0 413 0 182 0 595 Downtown Minneapolis Total 3,867 2,321 174 779 4,041 3,099 Northbound to St. Cloud - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Downtown Minneapolis 9 10 0 4 9 14 NE. Minneapolis 0 5 0 2 0 7 Fridley 14 1 1 0 15 1 Coon Rapids 4 1 0 0 4 1 Ramsey/Anoka 4 0 0 0 4 0 Elk River 18 11 1 4 19 15 Big Lake 51 19 2 7 53 26 Becker 2 1 0 0 2 1 Clear Lake 2 8 0 3 2 11 East St. Cloud 1 1 0 0 1 1 Downtown St. Cloud Total 105 57 5 22 110~ 79 Notes: (1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the Anoka station. (2) Includes driving to feeder bus station if available. (3) Includes walking to feeder bus station. 12/08/1998 Figure 5 PRELIMINARY RAIL RIDERSHIP RESULTS NORTHSTAR CORRIDOR - Concept B to Downtown St. Cloud Average Weekday Daily Ridership - Year 2020 Southbound to Minneapolis - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Downtown St. Cloud 66 41 3 16 69 57 East St. Cloud 64 41 3 16 67 57! Clear Lake 20 33 1 13 21 46 . Becker 8. 44 0 17 8 61 Big Lake 493 138 22 52 515 190 Elk River 576 508 26 192 602 700 Ramsey/Anoka 615 479 18 105 633 583 Coon Rapids 1,133 592 39 145 1,172 738 Fridley 1,244 330 76 132 1,320 461 NE. Minneapolis 0 436 0 192 0 628 Downtown Minneapolis Total 4,219 2,643 188 879 4,407 3,521 Northbound to St. Cloud - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Downtown Minneapolis 5 10 0 4 5 14 NE. Minneapolis 0: 3' 0 1 0 4 I Fridley 16 I 1 0 17 1 Coon Rapids 5 2 0 1: 5 3 Ramsey/Anoka 5 0 0 0 5 0 Elk River 30 18 1 7 31 25 Big Lake 74 30 3 11 77 41 Becker 3 1 0 0 . 3 1 Clear Lake 2 11 0 4 2 1 5 East St. Cloud 2 2 0 1 2 3 Downtown St. Cloud Total 142 78 6 29 148 107~ Notes: (1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the Anoka station. (2) Includes driving to feeder bus station if available. (3) Includes walking to feeder bus station. 12/08/1998 Figure 8 PRELIMINARY RAIL RIDERSHIP RESULTS NORTHSTAR CORRIDOR - Concept B to Rice Average Weekday Daily Ridership - Year 2005 Southbound to Minneapolis - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Rice 71 2 3 1 75 2 East St. Cloud 158 41 7 15 165 56 Clear Lake 18 32 1 12 19 45 Becker 6 35 0 13. 6 48 Big Lake 417 112 19 42 436 155 Elk River 466~ 408 21 154 487 562 Ramsey/Anoka 536 386 16 85 552 470 Coon Rapids 1,075 529 37 130 1,112 658 Fridley 1,218 327 75 131 1,293 458 NE. Minneapolis 0 413: 0 182 0 595 Downtown Minneapolis -~ - - Total 3,966 2,285 178 765 4,145 3,050 Northbound to Rice - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Downtown Minneapolis 9 10 0 4 9 14 NE. Minneapolis 0 5 0 2 0 7 Fridley 13 1 1 0 14 1 Coon Rapids 4 1 0 0 4 1 Ramsey/Anoka 4 0 0 0 4 0 Elk River 16 9 I 3 17 12 Big Lake 47 23 2 9 49 32 Becker 2 1 0 0 2 1 Clear Lake 2 9 0 3 2 12 East St. Cloud 0 0 0 0 0 0 Rice . Total 97 59 4 22 101 81 Notes: (1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the ^noka station. (2) Includes driving to feeder bus station if available. (3) Includes walking to feeder bus station. 12/08/1998 Figure 6 PRELIMINARY RAIL RIDERSHIP RESULTS NORTHSTAR CORRIDOR - Concept B to Rice Average Weekday Daily Ridership - Year 2020 Southbound to Minneapolis - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Rice 73 2 3 1 76 2 East St. Cloud 159 45 7 17 166 62 Clear Lake 20 33 1 13 20 46 Becker 8 44 0 17 8 61 Big Lake 493 138 22 52 5151 190 Elk River 576 508 26 192 602 700 Ramsey/Anoka 615 479 18 105 633 583 Coon Rapids 1,133 592 39 145 1,172 738 Fridley 1,244 330 76 132 1,320 461 NE. Minneapolis 0 436 0 192 0 628 Downtown Minneapolis Total 4,320 2,607 193 865 4,513 3,472 Northbound to Rice - Boardings by Station of Origin (1) Station Work Trip Other Trips All Trips Drive Access Walk Access Drive Access Walk Access Drive Access Walk Access (2) (3) (2) (3) (2) (3) Downtown Minneapolis 5 10 0 4 5 14 NE. Minneapolis 0 3 0 1 0 4 Fridley 15 1 1 0 16 1 Coon Rapids 5 2 0 1 5 3 Ramsey/Anoka 5 0 0 0 5 0 Elk River 26 17 I 6 27 23 Big Lake 62 31 3 12 65 43 Becker 4 1 0 0 4 1 Clear Lake 3 10 0 4 3 14 East St. Cloud 1 0 0 0 I 0 Rice - - Total 126 75 6 28 132 103 Notes: (1) For example, a round trip from Anoka to Minneapolis is counted as 2 boardings at the Anoka station. (2) Includes driving to feeder bus station if available. (3) Includes walking to feeder bus station. 12/08/1998