lk — - Request for Action
River
To Item Number
Mayor and City Council 8.2
Agenda Section Meeting Date Prepared by
General Business October 3, 2016 Steve Benoit,Recreation Manager
Item Description Reviewed by
Orono Park Skate Park Project Michael Hecker, Parks and Recreation Director
Reviewed by
Cal Portner, City Administrator
Action Requested
Adopt,by motion,the Orono Park Skate Park design.
Background/Discussion
Spohn Ranch Skateparks, the firm retained to design the Orono Park Skate Park, has completed the latest
draft of the proposed park. The plan was developed from community feedback received at two
workshop meetings and a Facebook Page designed specifically for the skate park project. Overall the
design has been well received by potential users of the park. The park utilizes a concrete design with
features highly desired by skaters that focused on what is considered to be good flow. Also, the park
utilizes a design intended to compliment surrounding features of Orono Park.
Council adoption of the design is required before the construction documents can be produced.
The skate park project has been approved to be included with park improvements to be funded as part of
the $30 million Community Center referendum this November.
Financial Impact
Construction cost: $370,187
Attachments
■ Design Schematic A
■ Design Schematic B
■ Design Schematic C
■ Design Schematic D
■ Construction Budget
POWERED 9r
UREI
i `ter � � •
.000I Alf
Y" 1
• 1 _
♦�-M . ��� � "Ire• ♦ a
4 1
4.
me
_
b
r r,L•. r i,"''7!`•;'fir
_
SKATEPARK DESIGN BY
ORONO PARK ■�
SKATE■ COPYRIGHT 2016
y, •. OF
r
ORONO PARK SKATEPARKDESIGN BY
SKATEPARK SPOHN RANCH
COPYRIGHT 2016
CITY OF ELK RIVER,MN
_ T-
AIL
ORONO PARK SKATEPARKDESIGN BY
SPOHN RANCH
SKATEPARK COPYRIGHT 2016 -
CITY OF ELK RIVER,MN
ORONO PARK SKATEPARKDESIGN BY
SPOHN RANCH
SKATEPARK
CITY OF ELK RIVER,MN
rie am DESIGN. BUILD. COME TOGETHER.
SPOHN RANCH
S K A T E P A R K S
CONSTRUCTION COST ESTIMATE
ORONO PARK SKATEPARK- ELK RIVER, MINNESOTA
JULY 21, 2016
MOBILIZATION /GENERAL REQUIREMENTS
ITEM QUANTITY
CREW MOBILIZATION 1 (LUMP SUM)
EQUIPMENT&GEAR MOBILIZATION 1 (LUMP SUM)
FUEL&MISCELLANEOUS SUPPLIES 40 WORKING DAYS
TEMP FENCING 600 LINEAR FEET
TEMP DUMPSTER 2 MONTHS
TEMP RESTROOM 2 MONTHS
SITE STAKING&LAYOUT 1 (LUMP SUM)
PUNCH LIST, CLEAN-UP&DE-MOBILIZATION 2 WORKING DAYS
ESTIMATED COST $25,000.00
STEEL FABRICATION
ITEM QUANTITY
CNC-CUT SCREEDS 1 (LUMP SUM)
HOT-DIP GALVANIZED STEEL COPING 228 LINEAR FEET
HOT-DIP GALVANIZED STEEL ANGLE 193 LINEAR FEET
HOT-DIP GALVANIZED STEEL GRIND RAILS 3 RAILS
SHIPPING 1 (LUMP SUM)
FIELD WELDING 1 (LUMP SUM)
ESTIMATED COST $28,020.00
SPOHN RANCH, INC. I P 626-330-5803 F 626-330-5503 1 W SPOHNRANCH.COM
E INFO@SPOHNRANCH.COM 1 6824 S CENTINELA AVE. LOS ANGELES, CA 90230
rie am DESIGN. BUILD. COME TOGETHER.
SPOHN RANCH
S K A T E P A R K S
SITE PREPARATION & EARTHWORK
ITEM QUANTITY
MEDIUM-SIZE TREE REMOVAL 2 TREES
LARGE-SIZE TREE REMOVAL 1 TREE
STRIP GRASS&TOPSOIL 8,763 SQUARE FEET
HAULING&DISPOSAL 1 (LUMP SUM)
SCARIFY SUB-GRADE 8,763 SQUARE FEET
MOISTURE CONDITION SUB-GRADE 8,763 SQUARE FEET
COMPACT SUB-GRADE 8,763 SQUARE FEET
IMPORT&PLACE BASE COURSE 112 CUBIC YARDS
CUTTING/SHAPING FOR>2.5 SKATE FEATURES 1,643 SQUARE FEET
CUTTING/SHAPING FOR<2.5'SKATE FEATURES 839 SQUARE FEET
ESTIMATED COST $51,942.00
DRAINAGE
ITEM QUANTITY
4"PVC LINE 250 LINEAR FEET
TRENCH EXCAVATION 250 LINEAR FEET
TRENCH BEDDING 250 LINEAR FEET
TRENCH BACKFILL 250 LINEAR FEET
TRENCH COMPACTION 250 LINEAR FEET
ZURN 415B FLOOR DRAIN 2 DRAINS
CATCH BASIN 2 CATCH BASINS
MISC. FITTINGS&SUPPLIES 1 (LUMP SUM)
ESTIMATED COST $7,080.00
SPOHN RANCH, INC. P 626-330-5803 F 626-330-5503 1 W SPOHNRANCH.COM
E INFO@SPOHNRANCH.COM 1 6824 S CENTINELA AVE. LOS ANGELES, CA 90230
rie am DESIGN. BUILD. COME TOGETHER.
SPOHN RANCH
S K A T E P A R K S
CONCRETE
ITEM QUANTITY
CONCRETE FLATWORK 4,956 SQUARE FEET
ENTRY SIDEWALK 433 SQUARE FEET
CONCRETE LEDGES&MANUAL PADS 140 CUBIC FEET
CURVED CONCRETE LEDGES&MANUAL PADS 367 CUBIC FEET
CONCRETE BANKS 965 SQUARE FEET
SHOTCRETE 2,136 SQUARE FEET
CONCRETE TURNDOWN WALLS 6 SQUARE FEET
SAW CUT CONTROL JOINTS 700 LINEAR FEET
EXPANSION JOINT FOAM 150 LINEAR FEET
CAULKING FOR JOINTS 850 LINEAR FEET
ESTIMATED COST $213,145.00
ADD-ALTERNATES
ITEM ESTIMATED COST
INTEGRAL COLOR FOR FLATWORK $13,000.00
LIGHTING $15,000.00
TURF RESTORATION&LANDSCAPING $10,000.00
SPOHN RANCH, INC. I P 626-330-5803 F 626-330-5503 1 W SPOHNRANCH.COM
E INFO@SPOHNRANCH.COM 1 6824 S CENTINELA AVE. LOS ANGELES, CA 90230
r! tt DESIGN. BUILD. COME TOGETHER.
SPOHN RANCH
S K A T E P A R K S
TOTAL ESTIMATED COSTS
ITEM QUANTITY
MOBILIZATION/GENERAL REQUIREMENTS $25,000.00
STEEL FABRICATION $28,020.00
SITE PREPARATION&EARTHWORK $51,942.00
DRAINAGE $7,080.00
CONCRETE $213,145.00
+ADD-ALTERNATES $38,000.00
+PERFORMANCE/PAYMENT BOND $7,000.00
TOTAL ESTIMATED COST $370,187.00
ASSUMPTIONS
• HIGHLIGHTED ITEMS ARE OPPORTUNITIES FOR IN-KIND MATERIAL/SERVICE DONATIONS TO REDUCE COST
• CLIENT TO CAP/CUT IRRIGATION PRIOR TO CONSTRUCTION
• CLIENT TO PROVIDE TEMPORARY ACCESS TO WATER&POWER SOURCE FOR CONSTRUCTION USE
• CLIENT TO RELOCATE TRAIL MAP
• ESTIMATE ASSUMES PERMIT FEES WILL BE WAIVED
• ESTIMATE DOES NOT INCLUDE TESTING FEES
SPOHN RANCH, INC. I P 626-330-5803 1 F 626-330-5503 1 W SPOHNRANCH.COM
E INFO@SPOHNRANCH.COM 1 6824 S CENTINELA AVE. LOS ANGELES, CA 90230