MEMORANDUM
TO: Economic Development Authority
FROM: Heidi Steinmetz, Assistant Director of Economic Development
DATE: November 14, 2005
SUBJECT: Northstar Business Park Update
Purpose
The purpose of this memorandum is to provide the EDA with updates on the following
items:
• Northstar Business Park infrastructure improvement project
• • Affiance Machine, Crystal Distibution, Inc. (CDT), and Medical Extrusion
Technologies (MET) projects
Improvement Project
The underground public infrastructure has been completed, the concrete curb and gutter has
been poured and the base pavement on the streets is in place. Installation of the small
utilities (gas,phone, electric) will begin on November 14th.
Assessment Schedule
The assessment roll was approved by the City Council in early October. The Finance
Department has completed the schedule,which will be certified in December.
Monument Sign
Based on input provided by the EDA in September,Planner Chris Leeseberg will revise the
design for the Northstar Business Park monument sign and obtain construction quotes. To
avoid winter construction costs, the sign will be built next spring.
Grant Agreement
The City will soon enter into a$495,000 grant agreement with the Minnesota Department of
Employment and Economic Development (DEED) for a portion of the infrastructure costs
for Northstar Business Park. This past summer, the City Council adopted a resolution
authorizing the grant application and certifying the availability of a 50% match,which will be
provided by bonds and special assessment to the EDA.
•
Northstar Business Park Update
November 14,2005 EDA Meeting
Page 2 of 2
• Alliance Machine, CDI, and MET
Alliance Machine
Alliance Machine's Vice President Bryan Provo provided staff with the following project
update: the walls will be completed by Nov. 315x, the roof will be added the first week of
December and the building will be fully enclosed shortly thereafter.
CDI
The Mutual Driveway Encroachment Agreement between the EDA and CDI was revised
per the EDA's October 17th recommendation and will be executed shortly.
It is anticipated that CDI's ground breaking will be held by the end of this month. Staff will
contact the EDA by phone and e-mail. CDI's President/Owner Pat O'Brien provided staff
with the following project update: CDI's parking lot and curbs are completed, on Dec. 5th'
the structural steel will arrive on site, on Dec. 12th the panels will arrive, and on Jan. 1', the
building will be completely weather tight (installation of roof, doors and windows
completed).
MET
MET's project manager provided staff with the following project update: the sanitary sewer
and water service are connected, the storm sewer will be completed in 2-3 days, the footing
work has begun, the site grading continues, the panels will arrive onsite on Dec. 6th, and the
steel will arrive shortly thereafter.