Action Requested
Approve, by motion, 2015 Seal Coat Improvement plans and authorize staff to advertise the project for
bids.
Background/Discussion
Staff has prepared plans and specifications for the 2015 seal coat project. This year’s project continues
the same approach that was approved and followed in 2014. We again are proposing to continue the
process of crack filling all streets in the city on an 8-year rotation. This is our primary defense for water
penetrating roadway surfaces.
We re-evaluated the surface conditions of all of the roadways which were crack-filled in 2014 to
determine, of those segments, which ones should be seal coated this year. We are no longer blanket
covering all of those segments, but rather seal coating segments that, without treatment, would be subject
to excessive premature failure.
The attached plan represents the areas proposed to be seal coated this season. For the past two years the
crack filling work has been contracted as part of our seal coating project. This year, the crack filling work
will be completed with city crews.
Upon approval, staff will advertise the project for bidding and bring the lowest responsible bid back to
the City Council for consideration and final approval.
Financial Impact
There is no cost associated with the requested action. The budget for 2015 preventative maintenance is
$365,199. Once bids are received, staff will evaluate the remaining budget to determine if other further
deteriorated areas can be treated with a more comprehensive mill and overlay within the budget.
Attachments
2015 Seal Coat Map
T
196TH AVE NW
190TH CIR NW
Orono Lake
7TH ST NW
5TH ST NW
BUSINESS CENTER DR NW
ORONO PKWY NW
Mississippi River
Kliever Marsh
175TH CT NW
173RD AVE NW
2015 Seal Coat Improvements
2015DoubleSealCoat
161