Consider Change Orders
The following change orders have been requested on the public safety building project.
Contractor
PUBLIC SAFETY
George Cook Construction
(Cabinet in Elevator Lobby)
George Cook Construction
(Furnish and Install Door Hardware)
George Cook Construction*
(Water Damage Repairs)
North Metro Landscaping, inc.
(Site Preparation)
Omann Brothers, Inc.
(Fairground Entrance)
Total
Previously Approved
Total Change Orders to Date
*This cost is to be reimbursed by the contractor
that caused the water damage.
Bid Package Change Order Change Order
Number Number Amount
14 14 $1,902.00
14 15 2,904.00
14 16 1,292.00
7 1 1,480.00
3 3 2,935.00
10,513.00
314,208.78
$324,721.78
Action Requested
The City Council is asked to approve the change orders as noted above.