3.3. SR 07-19-2004TO:
FROM:
DATE:
SUBJECT:
MEMORANDUM
Mayor and City Council
Lori Johnson, Finance Director
July 19, 2004
Consider Change Orders
Item # '3.3.*
The following change orders have been requested on the city hall building projects. As with
previous change orders approved recently, most of these have already been completed.
Bid Package Change Order Change Order
Contractor Number Number Amount
CITY HALL/PUBLIC UTILITIES
Direct Digital Controls
(Replace VFD or AHU #4)
Steinbrecher Painting
(Additional Painting)
Albers Mechanical
(Air Handling Coil)
Minnetonka Iron Works
(Work completed by Western Steel)
Weidner Plumbing & Heating
(Work done by Steinbrecher Painting)
Western Steel Erection
(Extra Work Orders)
Garage Door Store
(garage door openers)
Total
Previously Approved
Total Change Orders to Date
37 3 $2,928.00
22 5 959.00
34 5 5,361.00
7 1 (1,830.00)
36 5 (295.00)
8 4 2,575.00
17 1 610.00
10,307.00
137,206.59
$147,513.59
Action Requested
The City Council is asked to approve the change orders as noted above.