4.5. SR 04-04-2016 EOty1� ,.,�� Request for Action
River
To Item Number
Mayor and City Council 4.5
Agenda Section Meeting Date Prepared by
Consent Aril 4, 2016 Justin Femrite, P.E., City Engineer
Item Description Reviewed by
Approve Additional Professional Service Fee Cal Portner, City Administrator
Requests Reviewed by
Action Requested
Approve,by motion,increase of$23,910 in professional services for extra work associated with the 2015
Street Improvement and Eastern Area Trail and Mobility projects.
Background/Discussion
Attached are two requests for additional fees associated with providing additional engineering services on
the 2015 Street Improvement and the Eastern Area Trail and Mobility Improvement projects. The
requests area summarized as follows:
■ 2015 Street Improvements —$20,233
■ Easter Area Trail and Mobility Improvements - $3,677
Staff has sat down to review these requests with the consultant. We agree the requests are fair for the
additional services provided on the projects.
Financial Impact
If approved the above amounts will be added to the current approved fees and become part of the final
project costs. The project funding sources are sufficient to cover these increases.
Attachments
■ 2015 Street Improvements Additional Fee Request
■ Eastern Area Trail and Mobility Improvements Additional Fee Request
POWERED 6T
A IR
F==tOI_TON & NA E= N K , INC®
Consulting Engineers & Su
7533 Sunwood Drive NW• Ramsey, MN 55303
Phone(763)433-2851 • Fax (763)427-0833
www.bolton-menk.com
MEMORANDUM
Date: March 3, 2016
To: Justin Femrite, P.E., City Engineer
From: Cody Holmes, P.E., Project Manager
Mark D. Kasma, P.E., Senior Principal Engineer
Subject: 2015 Street Improvements Additional Fee Request
City of Elk River
BMI Project No. N15.108340
With this memo we are requesting additional fees in the amount of$20,233.00 for the additional work
completed and required for the 2015 Street Improvements project. Information below summarizes the
additional work to complete the construction of the 2015 Street Improvements project.
Construction Administration—$13,230
• Additional time was spent coordinating construction throughout the project, including time on
change orders 1 and 2.
• Cody Holmes- 122.5 hours at$108
Construction Observation -$7,003
• Additional time was spent completing observation on the project,including time on change orders
1 and 2.
• Additional observer time was needed during construction, city staff was not available to backfill,
so further time was spent onsite.
• Eathan Doyle-74.5 hours at$94
Thank you for your consideration,please let me know if you have any questions.
DESIGNING FOR A BETTER TOMORROW
Bolton&Menk is an equal opportunity employer
F==tOI_TON & NA E= N K , I NC®
Consulting Engineers & Su
7533 Sunwood Drive NW• Ramsey, MN 55303
Phone(763)433-2851 • Fax (763)427-0833
www.bolton-menk.com
MEMORANDUM
Date: March 3, 2016
To: Justin Femrite, P.E., City Engineer
From: Cody Holmes, P.E., Project Manager
Mark D. Kasma, P.E., Senior Principal Engineer
Subject: Eastern Area Trail/Mobility Improvements Additional Fee Request
City of Elk River
BMI Project No. N15.108488
With this memo we are requesting additional fees in the amount of$3,677.00 for the additional work
completed and required for the Eastern Area Trail and Mobility Improvements project. Information
below summarizes the additional work to complete the rebid and construction of the Eastern Area Trail
and Mobility Improvements.
Rebid Project&Prepare Contracts - $3,677
• Coordinate with MnDOT,revise plans and specifications for rebid of project, and prepare
contracts.
• Cody Holmes-25 hours at$108, Eathan Doyle-7.5 hours at$94,Jodi Ogren-4 hours at$68
Please call me to discuss if you have any questions.