5.2. & 5.3. SR 05-10-2004 Item # 5.2 & 5.3. MEMORANDUM TO: Mayor and City Council FROM: Pat Klaers, City Administrator DATE: May 10, 2004 SUBJECT: Other Business Additions - Ice Arena Floor and Koehler Property Updates Ice Arena Floor The Barn floor replacement project is underway, Ice Arena Manager Rich Czech will be in attendance to discuss a change order for the floor replacement project. Consideration of this change order item is time sensitive and cannot wait until the May 17 meeting, If possible, information regarding this item will be attached to this memo and if not, this information will be presented Monday evening, Koehler Property Update The city has been pursuing the purchase of the Koehler property, which is next to the Bailey property, for the anticipated Library expansion project. The appraisal has been completed and on Monday evening, I would like to update the City Council on a meeting Finance Director Lori Johnson and I had with Mr. and Mrs,Koehler on Friday, May 7, 2004. To: Mayor and City Council From: Rich Czech, Arena Manager Subject: Change Order for the replacement of the Barn's floor Date: May 7, 2004 Thursday May 6th, I had a construction meeting with Scott Ward from Stevens Engineering and Mark Rodorigo from Commercial Refrigeration. Our main discussion was about the radius of the south end of the rink. Two major problems were found in this area when the boards were removed. I will be attending the City Council meeting to discuss the problems and the solution to them. (nt) \.i..e.::n ~2) """"""'" cc I~Mdow 5-lo.-OY [-krl 5. () -i- S-I 3 STEVENS ENGINEERS May 10, 2004 Mr Rich Czech City of Elk River 13065 Orono Pkwy Elk River, MN 55330-5600 RE: Ice Rink Floor and Dasher Board Replacement Projects -RFl#1 Our File No, 6008 Dear Rich: Enclosed is the ,proposal from the contractor for replacing the perimeter concrete edge on the south end of the rink. As you know, after the existing dasher boards were removed it was discovered that the south radii on the existing perimeter concrete was poorly shaped for proper installation of a new dasher board system. It would be difficult and probably impossible in some locations to properly anchor the dasher boards in this area without using external posts. Some anchors would have to be placed in the rink floor concrete as well. If the conditions were left as-is the new dasher boards would be partially on and parna,lIy off the rink slab depending on the location, It would also be difficult, in some areas, to obtain the proper overhang distance of the dasher boards onto the rink slab to assure solid ice along the edges. The other main factor to consider is that the two radii on the south end would be slightly different in order to match the existing conditions; there may be an additional cost to fabricate the different radii. If you have any questions regarding this information or would like to disouss it further please call me at 651,436.2075, Yours very truly, STEVENS ENGINEERS, INC. .~~G.~ Scott A Ward, P.E, Enclosure 1656 LivinQstone Road. Hudson, WI 54016 715~386.5819. 651-436-2075 . 800-622-7670 . fax.: 715-386-5879 . 'WWw.stevensenglneers,com -. .-.--..., -, \\........ "...~ ..IU/....i:::'OCIllCI P.2 ~ --- STEVENS ENGINEERS - .: . .. , Proposal Request. :" ~fClCt NI!DC: Elk.tiwt loe.Amaa 0w'Dc: dtyof Elk River cOostrw:tion P2opou!, No.: #1 DC 5..f..04 htUea: No..: 6009 FfQJU: S~ Ward StBvent ~ .'l .. To: Mark Rodoxi:$9 ~(;W Rc:ftipration 104:E. Chesl:rmt &t V~ MN '~79.2. Re: ~~9f~~ecIge 1'Itis i1ilJ~ ~/i1r. wt1fkdese1'lbttd~. The~ isin~ tenJt$ 0Jatp _ tine<< it.ot """~iI7Je:st::rik dzejiJ! ICOJIf! of'WtJlk. 1Jre' ~sshtntiJ~~~. tM~lIPfHdWflt'k ~ trJ ..~ tId8/t>>m. THIS IS NOTA. DlRECTIYE TO 1lEG1N PROPOSED 1roRE. R.-w the' ~ Ml"'IO~~/Jr~QfIIt/. ~IO lite OwtrI!r.~cm wtll NJfr'Im ~~~hubem~, DE8CRIPllUN Of" WORK: ~.of~pmimca:r ~ ~ $OU!b * ofMk. In eaneraJ. wodc /l'baIl ~e rvmoving<<is&g~ oonc.rete ~-30" wide !or~~y114lioeat_on tbr: soutb _ ofth.e rink ~bQ!h zadilJS. ~ ~ pIrir!1ettt' CCIICl'de with a newtickae4 edge,with ~~m.1y 20" wide as mown ontbe attached ~ By ibis chaaIr the QVClllI1l ~ ~ will behKmlred by ~ 10~. Jul;lwde flu: COlIt QfaU. ~ wmt it! this pmpoal. Estimated mCh:UX(~) m ConItact Tune: -L~ days MfICbod ~f ddcw.iu.iug dwlge in ~ prioe: ___Unit PriCX':S -X.... Lump SUII\ ~) ., t" .', , : CON'l'RACTORt P.,,~imnpsomcostfbr~tbe~~.$i$~ $ "44. ..: IfthfR are anyqw::stiom ~ tis ~ ctJI:Ibu::t ~ ~.. 6S1.A.36.zD75. .: . )ka~A~; r~~~ddm'1. END 1 ,', DRILL IN AND EPOXY DOWELS IN EXISTING SLAB 5" MIN. IMBEDMENT (TYP) EXISTING CONCRETE CLEAN SAND 5" jL } 4 u ~ REPLACE PERIMETER CONCRETE THICKNESS TO MA TCH EXIST\NG WITH 4" MIN. #4 REBAR @ 16' O.C EXPANSION JOINT - ~ - ~ " 12" 8 It .. #5. REBAR (4 TOTAL) tv1ETER EDGE SECTION - - ~ ~ 8 12" 8