MEMORANDUM
TO: Economic Development Authority
FROM: Heidi Steinmetz, Assistant Director of Economic Development
DATE: August 8, 2005
SUBJECT: Northstar Business Park Development Update
Improvement Project and Plat Status Report/Schedule
Below is a status report/schedule that allows for fall/winter new business construction:
• Council approves plans/specs for first phase utilities and July 18 (Completed)
11, authorizes advertisement for bids
• Planning Commission reviews preliminary plat July 26 (Completed)
• Council reviews and approves preliminary and final plat August 1 (Completed)
• Bid open Until August 30
• Council approves bid and awards contract September 6
• Improvement project begins Mid-September
• Council determines cost to be assessed and sets September/October .
assessment hearing
• Council holds assessment hearing/adopts assessment roll October
• Three lots proposed for Affiance Machine, October
Crystal Distribution, Inc. and Medical Extrusion
Technologies available for site construction
Public Infrastructure Grant
On June 22, 2005, staff submitted a grant proposal in the amount of$495,000 to the
Minnesota Department of Employment and Economic Development (DEED) based on the
entire improvement project. Public Infrastructure grant funds are available from DEED for
up to 50% of the capital cost of the infrastructure. The City Council adopted a resolution
authorizing the grant application and certifying the availability of its 50%match (to be
provided by bonds and special assessment to the EDA). Staff has not received a response
from DEED regarding the grant application.
•