3.3. SR 11-15-2004 TO: Mayor and City Council Item # *3.3.* MEMORANDUM FROM: Lori Johnson, Finance Director DATE: November I, 2004 SUBJECT: Consider Change Orders The following change order has been requested on the public safety and city hall building projects. Contractor PUBLIC SAFETY Greenscape Landscaping (Raising the backflow) Bartley Sales (106" address letters) Carciofini Caulking Company (additional caulking) Western Steel Erection (addl work on stairs, handrail, entry, and other) Total Previously Approved Total Change Orders to Date CITY HALL Roof Tech (Flue pipe relocation) Western Steel Erection (Move temporary heat) Albers Mechanical (reroute floor drains, expansion tank, and other) Total Bid Package Change Order Change Order Number Number Amount 2 1 $ 542.19 28 2 1,910.00 18 1 557.00 12 4 2,046.00 5,055.19 319,817.63 $324,872.82 13 $ 478.42 5 8 5 234.00 34 5,979.50 6 6,691.92 Previously Approved Total Change Orders to Date Action Requested The City Council is asked to approve the change orders as noted above. 193,796.59 $200,488.51