Loading...
8.1. SR 12-21-2015 Request for Action To Mayor and Council Item Number 8.1 Agenda Section General Business Meeting Date December 21, 2015 Prepared by Tim Simon, Finance Director Item Description 2016-2020 Capital Improvement Plan Reviewed by Cal Portner, City Administrator Reviewed by Action Requested Approve, by motion, adoption of the 2016-2020 Capital Improvement Plan (CIP). Background/Discussion Over the past several months, city staff and the Council have reviewed the proposed 2016-2020 CIP leading up to its adoption. During various work sessions, we reviewed the costs, funding sources, cash flow analysis (5-year projections), and the general purpose of the projects. The CIP is a revolving document that is re-evaluated on an annual basis; upon each annual update some projects will be deleted, added, or even delayed, reflecting community needs and financial ability to fund the project. The CIP is a long-term planning tool and all purchases over $50,000 will come back to Council for approval per our financial management policies. A few highlights of the CIP for 2016:  Quite Zones (carried over from 2015)  Eastern area trail mobility project  Multipurpose building feasibility study (adjusted from $75,000 to $50,000)  Annual park improvements  Annual vehicle replacements  Human Resource Information System (carried over from 2015) As we discussed on November 2, the public safety departments are going to have to replace their 800 MHz portable radios in the next couple of years, and absent of any grant funding, this will be a significant expenditure. Staff will be proposing at the end of the year if any remaining general fund reserves exist beyond our reserve requirements and after the quiet zones and other recommendations that funds start being set aside for these replacements in the next few years as they are added to future CIP updates. Financial Impact See various funding sources identified in the 2016-2020 CIP. Attachments  2016-2020 Capital Improvement Plan  2016 equipment listing purchases (funded out of Equipment Replacement Fund) CAPITAL IMPROVEMENT PLAN 2016 – 2020 City Of Elk River CAPITAL IMPROVEMENT PLAN 2016 – 2020 Enclosed is the City of Elk River’s Capital Improvement Plan (CIP) for the years 2016- 2020. The document has been prepared for the City Council and Community to anticipate major expenditures in advance of the year they may become budget requests. The CIP is a planning tool that forecasts the City’s capital needs over a five-year period based on the City’s long-range plans, goals, and policies. City staff estimates the amount of funding that is needed for projects to be completed in the next five years. Projects listed in the first year are included in the budget and upon each annual update of the CIP some projects will be deleted, added, or even delayed reflecting community needs and financial ability to fund the project. Approval of the CIP by Council does not authorize spending or initiation of a given project nor allocate funding for any of the projects; it simply states that the Council’s support and acknowledgement of the Capital Improvement Plan as a planning tool. Capital improvements to streets, parks, buildings, equipment, software, and vehicles are included in the CIP. This plan shows the estimated project costs and the anticipated funding source. Specific information is shown on each project within this document. The CIP does not put specific designation on the priority of the projects. This uniqueness of the type of project generally is associated with a funding source. Cash flow estimates are done frequently to review cash reserve levels associated with the project funds. Capital Improvement Plan City of Elk River, Minnesota PROJECTS BY FUNDING SOURCE 2016 2020thru TotalSourceProject#Priority 2016 2017 2018 2019 2020 Bond Proceeds WW-17 4,200,0004,200,000Plant Expansion Master Plan n/a 4,200,0004,200,000Bond Proceeds Total Capital Outlay Reserve AD-05 25,00025,000Council Chamber Upgrades n/a BL-14 16,00012,000 4,000Fitness room equipment n/a CH-06 10,00010,000LED parking lot lights n/a EL-01 45,00045,000Election Equipment n/a FD-10 11,00011,000Thermal imager ladder #1 n/a PD-08 34,50034,500Arbitrator Interview Room System n/a ST-17 12,00012,000Truck mounted message board n/a TC-01 616,000166,000 125,000 145,000 30,000 150,000Annual Technology Upgrades n/a TC-04 75,00075,000Human Resource Information System (HRIS) Software n/a 844,500365,500 150,000 149,000 30,000 150,000Capital Outlay Reserve Total Equipment Replacement Fund BZ-01 55,00027,500 27,500Vehicle Replacement n/a CH-04 50,00015,000 35,000Vehicle replacement n/a Eng-1 25,00025,000Vehicle replacement n/a FD-01 77,00077,000Vehicle Replacement n/a FD-02 102,00050,000 52,000Fire Truck Replacement - Grass Rigs n/a FD-03 500,000500,000Fire Truck Replacement - Engines n/a FD-05 225,000225,000Fire Truck Replacement - Other n/a FD-07 10,00010,000Fire Department-Other equipment n/a PD-01 473,00076,000 117,000 70,000 105,000 105,000Marked Squad Replacement & Additions n/a PD-02 224,00054,000 27,000 62,000 81,000Unmarked Squad Replacement & Additions n/a PD-03 102,00034,000 34,000 34,000CSO Vehicle Replacement & Additions n/a PD-04 196,62644,542 43,000 32,542 48,542 28,000Police Department - Other Equipment n/a PD-07 190,00040,000 150,000Special Operation Truck n/a PK-16 98,40098,4002016 Park Maintenance Equipment n/a PK-17 177,700177,7002017 Park Maintenance Equipment n/a PK-18 202,500202,5002018 Park Maintenance Equipment n/a PK-19 97,80097,8002019 Park Maintenance Equipment n/a PK-20 153,600153,6002020 Park Maintenance Equipment n/a ST-01 298,000110,000 78,000 110,000Vehicle Replacement - pickup trucks n/a ST-02 735,000245,000 245,000 245,000Dump Truck Replacement n/a ST-03 345,000345,000Heavy Equipment Replacement n/a ST-04 304,65051,550 68,000 11,550 112,000 61,550Other Equipment Replacement n/a 4,642,276435,992 870,200 1,273,592 1,192,342 870,150Equipment Replacement Fund Total Page 12016-2020 CAPITAL IMPROVEMENT PLAN TotalSourceProject#Priority 2016 2017 2018 2019 2020 ERMU BL-14 16,00012,000 4,000Fitness room equipment n/a 16,00012,000 4,000ERMU Total Federal Grants II-32 160,000160,000Eastern Area Trail & Mobility Imp.n/a 160,000160,000Federal Grants Total Government Buildings Reserve AD-06 18,00018,000Administration space redesign n/a BL-03 50,00050,000Multi-purpose community center feasibility study n/a BL-07 237,597237,597Activity Center n/a FS-01 80,00080,000Fire Station #1 n/a PS-03 1,104,00019,000 40,000 520,000 500,000 25,000Public Safety Building maintenance n/a 1,489,597404,597 40,000 520,000 500,000 25,000Government Buildings Reserve Total GRE reserve II-34 320,00080,000 80,000 80,000 80,000Wayfinding signage n/a PR-71 78,34078,340Rivers Edge Commons Expansion-Phase I n/a 398,340158,340 80,000 80,000 80,000GRE reserve Total Ice Arena IA-01 120,000120,000Ice Arena Equipment n/a IA-02 128,500128,500Ice Arena Major Building Repair n/a 248,500248,500Ice Arena Total Library LB-03 24,00019,000 5,000Library Facility n/a 24,00019,000 5,000Library Total Liquor Fund LS-01 100,000100,000Northbound Building Maintenance n/a QZ 850,000850,000Quiet Zones n/a 950,000850,000 100,000Liquor Fund Total Municipal State Aid PM-01 2,000,0001,000,000 1,000,000Pavement Management Program n/a SC-03 1,828,996351,457 358,486 365,656 372,969 380,428Pavement Preventative Maintenance n/a 3,828,996351,457 1,358,486 365,656 1,372,969 380,428Municipal State Aid Total Park Dedication PR-71 259,135259,135Rivers Edge Commons Expansion-Phase I n/a Page 22016-2020 CAPITAL IMPROVEMENT PLAN TotalSourceProject#Priority 2016 2017 2018 2019 2020 259,135259,135Park Dedication Total Park Improvement Fund PIF-16 588,500588,5002016 park improvement projects n/a PIF-17 331,000331,0002017 park improvement projects n/a PIF-18 230,000230,0002018 park improvement projects n/a PIF-19 270,000270,0002019 park improvement projects n/a PIF-20 330,000330,0002020 park improvement projects n/a 1,749,500588,500 331,000 230,000 270,000 330,000Park Improvement Fund Total Pavement Management Fund PM-01 6,980,000100,000 3,330,000 100,000 3,350,000 100,000Pavement Management Program n/a SC-03 471,00498,543 91,514 84,344 102,031 94,572Pavement Preventative Maintenance n/a 7,451,004198,543 3,421,514 184,344 3,452,031 194,572Pavement Management Fund Total Sewer Fund PR-71 13,20013,200Rivers Edge Commons Expansion-Phase I n/a WW-06 47,00012,000 35,000Vehicle Replacement n/a 60,20025,200 35,000Sewer Fund Total State grants WW-17 800,000800,000Plant Expansion Master Plan n/a 800,000800,000State grants Total Storm Sewer PM-01 300,000150,000 150,000Pavement Management Program n/a 300,000150,000 150,000Storm Sewer Total Storm Water STM-1 1,410,000338,000 233,000 313,000 213,000 313,000Storm Water projects n/a 1,410,000338,000 233,000 313,000 213,000 313,000Storm Water Total Storm water utility PR-71 17,13517,135Rivers Edge Commons Expansion-Phase I n/a 17,13517,135Storm water utility Total Street Improvement Reserve II-00 415,00015,000 400,000Line Avenue cul-de-sac n/a II-32 360,000360,000Eastern Area Trail & Mobility Imp.n/a II-33 70,00040,000 30,000Intersection Improvements n/a II-35 180,000100,000 80,000Boulevard Improvements n/a PR-71 60,89060,890Rivers Edge Commons Expansion-Phase I n/a QZ 500,000500,000Quiet Zones n/a Page 32016-2020 CAPITAL IMPROVEMENT PLAN TotalSourceProject#Priority 2016 2017 2018 2019 2020 SL-09 12,00012,000Signal Light Painting n/a 1,597,8901,087,890 480,000 30,000Street Improvement Reserve Total Trunk Utility Fund II-39 250,000250,000Proctor Ave water main n/a II-42 300,000300,000Well #9 Filter Plant n/a 550,000300,000 250,000Trunk Utility Fund Total 30,997,07310,819,789 7,469,200 3,184,592 7,260,342 2,263,150GRAND TOTAL Page 42016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Upgrades to the Council Chambers: 1) Replace carpet and chairs in the Council Chambers Project #AD-05 Priority n/a Justification The Council Chambers is one of the most used space for the public in the city. The carpet is starting to show wear. Glue is showing thru on the carpet on the walls. The City has received franchise fees from the cable commission to be used for technology and Council Chamber upgrades. Useful Life Unassigned Project Name Council Chamber Upgrades Category Building Maintenance Type Maintenance Contact City Clerk Department Administration Total20162017201820192020Expenditures 20,00020,000Construction/Maintenance 5,0005,000Equipment 25,000 25,000Total Total20162017201820192020Funding Sources 25,00025,000Capital Outlay Reserve 25,000 25,000Total Page 52016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Administration department space redesign Project #AD-06 Priority n/a Justification Current furniture parts are running low and it is unlikely that building maintenance will find the needed parts for offices to match what we have currently. The administration department has requested for several years to expand the workspace area. By ordering the same cubicles as the finance department, building maintenance will be able to take the old cubicles and maintain a supply for other department modifications. Useful Life Unassigned Project Name Administration space redesign Category Office Equipment Type Maintenance Contact City Clerk Department Administration Total20162017201820192020Expenditures 18,00018,000Equipment 18,000 18,000Total Total20162017201820192020Funding Sources 18,00018,000Government Buildings Reserve 18,000 18,000Total Page 62016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replacement vehicles for building inspectors/code enforcement/environmental division based on 10 year useful life, mileage and general condition. 2016 - 2004 Ford Explorer 2017 - 2005 Ford Explorer Project #BZ-01 Priority n/a Justification The building safety department is looking at replacing the vehicle with a hybrid/smaller SUV type replacement. Useful Life 10 years Project Name Vehicle Replacement Category Vehicles Type Vehicle Contact Building Offical Department Building & Safety Total20162017201820192020Expenditures 55,00027,500 27,500Vehicles 27,500 27,500 55,000Total Total20162017201820192020Funding Sources 55,00027,500 27,500Equipment Replacement Fund 27,500 27,500 55,000Total Page 72016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2017 Replace John Deere Gator 2019 Replace 2001 F250 pickup truck Project #CH-04 Priority n/a Justification The Gator is used for many building maintenance activities in the winter and summer months. Pickups are regularly used for building maintenance activities all year round. Useful Life Unassigned Project Name Vehicle replacement Category Vehicles Type Vehicle Contact Building Maintenance Supv. Department City Hall Maintenance Total20162017201820192020Expenditures 50,00015,000 35,000Vehicles 15,000 35,000 50,000Total Total20162017201820192020Funding Sources 50,00015,000 35,000Equipment Replacement Fund 15,000 35,000 50,000Total Page 82016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description LED parking lot lights and exterior building light fixtures Project #CH-06 Priority n/a Justification Replace old non-efficient metal halide fixtures that are failing with LED. This will reduce energy costs and maintenance time not having to change bulbs. Useful Life Unassigned Project Name LED parking lot lights Category Maintenance projects Type Equipment Contact Building Maintenance Supv. Department City Hall Maintenance Total20162017201820192020Expenditures 10,00010,000Equipment 10,000 10,000Total Total20162017201820192020Funding Sources 10,00010,000Capital Outlay Reserve 10,000 10,000Total Page 92016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description New elections equipment Project #EL-01 Priority n/a Justification Sherburne County is going out for an RFP to replace the county-wide elections equipment. They are paying a large share of the cost. The current equipment is showing its wear with increasing equipment failures. Newer equipment will provide faster results. Useful Life Unassigned Project Name Election Equipment Category Equipment Type Equipment Contact City Clerk Department Elections Total20162017201820192020Expenditures 45,00045,000Equipment 45,000 45,000Total Total20162017201820192020Funding Sources 45,00045,000Capital Outlay Reserve 45,000 45,000Total Page 102016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replace 2008 Dodge Nitro Project #Eng-1 Priority n/a Justification Annual replacement of engineering equipment based on usage, age, and reliability. Useful Life Unassigned Project Name Vehicle replacement Category Vehicles Type Vehicle Contact Engineer Department Engineering Total20162017201820192020Expenditures 25,00025,000Vehicles 25,000 25,000Total Total20162017201820192020Funding Sources 25,00025,000Equipment Replacement Fund 25,000 25,000Total Page 112016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Annual pond cleaning, stormwater repairs, BMP inventory. Storm Water infrastructure projects combined with street projects are included on the pavement management CIP sheet. Project #STM-1 Priority n/a Justification These annual projects include the testing, removal, and disposal of sediment deposits from our stormwater ponds. This is needed to assure these devices are functioning as designed and achieving the water quality standards of our NPDES permit. The smaller stormwater repairs include minor pipe upsizing, culvert replacement, manhole and catch basin repairs and fixing of washout areas. Useful Life Unassigned Project Name Storm Water projects Category Maintenance projects Type Maintenance Contact Engineer Department Engineering Total20162017201820192020Expenditures 1,410,000338,000 233,000 313,000 213,000 313,000Construction/Maintenance 338,000 233,000 313,000 213,000 313,000 1,410,000Total Total20162017201820192020Funding Sources 1,410,000338,000 233,000 313,000 213,000 313,000Storm Water 338,000 233,000 313,000 213,000 313,000 1,410,000Total Page 122016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replace fire vehicles as follows: 2017 - Duty Officer/command vehicle (2005 Ford Expedition) 2017 - Inspector 2 (2006 Ford Explorer) Project #FD-01 Priority n/a Justification Fire Prevention Truck originally received on a FEMA grant to be used with the FEMA trailer. Replacement truck will be more of a multi-purpose vehicle. Duty Officer vehicle is the primary response vehicle and first on the scene to assess the additional vehicles to follow. This vehicle will be 12 years old in 2017. Useful Life Unassigned Project Name Vehicle Replacement Category Vehicles Type Vehicle Contact Fire Chief Department Fire Total20162017201820192020Expenditures 77,00077,000Vehicles 77,000 77,000Total Total20162017201820192020Funding Sources 77,00077,000Equipment Replacement Fund 77,000 77,000Total Page 132016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Grass Rig replacements as follows: 2018 - Grass Rig 2 (1988 Ford F350) 2020 - Grass Rig 4 (2006 Ford F350) Project #FD-02 Priority n/a Justification The grass rigs are 4X4 1-ton vehicles that are used during emergency response for various responses besides grass fires. The emergency response and safety become a factor during the expected life of the vehicles. Useful Life 15 years Project Name Fire Truck Replacement - Grass Rigs Category Vehicles Type Equipment Contact Fire Chief Department Fire Total20162017201820192020Expenditures 102,00050,000 52,000Vehicles 50,000 52,000 102,000Total Total20162017201820192020Funding Sources 102,00050,000 52,000Equipment Replacement Fund 50,000 52,000 102,000Total Page 142016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Fire Engine replacements as follows: 2018 -1997 Engine 1 Project #FD-03 Priority n/a Justification Primary front-line response unit out of Station #1 Useful Life 20 years Project Name Fire Truck Replacement - Engines Category Vehicles Type Vehicle Contact Fire Chief Department Fire Total20162017201820192020Expenditures 500,000500,000Vehicles 500,000 500,000Total Total20162017201820192020Funding Sources 500,000500,000Equipment Replacement Fund 500,000 500,000Total Page 152016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Other Fire Truck replacement as follows: 2019 - Replace 1999 Ford LT9500 Sterling (Tanker 2) Project #FD-05 Priority n/a Justification With 66 square mile coverage area, much of which is non-hydrated areas this tanker 2 is our largest at 3,000 gallons. Water is critical for tactical mission success and rural fires usually require multiple tenders running water to the fire scene. We have a tender in each station, tanker 2 is currently located at Station 1 on Jackson. Useful Life Unassigned Project Name Fire Truck Replacement - Other Category Vehicles Type Vehicle Contact Fire Chief Department Fire Total20162017201820192020Expenditures 225,000225,000Vehicles 225,000 225,000Total Total20162017201820192020Funding Sources 225,000225,000Equipment Replacement Fund 225,000 225,000Total Page 162016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Mobile Data Computers are for the replacement of older obsolete units that are currently in fire vehicles. Project #FD-07 Priority n/a Justification The computers allow for direct communications with Sherburne County Sheriff's Dispatch. They give the department mapping, hazards or alerts on file, etc. while enroute or on scenes. Without the updates of computers, some software or programs will not function properly. Useful Life Unassigned Project Name Fire Department-Other equipment Category Equipment Type Equipment Contact Fire Chief Department Fire Total20162017201820192020Expenditures 10,00010,000Equipment 10,000 10,000Total Total20162017201820192020Funding Sources 10,00010,000Equipment Replacement Fund 10,000 10,000Total Page 172016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Thermal imager ladder #1 Project #FD-10 Priority n/a Justification To increase capability of crews responding in Ladder 1 after refurbishment in 2015. Safety of firefighters entering IDLH atmosphere with zero visibility. Useful Life Unassigned Project Name Thermal imager ladder #1 Category Equipment Type Equipment Contact Fire Chief Department Fire Total20162017201820192020Expenditures 11,00011,000Equipment 11,000 11,000Total Total20162017201820192020Funding Sources 11,00011,000Capital Outlay Reserve 11,000 11,000Total Page 182016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - Master planning study on fire facilities and replacement of the backup generator. Project #FS-01 Priority n/a Justification Fire Station #1 was constructed in 1972 and based on age and condition requires repair and replacement costs. The purpose of the study is to lay the foundation for fire station facilities, specifically fire station #1 which was built in 1972. The study will provide short and long range planning options to explore facility construction options for existing and possibly future fire station locations. The generator is an old federal surplus that is in need of replacement. It does not have an automatic transfer switch requiring the firefighters or staff to manually convert the station over to generator by hand. Parts are becoming obsolete to make repairs. Useful Life 25 years Project Name Fire Station #1 Category Building Maintenance Type Maintenance Contact Fire Chief Department Fire Stations Total20162017201820192020Expenditures 40,00040,000Planning/Design 40,00040,000Equipment 80,000 80,000Total Total20162017201820192020Funding Sources 80,00080,000Government Buildings Reserve 80,000 80,000Total Page 192016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - 1999 Electric Ice Resurfacer Project #IA-01 Priority n/a Justification The existing electric machine was purchased in 1999 and will have over 5,000 hours of use on it. By establishing an ice resurfacer replacement plan the Arena will operate smoothly without unexpected problems arising. Useful Life 10 years Project Name Ice Arena Equipment Category Equipment Type Equipment Contact Park & Rec. Director Department Ice Arena Total20162017201820192020Expenditures 120,000120,000Equipment 120,000 120,000Total Total20162017201820192020Funding Sources 120,000120,000Ice Arena 120,000 120,000Total Page 202016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 projects include: expanding locker room #5 heating venting system for barn locker rooms Freon detector for the barn ice plant room exhaust system for make-up for charging Zamboni replace infrared heating in barn Community center feasibility study in 2016 will prioritize major capital outlay projects for the future years. CIP will be updated accordingly. Project #IA-02 Priority n/a Justification The Barn's roof was installed in the early 70's and is well past its life expectancy. The arena is starting to experience several leaks on the south end in addition the cooling system refrigerant will be obsolete in a few years. Many of these projects will be prioritized based on 2016 feasibility study. Useful Life 20 years Project Name Ice Arena Major Building Repair Category Building Maintenance Type Building Contact Ice Arena Manager Department Ice Arena Total20162017201820192020Expenditures 128,500128,500Building Maintenance 128,500 128,500Total Total20162017201820192020Funding Sources 128,500128,500Ice Arena 128,500 128,500Total Page 212016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Study and implement improvements to cul-de-sac Line Avenue north of Main St. Project #II-00 Priority n/a Justification This proposed enhancement project is being considered to improve traffic flow and safety of the transportation system in the area. Useful Life 25 years Project Name Line Avenue cul-de-sac Category Street Construction Type Infrastructure Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 400,000400,000Construction/Maintenance 15,00015,000Preliminary Design 15,000 400,000 415,000Total Total20162017201820192020Funding Sources 415,00015,000 400,000Street Improvement Reserve 15,000 400,000 415,000Total Page 222016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Construct the missing pieces of trail along the east side of Twin Lakes Road from the Northstar commuter rail station to Trott Brook Parkway. Also provide ADA compliant sidewalks and pedestrian ramps along Line Avenue from Main Street to 3rd Street. Project #II-32 Priority n/a Justification This trail/sidewalk project will provide safe connectivity of our existing off street trail and sidewalk systems in the area. Useful Life 15 years Project Name Eastern Area Trail & Mobility Imp. Category Trail Improvements Type Infrastructure Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 520,000520,000Construction/Maintenance 520,000 520,000Total Total20162017201820192020Funding Sources 160,000160,000Federal Grants 360,000360,000Street Improvement Reserve 520,000 520,000Total Page 232016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Improve major intersection with landscaping Project #II-33 Priority n/a Justification Beautification of School/169, Jackson/169, Proctor/10, Main/10, and 171st/10 intersections Useful Life 15 years Project Name Intersection Improvements Category Landscaping/Boulevards Type Improvement Contact Planning Manager Department Infrastructure Improvements Total20162017201820192020Expenditures 70,00040,000 30,000Construction/Maintenance 40,000 30,000 70,000Total Total20162017201820192020Funding Sources 70,00040,000 30,000Street Improvement Reserve 40,000 30,000 70,000Total Page 242016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Install gateway identification signage at major city entrances. Locations include east and west side of Highway 10 and south and north sides of Highway 169 at city boundaries (4 major city entrances) Project #II-34 Priority n/a Justification Enhance overall brand of the community, ease navigation, reinforce key destinations, and promote economic development. Define a sense of place and meet Council's goal of Community Development and Beautification in the Visioning Plan. Useful Life 25 years Project Name Wayfinding signage Category Landscaping/Boulevards Type Improvement Contact City Clerk Department Infrastructure Improvements Total20162017201820192020Expenditures 320,00080,000 80,000 80,000 80,000Construction/Maintenance 80,000 80,000 80,000 80,000 320,000Total Total20162017201820192020Funding Sources 320,00080,000 80,000 80,000 80,000GRE reserve 80,000 80,000 80,000 80,000 320,000Total Page 252016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description To achieve beautification goal for boulevard improvements Project #II-35 Priority n/a Justification Several improvements to existing boulevards are planned: Twin Lakes Road (north of 171st) 193rd (west of County Road 13, east of Xavier) Useful Life 15 years Project Name Boulevard Improvements Category Landscaping/Boulevards Type Improvement Contact Planning Manager Department Infrastructure Improvements Total20162017201820192020Expenditures 180,000100,000 80,000Construction/Maintenance 100,000 80,000 180,000Total Total20162017201820192020Funding Sources 180,000100,000 80,000Street Improvement Reserve 100,000 80,000 180,000Total Page 262016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Add new water main connecting Highland Road to Proctor Ave near the public works building. Project #II-39 Priority n/a Justification Increase system capacity to the north. Useful Life 20 years Project Name Proctor Ave water main Category Street & Utility Construction Type Infrastructure Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 250,000250,000Construction/Maintenance 250,000 250,000Total Total20162017201820192020Funding Sources 250,000250,000Trunk Utility Fund 250,000 250,000Total Page 272016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description ERMU well #9 filter project. Project #II-42 Priority n/a Justification This project is the third and final phase of a multi-year water capacity improvement plan to provide added capacity to serve growth in Natures Edge Business Center and the eastern areas of the urban services district. Useful Life 20 years Project Name Well #9 Filter Plant Category Street & Utility Construction Type Infrastructure Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 300,000300,000Construction/Maintenance 300,000 300,000Total Total20162017201820192020Funding Sources 300,000300,000Trunk Utility Fund 300,000 300,000Total Page 282016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replace, overlay or rehabilitate aged and deteriorated streets, storm drainage, and adjacent walks. Projects will be completed every other year. Project #PM-01 Priority n/a Justification Individual street pavement conditions will dictate what pavement management technique will be utilized to extend the life of that specific street segment. These techniques may range from a full reconstruction of the surface and aggregate base to simply overlaying the existing pavement. As they are implemented, the prescribed techniques will continually be gauged to assure their performance is proper in extending the life of our pavements. Useful Life 25 years Project Name Pavement Management Program Category Street & Utility Construction Type Improvement Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 8,980,0004,480,000 4,500,000Construction/Maintenance 300,000100,000 100,000 100,000Preliminary Design 100,000 4,480,000 100,000 4,500,000 100,000 9,280,000Total Total20162017201820192020Funding Sources 2,000,0001,000,000 1,000,000Municipal State Aid 6,980,000100,000 3,330,000 100,000 3,350,000 100,000Pavement Management Fund 300,000150,000 150,000Storm Sewer 100,000 4,480,000 100,000 4,500,000 100,000 9,280,000Total Page 292016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Establish a quiet zone at all street crossings along the BNSF rail line. Project #QZ Priority n/a Justification This project will involve the installation of supplemental safety measures and wayside horns to qualify the entire rail corridor through Elk River as a quiet zone. Useful Life 25 years Project Name Quiet Zones Category Street Construction Type Infrastructure Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 1,350,0001,350,000Construction/Maintenance 1,350,000 1,350,000Total Total20162017201820192020Funding Sources 850,000850,000Liquor Fund 500,000500,000Street Improvement Reserve 1,350,000 1,350,000Total Page 302016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Preventative maintenance on our streets includes sealcoating, crackfilling and small overlay projects. Project #SC-03 Priority n/a Justification It is important to complete annual preventative maintenance on our pavements to extend their service life. This investment is completed on segments between larger comprehensive reconditioning or reconstruction. Useful Life 7 years Project Name Pavement Preventative Maintenance Category Street Maintenance Type Maintenance Contact Street Supt. Department Infrastructure Improvements Total20162017201820192020Expenditures 2,300,000450,000 450,000 450,000 475,000 475,000Construction/Maintenance 450,000 450,000 450,000 475,000 475,000 2,300,000Total Total20162017201820192020Funding Sources 1,828,996351,457 358,486 365,656 372,969 380,428Municipal State Aid 471,00498,543 91,514 84,344 102,031 94,572Pavement Management Fund 450,000 450,000 450,000 475,000 475,000 2,300,000Total Page 312016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Paint signal systems at School/Jackson Avenue and School/Lions Park Drive Project #SL-09 Priority n/a Justification According to MNDOT/City signal agreements it is the responsibility of the City to repaint signal systems as needed to preserve our assets. The last 2 systems will be scheduled for painting in 2016 or as their condition requires. Useful Life 20 years Project Name Signal Light Painting Category Street Maintenance Type Improvement Contact Engineer Department Infrastructure Improvements Total20162017201820192020Expenditures 12,00012,000Construction/Maintenance 12,000 12,000Total Total20162017201820192020Funding Sources 12,00012,000Street Improvement Reserve 12,000 12,000Total Page 322016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Improvements to the Library Building and grounds: 2016 - Permanent curbs in parking lot and LED light replacements in parking lot. 2017 - Parking Ballard's improvement. Project #LB-03 Priority n/a Justification Beautification and maintenance of the library grounds and building. Useful Life Unassigned Project Name Library Facility Category Building Maintenance Type Improvement Contact Park & Rec. Director Department Library Total20162017201820192020Expenditures 24,00019,000 5,000Parking Lot 19,000 5,000 24,000Total Total20162017201820192020Funding Sources 24,00019,000 5,000Library 19,000 5,000 24,000Total Page 332016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Roof replacement at Northbound Liquor Store Project #LS-01 Priority n/a Justification The original roof from 1997 is starting to experience several leaks a year. We continue to perform minor roof patches, but frequency seems to be increasing. Useful Life 20 years Project Name Northbound Building Maintenance Category Building Maintenance Type Maintenance Contact Liquor Store Manager Department Liquor Fund Total20162017201820192020Expenditures 100,000100,000Building Maintenance 100,000 100,000Total Total20162017201820192020Funding Sources 100,000100,000Liquor Fund 100,000 100,000Total Page 342016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Phase I expansion of Rivers Edge Commons Park. Project #PR-71 Priority n/a Justification In 2015, a final concept plan was developed for the ultimate improvements to the Rivers Edge Commons Park. This park is home to the Riverfront concert series and draws thousands of people to the destination. In addition to concerts, weddings and events are held throughout the year. Seating has become limited with the growth of the demand for the park, Phase I will include adding additional seating and replacing a retaining wall on the city owned public parking lot. Useful Life Unassigned Project Name Rivers Edge Commons Expansion-Phase I Category Park Improvements Type Improvement Contact Park & Rec. Director Department Park Development & Improve Total20162017201820192020Expenditures 46,70046,700Planning/Design 382,000382,000Construction/Maintenance 428,700 428,700Total Total20162017201820192020Funding Sources 78,34078,340GRE reserve 259,135259,135Park Dedication 13,20013,200Sewer Fund 17,13517,135Storm water utility 60,89060,890Street Improvement Reserve 428,700 428,700Total Page 352016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 projects include: trail repairs and replacement ($220,000) park property lines ($3,000) Orono Park improvements ($20,000) upgrade irrigation to smart systems ($10,000) athletic field improvements ($100,000) athletic field improvements dugouts ($80,000) Skate park design ($17,500) Hillside improvements ($30,000) Houlton restoration management plan ($10,000) Rivers Edge Commons Park improvements ($20,000) Woodland Trails master plan/forest mgmt. ($23,000) Wayfinding signage ($25,000) Playground hoop replacement ($9,000) Trott Brook Tennis Court resurfacing ($14,000) Project #PIF-16 Priority n/a Justification Annual maintenance/repairs of our park system. Useful Life Unassigned Project Name 2016 park improvement projects Category Park Improvements Type Maintenance Contact Park & Rec. Director Department Park Improvement Fund Total20162017201820192020Expenditures 588,500588,500Park Improvements 588,500 588,500Total Total20162017201820192020Funding Sources 588,500588,500Park Improvement Fund 588,500 588,500Total Page 362016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2017 projects include: trail repairs and replacement ($133,000) Bailey Point kiosk ($20,000) park property lines ($3,000) Hillside Park improvements ($20,000) Houtlon restoration (FRM match) ($10,000) athletic field amenities ($35,000) Lions Park playground replacement ($110,000) Project #PIF-17 Priority n/a Justification Annual maintenance/repairs of our park system. Useful Life Unassigned Project Name 2017 park improvement projects Category Park Improvements Type Maintenance Contact Park & Rec. Director Department Park Improvement Fund Total20162017201820192020Expenditures 331,000331,000Park Improvements 331,000 331,000Total Total20162017201820192020Funding Sources 331,000331,000Park Improvement Fund 331,000 331,000Total Page 372016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2018 projects include: trail repairs and replacement ($110,000) Deerfield improvements ($60,000) Woodland Trails Park ($60,000) Project #PIF-18 Priority n/a Justification Annual maintenance/repairs of our park system. Useful Life Unassigned Project Name 2018 park improvement projects Category Park Improvements Type Maintenance Contact Park & Rec. Director Department Park Improvement Fund Total20162017201820192020Expenditures 230,000230,000Park Improvements 230,000 230,000Total Total20162017201820192020Funding Sources 230,000230,000Park Improvement Fund 230,000 230,000Total Page 382016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2019 projects include: Trail repairs & connections ($270,000) Project #PIF-19 Priority n/a Justification Annual maintenance/repairs of our park system. Useful Life Unassigned Project Name 2019 park improvement projects Category Park Improvements Type Maintenance Contact Park & Rec. Director Department Park Improvement Fund Total20162017201820192020Expenditures 270,000270,000Park Improvements 270,000 270,000Total Total20162017201820192020Funding Sources 270,000270,000Park Improvement Fund 270,000 270,000Total Page 392016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2020 projects include: Trott Brook Park playgound ($150,000) Woodland Trails Park ($180,000) Project #PIF-20 Priority n/a Justification Annual maintenance/repairs of our park system. Useful Life Unassigned Project Name 2020 park improvement projects Category Park Improvements Type Maintenance Contact Park & Rec. Director Department Park Improvement Fund Total20162017201820192020Expenditures 330,000330,000Park Improvements 330,000 330,000Total Total20162017201820192020Funding Sources 330,000330,000Park Improvement Fund 330,000 330,000Total Page 402016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2002 Dodge Ram 2500 $32,500 2005 Chevy $32,500 2010 JD 3720 Tractor $21,800 2002 Skidoo Skandic Snowmobile $11,600 Project #PK-16 Priority n/a Justification Annual replacement of parks equipment based on usage, age, and reliability. Useful Life Unassigned Project Name 2016 Park Maintenance Equipment Category Equipment Type Equipment Contact Park & Rec. Director Department Park Maintenance Total20162017201820192020Expenditures 98,40098,400Vehicles 98,400 98,400Total Total20162017201820192020Funding Sources 98,40098,400Equipment Replacement Fund 98,400 98,400Total Page 412016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 1990 F350 $21,000 2005 Chevy Silverado $30,500 Trail Maint./Grooming equipment $6,000 2011 Toro Groundsmaster 16ft mower $91,600 2006 Mower trailer $10,500 Tractor attachments $14,200 Skid steer attachments $3,900 Project #PK-17 Priority n/a Justification Annual replacement of parks equipment based on usage, age, and reliability. Useful Life Unassigned Project Name 2017 Park Maintenance Equipment Category Equipment Type Equipment Contact Park & Rec. Director Department Park Maintenance Total20162017201820192020Expenditures 177,700177,700Equipment 177,700 177,700Total Total20162017201820192020Funding Sources 177,700177,700Equipment Replacement Fund 177,700 177,700Total Page 422016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replace 2007 GMC 1-ton $55,500 Replace 2008 Kubota RTV 1100 $35,900 Replace 2011 Toro Groundsmater wide area mower $72,100 Tractor attachments $21,500 Skid steer attachments $3,000 Replace trailer $8,500 Replace trail maint./grooming equipment $6,000 Project #PK-18 Priority n/a Justification Annual replacement of parks equipment based on usage, age, and reliability. Useful Life Unassigned Project Name 2018 Park Maintenance Equipment Category Equipment Type Equipment Contact Park & Rec. Director Department Park Maintenance Total20162017201820192020Expenditures 202,500202,500Equipment 202,500 202,500Total Total20162017201820192020Funding Sources 202,500202,500Equipment Replacement Fund 202,500 202,500Total Page 432016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replace tractor attachments $11,000 2003 ATV replacement $6,000 Replace 2008 Ford F250 Replace 2011 Ford F550 Project #PK-19 Priority n/a Justification Annual replacement of parks equipment based on usage, age, and reliability. Useful Life Unassigned Project Name 2019 Park Maintenance Equipment Category Equipment Type Equipment Contact Park & Rec. Director Department Park Maintenance Total20162017201820192020Expenditures 97,80097,800Equipment 97,800 97,800Total Total20162017201820192020Funding Sources 97,80097,800Equipment Replacement Fund 97,800 97,800Total Page 442016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2009 Chevy Silverado 3/4 t - $61,400 Tractor attachments - $15,000 2010 John Deere Tractor replacement - $70,000 Skid steer attachments - $7,200 Project #PK-20 Priority n/a Justification Annual replacement of parks equipment based on usage, age, and reliability. Useful Life Unassigned Project Name 2020 Park Maintenance Equipment Category Equipment Type Equipment Contact Park & Rec. Director Department Park Maintenance Total20162017201820192020Expenditures 153,600153,600Equipment 153,600 153,600Total Total20162017201820192020Funding Sources 153,600153,600Equipment Replacement Fund 153,600 153,600Total Page 452016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Routine replacement of vehicles at or near 100,000 miles. Includes all equipment and setup. 2016 - 2 replacement 2017 - 3 replacement 2018 - 2 replacement 2019 - 3 replacement 2020 - 3 replacement Project #PD-01 Priority n/a Justification Annual replacement (3-4 years) of vehicles with over 100,000 miles or high miles and excessive maint. cost. Useful Life 4 years Project Name Marked Squad Replacement & Additions Category Vehicles Type Vehicle Contact Police Chief Department Police Total20162017201820192020Expenditures 473,00076,000 117,000 70,000 105,000 105,000Vehicles 76,000 117,000 70,000 105,000 105,000 473,000Total Total20162017201820192020Funding Sources 473,00076,000 117,000 70,000 105,000 105,000Equipment Replacement Fund 76,000 117,000 70,000 105,000 105,000 473,000Total Page 462016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - 2 replacement 2017 - None 2018 - 1 replacement 2019 - 2 replacement 2020 - 3 replacement Project #PD-02 Priority n/a Justification Annual replacement of high mileage unmarked vehicles. (100,000 plus or over 7-years old) Useful Life 7 years Project Name Unmarked Squad Replacement & Additions Category Vehicles Type Vehicle Contact Police Chief Department Police Total20162017201820192020Expenditures 224,00054,000 27,000 62,000 81,000Vehicles 54,000 27,000 62,000 81,000 224,000Total Total20162017201820192020Funding Sources 224,00054,000 27,000 62,000 81,000Equipment Replacement Fund 54,000 27,000 62,000 81,000 224,000Total Page 472016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description CSO vehicle replacement and additions as follows: 2016 - 1 replacement 2019 - 1 replacement 2020 - 1 replacement Project #PD-03 Priority n/a Justification Annual replacement of vehicles with over 100,000 miles or over 6-years old. Useful Life 6 years Project Name CSO Vehicle Replacement & Additions Category Vehicles Type Vehicle Contact Police Chief Department Police Total20162017201820192020Expenditures 102,00034,000 34,000 34,000Vehicles 34,000 34,000 34,000 102,000Total Total20162017201820192020Funding Sources 102,00034,000 34,000 34,000Equipment Replacement Fund 34,000 34,000 34,000 102,000Total Page 482016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - 3 Mobile Computer replacement and radar/camera replacement (3 units) 2017 - 2 Mobile Computer replacement and radar/camera replacement (2 units) 2018 - 2 Mobile Computer replacement and radar/camera replacement (2 units) 2019 - 3 Mobile Computer replacement and radar/cmaera replacment (2 units) 2020 - 3 Mobile Computer replacement Project #PD-04 Priority n/a Justification Annual replacement of computers that are over 5-7 years old. Squad video camera and radars replacement is based on useful life of the equipment in a replacement rotation. Useful Life Unassigned Project Name Police Department - Other Equipment Category Equipment Type Equipment Contact Police Chief Department Police Total20162017201820192020Expenditures 196,62644,542 43,000 32,542 48,542 28,000Equipment 44,542 43,000 32,542 48,542 28,000 196,626Total Total20162017201820192020Funding Sources 196,62644,542 43,000 32,542 48,542 28,000Equipment Replacement Fund 44,542 43,000 32,542 48,542 28,000 196,626Total Page 492016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 SWAT van to compliment the 1993 International truck transferred from the Fire Department in 2011. The department will evaluate the replacement of the 1993 international truck in 2019. Project #PD-07 Priority n/a Justification The Special Operations van will be a multi-purpose vehicle used in the following circumstances: SWAT team and Crisis Negotiators for personnel and equipment transport during critical incidents. Mobile Command Post (police station on wheels) during Critical Incidents (see above), major incidents (storms, large fire scenes, major crashes etc.), and major community events (4th of July, etc). Major Crime Scene response- It is equipped with investigative supplies and equipment enabling detectives to operate more effectively at scenes they will be at for an extended period of time. Useful Life 20 years Project Name Special Operation Truck Category Equipment Type Equipment Contact Police Chief Department Police Total20162017201820192020Expenditures 190,00040,000 150,000Vehicles 40,000 150,000 190,000Total Total20162017201820192020Funding Sources 190,00040,000 150,000Equipment Replacement Fund 40,000 150,000 190,000Total Page 502016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Panasonic arbitrator interview room system Project #PD-08 Priority n/a Justification Install new cameras and software system for the four interview rooms. The current system is experiencing some issues and the new panasonic system will match the ones used in the squad cars. Useful Life Unassigned Project Name Arbitrator Interview Room System Category Technology/Communiciations Type Equipment Contact Police Chief Department Police Total20162017201820192020Expenditures 34,50034,500Software/Hardware 34,500 34,500Total Total20162017201820192020Funding Sources 34,50034,500Capital Outlay Reserve 34,500 34,500Total Page 512016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Multi-purpose community center feasibility study Project #BL-03 Priority n/a Justification Several facilities including Ice Arena, Activity Center, Lion's park are in need of some significant renovations/repairs in the near future. The study will determine the appropriate future use of those facilties and the possiblity of creating one multi-purpose building. Useful Life Unassigned Project Name Multi-purpose community center feasibility study Category Buildings Type Study Contact Park & Rec. Director Department Public Buildings Total20162017201820192020Expenditures 50,00050,000Planning/Design 50,000 50,000Total Total20162017201820192020Funding Sources 50,00050,000Government Buildings Reserve 50,000 50,000Total Page 522016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 projects include roof replacement, ventilation system, carpet, boilers, AC unit replacement, doors, lighting/ceiling tiles, EMS controls and replacing the exterior lighting with LED. Project #BL-07 Priority n/a Justification The activity center was built in 1975 and functioned as a library prior to it becoming the activity center. Projects will be prioritized pending facility plan review. Useful Life Unassigned Project Name Activity Center Category Buildings Type Maintenance Contact Park & Rec. Director Department Public Buildings Total20162017201820192020Expenditures 237,597237,597Building Maintenance 237,597 237,597Total Total20162017201820192020Funding Sources 237,597237,597Government Buildings Reserve 237,597 237,597Total Page 532016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Fitness room equipment replacement Project #BL-14 Priority n/a Justification The equipment is becoming outdated and in some cases obsolete and in need of replacement. A wellness room committee which was chaired by Patrol Captain Darren McKernan has provided recommendations on various replacements with the goal of increased room usage and ease of use that provides a full range of workouts. Useful Life Unassigned Project Name Fitness room equipment Category Equipment Type Equipment Contact Police Captain Department Public Buildings Total20162017201820192020Expenditures 32,00024,000 8,000Equipment 24,000 8,000 32,000Total Total20162017201820192020Funding Sources 16,00012,000 4,000Capital Outlay Reserve 16,00012,000 4,000ERMU 24,000 8,000 32,000Total Page 542016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - Turnout gear washer (fire side, carried over from 2015), front office cubicle redesign (police) 2017 - Carpet replacement in the remaining Police and Fire department 2017 - Additional garage space (2018), with engineering starting in (2017) 2018 - 2nd floor buildout of the public safety building (2019), with engineering starting in (2018) 2019 - floor tile replacement Project #PS-03 Priority n/a Justification The Public Safety building was built in 2002 and the traffic volume from staff and visitors has started to wear on the carpet and tiles. Due to additional traffic and space needs the Police department is in need of additional garage space and to help with flow of traffic. The 2nd floor of the Police department is not built out and the department is starting to plan for the eventual buildout of the 2nd floor. Useful Life Unassigned Project Name Public Safety Building maintenance Category Building Maintenance Type Maintenance Contact Building Maintenance Supv. Department Public Safety Building Total20162017201820192020Expenditures 40,00020,000 20,000Planning/Design 19,00019,000Equipment 45,00020,000 25,000Building Maintenance 1,000,000500,000 500,000Design/Construction 19,000 40,000 520,000 500,000 25,000 1,104,000Total Total20162017201820192020Funding Sources 1,104,00019,000 40,000 520,000 500,000 25,000Government Buildings Reserve 19,000 40,000 520,000 500,000 25,000 1,104,000Total Page 552016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - replace 1998 Chevy 1/2 ton with 2010 Ford Explorer from Police dept. 2018 - replace 2001 Ford. Project #WW-06 Priority n/a Justification Annual replacement of vehicles after approximately 10 years and is adjusted based on maintenance costs and condition of vehicles. Useful Life 10 years Project Name Vehicle Replacement Category Vehicles Type Vehicle Contact Chief Wastewater Operator Department Sewer Department Total20162017201820192020Expenditures 47,00012,000 35,000Vehicles 12,000 35,000 47,000Total Total20162017201820192020Funding Sources 47,00012,000 35,000Sewer Fund 12,000 35,000 47,000Total Page 562016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Modification to the existing WWTF. These modifications will increase the treatment capacity and meet the limits of our MPCA discharge permit. The improvements are currently being designed according to growth projections, permit requirements and findings of the approved Facility Plan. Project started in 2014. Project #WW-17 Priority n/a Justification In addition to the increased flow projections expected as the City grows, treatment limits of our reissued MPCA permit continue to require additional equipment and treatment processes to meet the MPCA requirements. Useful Life Unassigned Project Name Plant Expansion Master Plan Category Plant Expansion Type Improvement Contact Engineer Department Sewer Department Total20162017201820192020Expenditures 5,000,0005,000,000Construction/Maintenance 5,000,000 5,000,000Total Total20162017201820192020Funding Sources 4,200,0004,200,000Bond Proceeds 800,000800,000State grants 5,000,000 5,000,000Total Page 572016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Street department pickup truck replacements. 2018 - replace 2008 Ford F250 and 2007 Ford F550 dump box truck 2019 - replace 2008 Ford F550 dump box truck 2020 - replace 2010 Ford F250 and 2010 Ford F550 flatbed Project #ST-01 Priority n/a Justification Annual replacement of streets equipment based on usage, age, and reliability. Useful Life 10 years Project Name Vehicle Replacement - pickup trucks Category Vehicles Type Vehicle Contact Street Supt. Department Streets Total20162017201820192020Expenditures 298,000110,000 78,000 110,000Vehicles 110,000 78,000 110,000 298,000Total Total20162017201820192020Funding Sources 298,000110,000 78,000 110,000Equipment Replacement Fund 110,000 78,000 110,000 298,000Total Page 582016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Dump truck replacement and additions. Includes all plow equipment. 2018 - 1 Tandem Axle with plow, replaces 2003 Tandem Axle plow truck 2019 - 1 Tandem Axle with plow, replaces 2004 Tandem Axle plow truck 2020 - 1 Tandem Axle with plow, replaces 2005 Tandem Axle plow truck Project #ST-02 Priority n/a Justification Annual replacement of streets equipment based on usage, age, and reliability. Useful Life 15 years Project Name Dump Truck Replacement Category Heavy Equipment Type Equipment Contact Street Supt. Department Streets Total20162017201820192020Expenditures 735,000245,000 245,000 245,000Equipment 245,000 245,000 245,000 735,000Total Total20162017201820192020Funding Sources 735,000245,000 245,000 245,000Equipment Replacement Fund 245,000 245,000 245,000 735,000Total Page 592016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Heavy Equipment replacements & additions as follows: 2017 - sweeper (replaces 2005, unit #316), front-end loader (replaces 2003, unit #313) Project #ST-03 Priority n/a Justification Annual replacement of streets equipment based on usage, age, and reliability. Useful Life 15 years Project Name Heavy Equipment Replacement Category Vehicles Type Equipment Contact Street Supt. Department Streets Total20162017201820192020Expenditures 345,000345,000Equipment 345,000 345,000Total Total20162017201820192020Funding Sources 345,000345,000Equipment Replacement Fund 345,000 345,000Total Page 602016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Replace other Street Department equipment as follows: 2016 - Roller for grader $25,000, pavement cutter $11,550, Wacker roller, $15,000 2017 - Vac trailer 2018 - Graco easy liner, replaces 2004 2019 - Replace 2009 Bobcat S300, $56,000, Replace 2009 Cimiline 230D meter, $56,000 2020 - Replace 2000 brush chipper, $50,000, Replace 2008 pavement cutter, $11,550 Project #ST-04 Priority n/a Justification Annual replacement of streets equipment based on usage, age, and reliability. Useful Life Unassigned Project Name Other Equipment Replacement Category Equipment Type Equipment Contact Street Supt. Department Streets Total20162017201820192020Expenditures 304,65051,550 68,000 11,550 112,000 61,550Equipment 51,550 68,000 11,550 112,000 61,550 304,650Total Total20162017201820192020Funding Sources 304,65051,550 68,000 11,550 112,000 61,550Equipment Replacement Fund 51,550 68,000 11,550 112,000 61,550 304,650Total Page 612016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Truck mounted message board Project #ST-17 Priority n/a Justification To help control traffic during mobile workzone construction and maintenance. Useful Life Unassigned Project Name Truck mounted message board Category Equipment Type Equipment Contact Street Supt. Department Streets Total20162017201820192020Expenditures 12,00012,000Equipment 12,000 12,000Total Total20162017201820192020Funding Sources 12,00012,000Capital Outlay Reserve 12,000 12,000Total Page 622016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description 2016 - Enterprise backup system, fiber network enhancements, security camera replacements, arbitrator storage upgrade, mobile management system and Microsoft refresh 2017 - Enterprise backup system, virtualization upgrade/blade, financial software upgrade/replacement and fiber network enhancements 2018 - Laserfiche upgrade, hardware/enterprise switch/UPS, fiber network enhancements and virtual desktop 2019 - Security camera replacement and fiber network enhancements 2020 - Enterprise backup system, fiber network enhancements, laptops/computers council and Microsoft refresh Project #TC-01 Priority n/a Justification Annual replacement and upgrade of information technology software/hardware. Useful Life Unassigned Project Name Annual Technology Upgrades Category Technology/Communiciations Type Equipment Contact IT Coordinator Department Technology/Communications Total20162017201820192020Expenditures 616,000166,000 125,000 145,000 30,000 150,000Equipment 166,000 125,000 145,000 30,000 150,000 616,000Total Total20162017201820192020Funding Sources 616,000166,000 125,000 145,000 30,000 150,000Capital Outlay Reserve 166,000 125,000 145,000 30,000 150,000 616,000Total Page 632016-2020 CAPITAL IMPROVEMENT PLAN Capital Improvement Plan City of Elk River, Minnesota 2016 2020thru Description Human Resource Information System (HRIS) Software Carried forward from 2015. Project #TC-04 Priority n/a Justification With over 125 full-time employees software automation will streamline many processes. This software will be used for on-line applications, applicant tracking, onboarding, performance evaluations, training tracking, performance management, and more. This will help to automate many aspects of Human Resources and make information accessible to staff and supervisors. In addition, this will include the payroll processing to provide a seamless interface and eliminate many data redundancies and errors. For 2017, if approved we will eliminate payroll processing software with our financial system and a secondary timekeeping system for non police staff and adjust staffing accordingly. We anticipate about a 6 month transition including running duplicate payrolls to ensure data is correct and has transferred. Useful Life Unassigned Project Name Human Resource Information System (HRIS) Software Category Software Type Technology Contact Human Resource Rep Department Technology/Communications Total20162017201820192020Expenditures 75,00075,000Software/Hardware 75,000 75,000Total Total20162017201820192020Funding Sources 75,00075,000Capital Outlay Reserve 75,000 75,000Total Page 642016-2020 CAPITAL IMPROVEMENT PLAN No . U n i t # O l d D e s c r i p t i o n R p l . C y c l e A g e Di s p o s i t i o n De p a r t m e n t P r i m a r y D i v i s i o n N e w V e h i c l e D e s c r i p t i o n Est. Cost 2016 1 N / A N / A N/ A N / A N / A F i r e A d m i n i s t r a t i o n M o b i l e C o m p u t e r s 1 0 , 0 0 0 2 6 0 4 2 0 1 2 C h e v y T a h o e 3 - 4 4 A u c t i o n P o l i c e P a t r o l 2 0 1 6 4 x 4 C h e v y T a h o e 3 8 , 0 0 0 3 6 1 3 2 0 1 2 C h e v y T a h o e 3 - 4 4 A u c t i o n P o l i c e P a t r o l 2 0 1 6 4 x 4 C h e v y T a h o e 3 8 , 0 0 0 4 N / A 2 0 0 4 R a d a r a n d C a m e r a r e p l . 8 1 2 A u c t i o n P o l i c e P a t r ol R a d a r a n d C a m e r a r e p l a c e m e n t ( 2 u n i t s ) 2 0 , 5 4 2 5 6 0 3 2 0 1 0 C h e v y I m p a l a 7 6 A u c t i o n P o l i c e I n v e s t i g a t i o n s 20 1 5 F o r d I n t e r c e p t o r S e d a n 2 7 , 0 0 0 6 6 0 5 2 0 0 8 C h e v y I m p a l a ( t o S t r e e t s P o o l ) 7 8 T r a n s f e r P o li c e I n v e s t i g a t i o n s 2 0 1 5 F o r d I n t e r c e p t o r S e d a n 2 7 , 0 0 0 7 6 1 4 2 0 1 0 F o r d E x ( r e p l / 9 8 C h e v i n W W ) 8 6 T r a n s f e r P o l ic e C S O 2 0 1 6 F o r d E x p l o r e r 3 4 , 0 0 0 8 N / A M o b i l e S q u a d C o m p u t e r s ( 3 ) 4 4 A u c t i o n P o l i c e P a t r o l Mo b i l e S q u a d C o m p u t e r s ( 3 ) 2 4 , 0 0 0 9 N / A N / A N/ A N / A N / A P o l i c e A d m i n i s t r a t i o n S W A T V a n 40,000 10 N / A N / A N/ A N / A N / A P u b l i c W o r k s S t r e e t s R o u t e r f o r c r a c k f i l l i n g 2 5 , 0 0 0 11 N / A N / A N/ A N / A N / A P u b l i c W o r k s S t r e e t s P u l l b e h i n d r o l l e r f o r gr a d i n g 2 6 , 5 5 0 12 5 0 6 2 0 0 4 F o r d E x p l o r e r 1 0 1 2 A u c t i o n F A B S B u i l d i n g S a f e ty S i m i l a r S U V 27,500 13 7 4 7 2 0 0 2 D o d g e 2 5 0 0 1 0 1 3 A u c t i o n Pa r k s a n d R e c r e a t i o n P a r k M a i n t e n a n c e 2 0 1 6 C h e v y o r D od g e 2 5 0 0 3 2 , 5 0 0 14 7 4 9 2 0 0 5 C h e v y 2 5 0 0 H D 1 0 1 0 A u c t i o n Pa r k s a n d R e c r e a t i o n P a r k M a i n t e n a n c e 2 0 1 6 C h e v y o r D od g e 2 5 0 0 3 2 , 5 0 0 15 7 3 4 2 0 1 0 J D 3 7 2 0 T r a c t o r 1 0 - 1 2 6 T r a d e I n P a r k s a n d R e cr e a t i o n P a r k M a i n t e n a n c e 2 0 1 6 J D 4 7 2 0 T r a c t o r * * 2 1 , 8 0 0 16 7 1 2 2 0 0 2 S k i d o o S k a n d i c S n o w m o b i l e 3 - 5 1 3 A u c t i o n P a r k s a n d R e c r e a t i o n P a r k M a i n t e n a n c e 2 0 1 5 S k i d o o S k a n d i c S n o w m o b i l e 1 1 , 6 0 0 Total $435,992 No t e s : Rp l C y c l e = p e r o u r a d o p t e d p o l i c y o n u s e f u l l i v e s . ** = F l e e t c o m m i t t e e r e c o m m e n d s t h i s t r a d e - i n / p u r c h as e b e t i e d t o s e r v i c e l e v e l e x p e c t a t i o n s o f C C a n d t h e P a r k s M a s t e r P l a n . 20 1 6 E q u i p m e n t P u r c h a s e s