Loading...
4.4. SR 09-25-2000Item 4.4. Howard R, Green Oompany QONSULTING ENGINEERS September 20, 2000 File: 230000M-0325 Honorable Mayor and City Council City of Elk River 13065 Orono Parkway P.O. Box 490 Elk River, MN 55330-0490 RE: UPDATE ON CURRENT PROJECTS Dear Council Members: This correspondence is intended to provide a brief written follow-up to the projects listed in Pat Klaer's memo to the City Council. 1. Signals on County Road 1 at School Street and County Road 77 As the City Council is aware, this is a County project. The County has recently indicated to the City that two small easements are needed for the School Street installation. We have prepared the documents and sent one to the School District for their consideration. The other was passed on to Howard Roston, City Attorney, for acquisition from the apartment complex at the southeast corner of the intersection of School Street and County Road 77. Sherburne County has recently opened and awarded the bid for these two projects to Design Electric, Inc. They are in the process now of scheduling a preconstruction meeting, anticipating that the easements will be forthcoming. This would indicate that construction will likely occur this fall, with delivery of signal equipment and installation sometime in the winter months. No Parking Signage and Crosswalk at East Side of Lowell Avenue on Main Street. Phil Hals has received a few calls regarding concerns about the difficulty in crossing Main Street at Lowell Avenue with cars parked in that area and no designated crosswalk. Apparently, senior citizens from south of Main Street use this route to walk over towards the convenience store/gas station located near Highway 10 for minor groceries. It may also be used just as a walking route. I have been working with Phil Hals to prepare a proposal relative to eliminating one or two parking stalls on the south side of Main Street and potentially installing a painted and signed crosswalk at this location. When more specific information is available relative to our proposal, we will present it to the City Council. O:\PROJ~230000M\0325\Itr 9-20-00 Council. Summary.doc 1326 Energy Park Drive · St. Paul, MN 55108 · 651/644-4389 fax 651/644-9446 toll free 888/368-4389 Honorable Mayor and City Council September 20, 2000 Page Two 3. Business Center Drive/Waco Street City Council discussed the bids for this project several meetings ago, and by consensus indicated the project would be awarded once the final plat of Elk Path Business Center was filed and all the necessary paperwork was in place from MnDOT. We have been waiting until Monday of this week for the MnDOT paperwork to be complete. It is now complete; therefore, attached are a memo and a resolution formally awarding the Western Area Phase IV improvement project to Richard Knutson, Inc. We would recommend adoption of this resolution. The Contractor has started some preliminary work in the area last week. Major work should begin in the near future. It would be our intent to get as much construction done as weather permits this fall. 4. Holt/Irving Sewer Main Lining This is a project that the City Council awarded a couple of meetings ago. We have just completed the paperwork with the Contractor for this project and held the preconstruction conference. We are prepared with a newsletter to be mailed to the affected property owners. The work should be accomplished sometime during the middle of October. Highway 169/County Road 33 Signal (temporary) and Interchange Projects for 2003 MnDOT has hired a consultant, EnviroScience, to provide a scoping document for the proposed interchange at TH 169 and County Road 33. Along with Steve Rohlf, Councilmember Dietz, and Scott Harlicker, I recently attended a Technical Advisory Committee meeting relative to this interchange. Attached for your information is the packet of alternatives they are considering for the design of the interchange. I will be available to discuss these options in more detail. However, it should be noted that it is staff's opinion that Alternative No. 1 would be the most desirable. Another item that should be noted regarding the same intersection has to do with the proposed temporary signal. As the City Council is aware, MnDOT has agreed that a temporary signal is warranted at this intersection and was prepared to install it in 2001. It was originally planned to be installed in 2000, but due to funding necessary for the County portion of this project, it was pushed back one year to allow for budgeting of these moneys. This was before money became available for the proposed interchange at this intersection. MnDOT has indicated to Sherburne County that the County may install a temporary signal here. We believe it is important that the temporary signal be installed even though an interchange is planned for 2003. We believe this because of potential traffic safety issues at this interchange due to the large number of gravel trucks accessing the highway at this point. We think that the signal will serve a useful purpose in maintaining traffic during the construction of the interchange. The interchange is planned to be bid in early 2003 and it is anticipated it will take at Howard R. Green Company O:\PROJ~30000M\0325\Itr 9-20-00 Counc~l~lEl~.~ff~JG ENGINEERS Honorable Mayor and City Council September 20, 2000 Page Three least two construction seasons to complete. This would indicate that the interchange will not be fully operational until sometime in 2005. Therefore, a temporary signal installed early next year would be operational for four to five years. For the City Council's consideration, we have prepared a draft resolution that would indicate to the County that the City Council wants the temporary signalization of this intersection to proceed. 6. East Elk River Public Improvement Project There are several projects ongoing in the East Elk River area. Work is proceeding on Tyler Street south of County Road 12. This portion of the City project will be substantially complete with the final lift of bituminous and signing and striping of the road yet this fall. North of County Road 12, the road has proceeded as far as it can prior to connecting to County Road 13. The first lift of blacktop is on this portion of Tyler Street north of County Road 12. The Main Street/TH 169 project is starting to take shape. As of the time of this correspondence, the first lift of blacktop was on all portions of Main Street east of TH 169. The watermain was all installed west of TH 169 and the Contractor was in the process of reconnecting services to the new watermain, after which the paving of the roadway can proceed. We believe that within the next three weeks Main Street will be opened to unrestricted traffic. The County Road 12 project has begun this fall. The Contractor is only going to construct the first approximately 3,000 feet of the roadway. That would go from the intersection of County Road 13 to about 400 to 500 feet east of Tyler Street. This should be complete with curb and gutter and the first lift of blacktop before the onset of winter. The completion of the northern end of Zane Street in Elk River Crossing has begun this week. The surcharge is being removed, utilities installed, and a temporary street surface put in place. The roadway will be temporary in nature because there may be some minor additional settlement that can be anticipated through the next year. Therefore, this roadway will be monitored to determine if settlement continues to occur. Approximately a year from now, a decision will be made relative to the completion of the final roadway including the concrete curb and gutter. Until such time, a portion of the Developer's money will be withheld to ensure that there are sufficient funds available to construct the permanent roadway. The other project in this area is 175th Street improvements. City Council had originally directed that this project should proceed in 2001. Staff is continuing work on this schedule, anticipating that a neighborhood meeting would be held on October 17. At that meeting, the concept of landowners giving easements in exchange for no street assessments will be discussed with the residents and easement documents will be distributed. This will initiate the land acquisition phase. As I have indicated in the past, plans for this project are approximately Howard R, Green Company O:\PROJ~230000M\0325\Itr 9-20-00 Coun~pJ~-fl'fF~JG ENGINEERS Honorable Mayor and City Council September 20, 2000 Page Four 75% complete and will be completed by the spring of 2001. The one hang-up this project may encounter in being constructed in 2001 is that County Road 12 will be under construction for a good portion of the year. At a later date, a decision can be made whether or not to begin the project on 175th Street later during the 2001 construction season or to hold it back until the spring of 2002. 7. Auburn Street As Council has directed, I have organized and facilitated a meeting of staff members to brainstorm and discuss options for dealing with the neighbors' complaints regarding the amount and speed of traffic on Auburn Street. I am currently preparing a draft of the minutes from that meeting which will be reviewed by all attendants and will be available to present to the City Council at an upcoming meeting. 8. Pavement Replacement Program It is my understanding that a pavement replacement program was discussed briefly during the recent budget cycle. City staff has done a substantial amount of work on this project several years ago. The project sat for awhile as the East Elk River project proceeded through design and on to construction. At any appropriate time, staff would be available to present the pavement replacement program to the City Council as a whole for their consideration and direction. It is my understanding that initiation of this project may not happen until 2002 or 2003, depending on the availability of funding. It still would be a worthwhile exercise to get the program into shape and understand what is involved prior to initiating the first project. 9. Highway JO/Main Street Intersection Based on City Council's recent discussions, we have started to revisit this issue and will in the next few weeks be available to present some findings and options to the City Council for their consideration. Timing is appropriate for this project as one of the funding scenarios we can consider would be application for a TEA- 21 grant when the next round of solicitations occurs in late November. This is just a brief update on each of these projects. I will be in attendance at your September 25, 2000, City Council meeting and will be able to discuss any of these projects in greater detail. Sincerely, Howard R. Green Company Terry J:'M'aurer, P.E. TJM:tw Attachments Howard R. Green Company O:\PROJ~30000M\0325\Itr 9-20-00 Coun~__.,~-~r~G ENGINEERS Howard R, Green Company CONSULTING ENGINEERS September 19, 2000 File: 807650-0060 Honorable Mayor and City Council City of Elk River 13065 Orono Parkway P.O. Box 490 Elk River, MN 55330-0490 RE: WESTERN AREA PHASE IV AWARD OF PROJECT Dear Council Members: Bids were opened on Friday, August 11, at 10:00 a.m. for the above-referenced project. Richard Knutson, Inc., was the Iow bidder in the amount of $1,341,751.66. As discussed at the August 14, 2000, City Council meeting, award of the project was conditioned upon the final plat of Elk Path Business Park being recorded with Sherbume County and that the City receive a fully executed set of plans from MnDOT. The plat was recorded and we have received the necessary paperwork from MnDOT including a signed set of plans and a fully executed agreement. Therefore, attached is a resolution awarding the Western Area Phase IV Improvement project to Richard Knutson, Inc. We would recommend City adoption of this resolution. If you have any questions regarding this project, I will be in attendance at your September 25, 2000, City Council meeting. Sincerely, Howard R. Green Company Terry J. ~aurer, P.E. TJM:tw Attachment O:~PROJ~807650~:X)60~tr 091400 Council.doc 1326 Energy Park Drive · St. Paul, MN 55108 · 651/644-4389 fax 651/644-9446 toll free 888/368-4389 RESOLUTION 00- A RESOLUTION FOR THE CITY OF ELK RIVER A RESOLUTION ACCEPTING BID AND AUTHORIZING EXECUTION OF CONTRACT IN THE MATTER OF THE WESTERN AREA PHASE IV IMPROVEMENT OF 2000 WHEREAS pursuant to Resolution 00-50, competitive bids were solicited and received for the Western Area Phase IV Improvement as set forth in the bid tabulation attached hereto and incorporated herein by this reference; and WHEREAS the City Council has considered the amount of the bids and the responsibility of the bidders and determined that Richard Knutson, Inc. is the lowest responsible bidder; NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Elk River, Minnesota: The Mayor and City Administrator are authorized and directed to execute, on behalf of the City, such contract with Richard Knutson, Inc. as is approved by the City Attorney for the completion of the Western Area Phase IV Improvement according to the approved plans and specifications designated in Resolution 00-50. The City Administrator is authorized and directed to forthwith return to all bidders the deposits made with their bids upon execution of the contract above specified. Passed and adopted this 25th day of September, 2000. Stephanie A. Klinzing, Mayor ATTEST: Sandra A. Peine, City Clerk O:\PROJ\807650\0060\Res-O702OO-SpecsBids-WesternlV.doc ADVISORY COMMITTEE MEETING September 15, 2000 T.H. 169 & County Road 33 S.P. 7106 - 66 Prepared by: Enviroscience H:L2000~0000.46 TH 169L4,dvisory Committee Meeting 9-15-2000.doc TABLE OF CONTENTS 1. Index Map 2. August 24, 1999 Traffic Counts 3. 2003 Traffic Projections e ® 2023 Traffic Projections Future Co. Rds. Improvement Project 6- 13 Alternatives 1 through 10 14- 15 Intersection Configurations Notes: Alternative 5 also presents Alternative 6, 7 and 8 H:~2000k20000.46 TH 169LAoeviso~' Committee Meeting 9-15-2000.doc % · · o INDEX £ittl~ MAP ? - / ??'-,..' '- .~~MN/DOT ...- (320) 255-4229 ST. CLOUD, MINNESOTA File Name : 33169 Site Code : 00000000 Start Date : 08/24/1999 Page No :2 Groups Pfinled- 1 - Unshifted TH 169 ........... CR 33 1R'169 'CR-33' From North From East From South From West Start Timei Right Thru Lefl / ruII L 'I' o~a~; --F~-c'tb-T----l'.0-,'--l:0 ..... 1.0 .... 1.0 1:0 1:0 1:01---'170; 1.-D, 1['. 10-1~'[7.0, 1.0 t 1.-0 i 1.0 i 1'70 f 1.0 04~00-PM-~'----6-:-- 174 ...... 6 0' 1 ..... 5 ....... 5-h----0, 8 3T3~29 0 i 1-0 ' 3 ' 6--0-F---~566-' 04:15 PM 9 181 6 0 f 7 2 649 04:30 PM 3 198 5 0; 3 9 637 04:45 PM 4 184 0 0: 5 4 645 lotal 22-'---737--~,-17---0 16--20-- :2497- 12 5 3 8 8 4 160 206 25.9 33.4 0.8 1.0 05:00 PM 8 146 2 0 05:15 PM 5 170 I 0. 05:30 PM 0 163 1 0 ~ Grand Total 268 9313 134 0 Apprch % 2.8 95.9 1.4 0.0 Total % 1.3 43.8 0.6 0.0 9 0r 12 7 O! 15 5 o; 12 26' O; .47 4 0 13 6 0 14 3 0 10 251 0 264 40.7 0.0 2.7 1.2 0.0 1.2 I~t lb~ Out In Total F9-1:42'I I-9~1-~ ,,'f885'T1 ~-268T93-13'7--1-3:4T~-0~ -] -Rig-fit-Th-ru--Le-~E-'P e-'d s ? North ~12~799-6~0T.' O 0-AT~F 8/24/99 5:30:00 11 - Unshifted Left Thru Right Peds ~ ,'97ZZ ~ TH 169 377 26 350 26 379 22 Y4~9--T03- 399 29 369 29 354 28 8725 733 89.7 7.5 41.0 3.4 0 0 0 0 0 0 0 11 4 5 0 12 3 6 0 17 6 7 0 50'--T6 2a. 0I 12 8 5 0 15 4 3 0 14 7 8 0 755 208 257 0 61.9 17.0 21.1 0.0 3.5 1.0 1.2 0.0 6A3 627 - 800 21274 ~ m 0 )> 0 c.. ~ ~ frl :x I"q C) u'l 0 -I m m I'Z75 LT ~ T 5 02 'z,~$ ~T ENVIROSOIENCE ENGINEERS * SCIENTISTS ' LAND SURVEYORS 10200 VALLEY VIEW ROAD surrE 15tA EDEN PRAIRIE, MINNF..8OTA 5~344-3544 (S12) ~,4-s4ee PROJECT SHEET NO. BY DATE. JOB NO CHECKED BY__DATE REMARKS N NT P~- REMOVED AS PART FUTURE PROJECT INERS IN THE FUTURE FUTURE NEW ROAD FUTURE CUL-DE-SAC RADIO TOWERS- ::{RENT ELK RIVER S.P. 7106-66 / / / / / \ \ FUTURE LOCATIO CO. RD. PARCLO ~p~RAMPS AND THREL ,.OOPS NC DURING OF THE TIME PARCLO , i ./ TWO RAMPS AND TWO L ,3PS / ELK RIVER., × ALTERNATIVE 2 S.P. 7J06-66 ~/ / \ - / ~ '~ ......... "'-' FRONTAGE~ ~ ~ ' · ONE RAMP AND THREE LvOPS ELK RIVER / ALTERNATIVE 3 S'P' 7106~6 ~ . ~ . ~ ~ .., .. 'x~~~.~ .',,~~~ x - ~ . ~.:,~,,~.. -~.- ...~.:, , ~ ~ LOCATIC. / ~ /; I ~ -~ ~ co..~.:~~~ "' ' ~ ~- . : / ~ ~ / NORMALLY MC ST OF ~E TIME. ~ ' Y ~ ~ ~ I ~ / DURING CON81'RUCTION ; .... ~ ~~~ [ ~ / , /~ us~ P.OCTO. ST~,T ~~ ~ ~ ~ ~/ ~ I/ FOR DETOUR.T.H. 169 N.I ~ ~~~f~ : !~ : ~ ---~ / ~~ ~~ [ ~I~ .~ ~~~ -,,./~. r. ='' ' "'~ ELK RIVER S.P. 7106-66 / / / / ? \ / \ FUTURE ~__~\ LOGATIC CO. RD. DIAMOND ALTERNATIVE 4 STAGE STRUCTION ~l.W. AND N.E. RAMPS ARE CO. RD. 33 FROM T.H. 1 N. OF CO. RD. 33 WILL PROCTOR STREET ELK RIVER S.P. 7t 06..66 PARCLO TWO RAMPS AND TWO L~JOPS ALTERNATIVE 5 ICTION BYPASS ~- ,. PARCLO ~ ~ ELK RIVER ALTERNATIVE 9 ~,,,,~ .__- E":-~.~L~ s.P. 7 t 06~6 ~ ~ ' / X-~~C .'/ ' ~ ~ ~-''' ' ' t ~ ~"~ ' ..... '" ' , , ~~ I ' ~- ' ~ ' ~ ....... . . ..... . LpROPO~E[ - ~ . '~ -7~'~ ~"/ /-~- ' ='" - ~ ~. ~~ ~~ :,~ . .~_ ]/ ~ // / . ~ ~ - ~. I= .. ~ ,~1 ZFk~ "~. '" -J] , ELK RIVER S.P. 7106..66 I / / / / / \ / \ / \ FUTURE LOCATIC CO. RD. SPLIT PARCLO ALTERNATIVE 10 IN STAGE INTERSECTION CONFIGURATION ENVIROSCIENCE ENGINEERS * SCIENTISTS "LAND SURVEYORS 10200 VALLEY V1EW ROAD SUITE 151A EDEN PRAIRIE, MINNESOTA 55344.-3544 (e12) 944--848~ PROJECT S.~ ~ [06 ~"~6 SI--IEET NO BY DATE JOB. NO CHECKED BY DATE REMARKS : ' i ' ' ' : ..... : ' : ....... ' ....... ! ' Z . ' ; ' ' ' : ' :'":'":"': .......... i ............. i'";'":"'!"'! .... :" : ............... .......................... -....i....: INTERSECTION ...... CONFIGURATION ENVlROSI]IENI3E ENGINEERS · SCIENTISTS · LAND SURVEYORS 10200 VALLEYVlEW ROAD SUITE 151A EDEN PRAIRIE, MINNESOTA 55344-3.544 (612) ~ BY DATE CHECKED BY DATE REMARKS SHEET NO.. JOB. NO. }5 RESOLUTION 00- A RESOLUTION OF THE CITY OF ELK RIVER A RESOLUTION INDICATING CITY SUPPORT FOR THE INSTALLATION OF A TEMPORARY SIGNAL SYSTEM AT THE INTERSECTION OF TRUNK HIGHWAY 169 AND COUNTY ROAD 33 WHEREAS MnDOT has done a Signal Warrant Study at the intersection of TH 169 and County Road 33, the results of which indicate a signal is warranted; and WHEREAS MnDOT has recently been allocated funding for the installation of an interchange at this same intersection to be let in 2003 with construction anticipated to take two seasons after the letting; and WHEREAS a temporary signal system would provide for a safer intersection until such time as the interchange project is let, and would provide for better operation of the intersection during the construction of the interchange. NOW THEREFORE BE IT RESOLVED by the City Council of the City of Elk River, Minnesota: The City Council strongly recommends to the Sherburne County Board of Commissioners that the temporary signal system for the intersection of TH 169 and County Road 33 move forward as quickly as possible with installation of said signal system as early as permitted in the spring of 2001. Passed and adopted this 25th day of September 2000. ATTEST: Stephanie A. Klinzing, Mayor Sandra A. Peine, City Clerk O:\PROJ\811970J\0325\Resolution 9-20-00.doc Howard R, Green Company CONSULTING ENGINEERS September 19, 2000 File: 808200-0071 Mr. Pat Klaers City Administrator City of Elk River 13065 Orono Parkway P.O. Box 490 Elk River, MN 55330-0490 RE: MAIN STREET/TH 169 IMPROVEMENTS CHANGE ORDER NO. 1 Dear Mr. Klaers: MnDOT has requested some minor changes in the temporary signal currently being installed with the Hardrives, Inc., contract for the improvements along Main Street in the vicinity of TH 169. The changes requested by MnDOT were to increase the size of the conduit from 2-inch to 3-inch and to add additional loop detectors. This resulted in an increase in the contract pdce to Harddves, Inc., in the amount of $4,352.48. Attached are three copies of the change order signed by Harddves, Inc., for this increase work. We recommend approval by the City Council for Change Order No. 1 to the Main Street/TH 169 Improvement project. If you have any questions regarding this issue, I will be in attendance at the City Council's meeting on Monday, September 25, 2000. Sincerely, Howard R. Green Company Terry J. Maurer, P.E. TJM:tw Attachments O:~ROJ~808200\0071~ltr 9-19-00 Klaers CO#1.doc 1326 Energy Park Drive · St. Paul, MN 55108 · 651/644-4389 fax 651/644-9446 toll free 888/368-4389 (Instructions on reverse side) CHANGE ORDER NO. 1 PROJECT: Eastern Area Phase III Street & Utility Improvements OWNER: City of Elk River 13065 Orono Parkway Elk River, MN 55330 CONTRACTOR: Hardrives, Inc. 14475 Quiram Drive Rogers, MN 55374 CONTRACT FOR: Eastern Area Phase III Street and Utility Improvements DATE OF ISSUANCE: 8109/00 OWNER's Project No. 808200J ENGINEER: Howard R. Green Company 1326 Energy Park Drive St. Paul, MN 55108-5202 ENGINEER's Project No. 808200J You are directed to make the following changes in the Contract Documents. Description: Plans (Sheet 44&45) TH 169/Main St. Signal 1. The 2" RSC from poles 1, 2, 4, 5 should be changed to 3" RSC. (TH 169 Signal) 2. Detectors D8-2, D4-2, D4-3 should be changed from one 6'x6' NMC loop to two 6'x6' NMC loops. (CSAH 13 Signal) Purpose of Change Order: Mn/DOT comments Attachments: Revised plan sheets 44 and 45 CHANGE IN CONTRACT PRICE: Original Contract Price $ 847,023.37 Previous Change Orders No. $ 0.00 to No. Contract Price prior to this Change Order $ 847,023.37 Net Increase (D~.,~,~o=) of this Change Order $ 4,352.48 Contract Price with all approved Change Orders $ 851,375.85 CHANGE IN CONTRACT TIME: Original Contract Time 55 working days days or date Net change from previous Change Orders 0 working days Days Contract Time Prior to this Change Order 0 workinq days days or date Net Increase (Decrease) of this Change Order 0 workinq days Days Contract Time with all approved Change Orders 55 working days days or date RECOMMENDED: By Howard R. Green Company EJCDC No. 1910-8-B (1986 Edition) APPROVED: By City of Elk River Hardrives, Inc. O:\PROJ~8082OOJ~0071\ChangeOrder~l .doc I VEHICLE DETECTION NO. SIZE FUNCTION LOCATION 01-1 4-6x6 1 AS SHOWN )I-2 4-Bx6 1 AS SHOWN 02-1,02-2 6x6 3 500 03-1 2-Gx6 J t JAS SHOWN 03-2 2-Gx6 1 AS SHOWN 04-1.04-2 6x6 j 1 J AS SHOW~ 04-3,04-4 6x6 ? AS SHOWN 04-5.04-6 6x6 ? AS SHOWN 05-1 4-6x6 1 AS SHOWN 05-2 4-6x6 1 AS SHOWN 06-1,06-2 6x6 3 500 D?-1 4-BxB 1 AS SHOWN ,7-2 4-$xBJ 1 lAS SHOWN 2-6x6 1 AS SHOWN DB-3,DB-4 6x6 7 AS SHOWN 08-5.08-6 6x6 7 AS SHOWN LOOP FUNCTION: 1C&E = CALL & EXTEND 3 E = EXTEND ONLY 7 DELAY CALL - IMMEDIATE EXTEND ALL LOOP DETECTORS SHALL BE INSTALLED IN NMC UNLESS OTHERWISE INDICATED 2" RSC 4" RSC --~ INSTALL PEDESTAL FOUNDATION 1Sit FOR 10 FT. PEDESTAL BASE EXTEND INTO HH 14 12 11 2" RSC 4" RSC 4" RSC <)INSTALL PA100 POLE FOUNDATION EXTEND INT0 H.H.IO 3" RSC DESIGNED BY: CNR DRAWN BY= BAS APPROVED BY: HDP JOB NUMBER 8082OOJ CAD DATE: 6-25-2000 6-23-2"000 R£~.~. 12007 R£VtSII~D£SCRIPTION 04-2 L4" RSC 4" RSC % II II 2" RSC 6" RSC 4 OINSTALL PA100 POLE FOUNDATION EXTEND INTO H.H.4 3" RSC ,[ 08-2 DB-] 7 II Il II Il Il // / RSC 1326 ENERGY PARK DRIVEJ . ST. PAUL, MINNESOTA 55108 I [651) 644-4389 JHoward R Green Company CONSULTING ENGINEERS I" RSC RSC NOTES: 1. CONDUIT BETWEEN HH 19 AND EOUIPMENT PAD AND HH 1 AND CONTROLLER CABINET SHALL BE CAPPED AT LOCATION OF FUTURE CABINET. 2. DETECTOR LOCATIONS WILL BE VARIFIED IN THE FIELD BY ENGINEER PRIOR TO 3. ALL NEW LOOPS SHALL BE INSTALLED IN NMC. / // / OINSTALL PEDESTAL FOUNDATION FOR 10 FT. PEDESTAL BASE EXTEND INTO HH 5 3" RSC CITY OF ELK RIVER SIGNAL SYSTEM ELK RIVER, MINNESOTA 2000 SEE STANDARD PLATES: Bl12C - PEDESTAL FOUNDATION 8114A - PVC HANDHOLE/PULLBOX B1210 - TRANSFORMER BASE AND POLE BASE PLATE B126F - POLE FOUNDATION (50 SCALm O 10 20 ~ INTERSECTION LAYOUT UNDERGROUND EQUIPMENT MAIN STREET AND T.H. S.A.P. 204-113-09 169 Il NOTES: 1. HH §,9 AND 12 SHALL BE CONSTRUCTED TO ALLOW FOR FUTURE CONNECTION OF 2" RSC TO SIGNAL BASE. 2. HH 2 SHALL BE CONSTRUCTED TO ALLOW FOR FUTURE CONNECTION OF 4" RSC TO FUTURE HH I(NW OF HH 2) AND 5" RSC TO FUTURE CONTROLLER CABINET CNW OF HH 2) 3. DETECTOR LOCATIONS WILL BE VARIFIED IN THE FIELD BY ENGINEER PRIOR TO INSTALLATION. 4. ALL NEW LOOPS SHALL BE INSTALLED IN NMC. 6*00 MAiN ST. E.B. D2-2 (50 M.P.H.) ~2-1 4jj 4" RSC II II II II APPROVED BY: HDP JOB NUMBER CAO CAD FILE m~cao~o~ .... ~ ~'~'-- THE BACK OF THE LOOP DETECTOR SHALL BE PLACED 120'FROM THE CROSS WALK 4" RSC 2,,,/ / / II II II II II II II 7+00 II II II II II /11 II RSC 4" RSC II 8~00 VE~. NO. SIZE, - D1-1 6x12 D1-2, D1-3 6x6 __ ~2-1,D2-2 6x6 ~ D3-t. D3-2 (2) 6x6 3 ~3-3, D3-4 6x6 1 -- D4.1 6x6 1 ~ D4-2 ?~.") 6x6 7 ~AS Sh, D4-3 [.~) 6x6 1 ~S SHOW, . DS-1 Gxl2 3 AS SHOWN. J D5-2 Gx£ 1 AS SHOWN_ ~6-1, D6-2 6x6 1 AS SHOWN - D8-1 6x6 1 120 D8-2 L~.") 6x6 7 JAS SHOW~ OOP FUNCTION: (~)= CALL & EXTEND (~) = EXTEND ONLY (~) = DELAY CALL - IMMEDIATE EXTEND ALL LOOP DETECTORS SHALL BE INSTALLED IN NMC uNLESS OTHERWISE INDICATED 4" RSC 2" RSC RSC  i32(~ £NER~IciTY DF ELK RIVER ELK RIVER. MINNESDTA 2000 Ho_ward R. Green Company 1/ GNA SYSTE CONSULTING ENGINEERS 40 SCALE ~- 0 10 20 INTERSECTION LAYDUT S.A,P. 204- - UNDERGROUND EOU]PMENT MAIN STREET AND C.S.A.H- 13