4.3. SR 12-19-2016 Eclty1� ,.,�� Request for Action River To Item Number Mayor and City Council 4.3 Agenda Section Meeting Date Prepared by Consent December 19, 2016 Justin Femrite P.E., City Engineer Item Description Reviewed by Pay Estimates Lori Ziemer, Finance Director Reviewed by Cal Portner, City Administrator Action Requested Approve,by motion, the pay estimates as detailed below Background/Discussion The following pay estimates have been reviewed and found to be accurate and in accordance with the approved contract. Financial Impact PROJECT PAY EST. # CONTRACTOR AMOUNT WWTF Improvements 25 Rice Lake Construction Group $467,283.53 2015 Street Improvements Final North Valley,Inc. $132,262.83 Eastern Area Trail and Mobility Final U.S. Sitework $81,454.68 Attachments ■ Pay Estimates POWERED 6T Template Updoted 4/14 INAWRE1 g:\elk river\t21.106811_ramsey\8_construction_phase\pay requests\pay app 25\femrite pay app 25.docx December 6, 2016 Mr. Justin Femrite, P.E. City Engineer City of Elk River 13065 Orono Parkway Elk River, MN 55330 RE: Elk River WWTF WWTF Improvements Project Project No.: T21.106811 Dear Justin: Please find enclosed Pay Application No. 25 for the above referenced project. I have reviewed the Pay Application and find it to be complete and in order. I recommend that payment be made in the amount shown. If you agree, please sign and return one signed copy to the Contractor with payment and one to me for our files. If you have any questions on the above, please call. Sincerely, BOLTON & MENK, INC. Seth A. Peterson, P.E. Project Manager Cc: Tej Bala, Bolton & Menk, Inc. Enclosures CONTRACTOR'S PAY REQUEST DISTRIBUTION: 2015 STREET IMPROVEMENTS CONTRACTOR (1) CITY OF ELK RIVER OWNER (1) SAP 204-135-001, 204-107-007, 204-114-003, 204-116-002 ENGINEER (1) BMI PROJECT NO. N15.108340 BONDING CO. (1) TOTAL AMOUNT BID PLUS APPROVED CHANGE ORDERS $3,953,239.73 TOTAL, COMPLETED WORK TO DATE $4,038,191.27 TOTAL, STORED MATERIALS TO DATE $0.00 DEDUCTION FOR STORED MATERIALS USED IN WORK COMPLETED $0.00 TOTAL, COMPLETED WORK & STORED MATERIALS $4,038,191.27 RETAINED PERCENTAGE ( 0%) $0.00 TOTAL AMOUNT OF OTHER PAYMENTS OR (DEDUCTIONS) $0.00 NET AMOUNT DUE TO CONTRACTOR TO DATE $4,038,191.27 TOTAL AMOUNT PAID ON PREVIOUS ESTIMATES 1 $3,905,928.44 PAY CONTRACTOR AS ESTIMATE NO. 8 FINAL L $132,262.83 Certificate for Final Payment hereby certify that, to the best of my knowledge and belief, all items quantities and prices of work and material shown on this Estimate are correct and that all work has been performed in full accordance with the terms and conditions of the Contract for this project between the Owner and the undersigned Contractor, and as amended by any authorized changes, and that the foregoing is a true and correct statement of the amount for the Final Estimate, that the provisions of M. S. 290.92 have been complied with and that all claims against me by reason of the Contract have been paid or satisfactorily secured. Contractor: North Valley, Inc. 20015 Iguana St NW # 100 No_ hen MN 55330 y Presicimt »ead Name Title Date Dgomil er 6, 2016 Approved thi Contractor's Suret CHECKED AND APPROVED AS TO QUANTITIES AND AMOUNT: ENGINEER: BOLTON & M N , INC., 7533 Sunwood Drive NW, Suite 206, Ramsey, MN 55303 a BY , PROJECT ENGINEER Cody L."Holmes, P.E. Date t .�-J-11 6 � 12-0 t 6 APPROVED FOR PAYMENT: OWNER: By Name Title Date And Name Title Date Partial Pay Estimate No.: 6 FI 2015 STREET IMPROVEMENTS CITY OF ELK RIVER SAP 204135-001, 204-107-W7,204-114-003, 204116-002 BMI PROJECT NO. N15.108340 "4r)Rl M, N,! - vr;"' 7 nc-; nR--R �R> -7 ITEM NO. ITEM UNIT PRICE AS BID PREVIOUS ESTIMATE COMPLETED TO DATE ESTIMATED QUANTITY ESTIMATED ESTIMATED AMOUNT QUANTITY ESTIMATED ESTIMATED AMOUNT QUANTITY ESTIMATED AMOUNT 1 2021.501 MOBILIZATION $149,206.38 1 UM $149,206.38 1 LUMP SUM $149,206.38 1.00 LUMP SUM $149,206.36 2 2101.511 CLEARING AND GRUBBING $3,733.15 1 UM $3,733.15 1 LUMP SUM $3,733.15 1.00 LUMP SUM $3,733.15 3 2104.501 REMOVE CONCRETE CURB &GUTTER $4.80 880T %LIQN $4,224.00 841 LIN FT $4,036.80 841.00 LIN FT $4,036.80 4 2104.501 REMOVE SEWER PIPE STORM $10.93 764T $8,350.52 614 LIN FT $6,711.02 614.00 LIN FT $6,711.02 5 2104.503 REMOVE CONCRETE DRIVEWAY PAVEMENT $1.33 5013T $6,667.29 4814 SQ FT $6,402.62 4,999.00 SO FT $6,648.67 6 2104.505 REMOVE CONCRETE VALLEY GUTTER $14.40 40D $576.00 56.2 SQ YD $809.28 56.20 SQ YD $809.28 7 2104.505 REMOVE BITUMINOUS DRIVEWAY PAVEMENT $5.07 1628 SQ YD $8,253.96 2737 SQ YD $13,876.59 2,737.00 SQ YD $13,876.59 8 2104.505 REMOVE BITUMINOUS PAVEMENT $6.24 400 SQ YD $2,496.00 0 SQ YD $0.00 0.00 SQ YD $0.00 9 2105.501 COMMON EXCAVATION P $17.60 16416 CU YD $288,921.60 16416 CU YD $288,921.60 16,416.00 CU YD $288,921.60 10 2105.505 MUCK EXCAVATION L $0.53 12000 CU YD $6,360.00 3290 CU YD $1,743.70 3,290.00 CU YD $1,743.70 11 2105.507 SUBGRADE EXCAVATION E $10.13 710 CU YD $7,192.30 7682 CU YD $77,818.66 8,954.00 CU YD $90,704.02 12 2105.521 GRANULAR BORROW C $0.53 14200 CU YD $7,526.00 0 CU YD $0.00 0.00 CU YD $0.00 13 2105.522 SELECT GRANULAR BORROW CV $0.53 710 CU YD $376.30 3290 CU YD $1,743.70 3,290.00 CU YD $1,743.70 14 2105.535 PLACE SALVAGED AGGREGATE FROM STOCKPILE (CLASS 7) $4.001 7275 CU YD $29,100.00 8856.6 CU YD $35,426.40 8,846.50 CU YD $35,386.00 15 2105.607 POND EXCAVATION P $10.40 665 CU YD $6,916.00 665 CU YD $6,916.00 665.00 CU YD $6,916.00 16 2118.607 AGGREGATE SURFACING C CLASS 2 $63.90 925 CU YD $59,107.50 971.5 CU YD $62,078.85 971.501 CU YD $62,078.85 17 2211.501 AGGREGATE BASE CV CLASS 5 $10.67 15570 TON $166,131.90 23142.28 TON $246,928.13 23,324.631 TON $248,873.80 18 2215.501 BITUMINOUS PAVEMENT RECLAMATION IN-PLACE 8" DEPTH $1.62 48764 SQ YD $78,997.68 61018.68 SQ YD $98,850.26 61,018.68 SQ YD $98,850.26 19 2215.501 BITUMINOUS PAVEMENT RECLAMATION 8" DEPTH $2.08 32576 SQ YD $67,758.08 32576 SQ YD $67,758.08 32,576.00 SQ YD $67,758.08 20 2231.501 BITUMINOUS PATCHING MIXTURE $0.01 675 TON $6.75 27.33 TON $0.27 27.33 TON $0.27 21 2231.604 BITUMINOUS PATCH - SPECIAL(ROADWAY) $42.35 800 SQ YD $33,850.00 1538 SQ YD $65,134.30 2,232.00 SQ YD $94,525.20 22 2231.604 BITUMINOUS PATCH -SPECIAL(DRIVEWAY) $29.28 1938 SQ YD $56,744.64 2496.7 SQ YD $73,103.38 2,496.70 SQ YD $73,103.38 23 2232.501 MILL BITUMINOUS SURFACE 1.5" $1.38 4226 SQ YD $5,831.88 10897 SQ YD $15,037.86 10,897.00 SQ YD $15,037.86 24 2232.501 MILL BITUMINOUS SURFACE 3" $1.11 6563 SQ YD $7,284.93 12852.86 SQ YD $14,266.67 12,852.86 SQ YD $14,266.67 25 2232.501 MILL BITUMINOUS SURFACE APER 0" - 2" $0.92 11305 SQ YD $10,400.60 8917 SQ YD $87203.64 8,917.00 SQ YD $8,203.64 26 2360.501 TYPE SP 9.5 WEARING COURSE MIXTURE 2,C $61.02 19037 TON $1,161,637.74 16254.37 TON $991,841.66 16,270.11 TON $992,802.11 27 2360.501 TYPE SP 9.5 WEARING COURSE MIXTURE 4,E $60.091 3486 TON $209,473.74 3788.22 TON $227,634.14 3,788.22 TON $227,634.14 28 2360.502 TYPE SP 12.5 NON WEARING COURSE MIXTURE 2,C $54.65 11648 TON $636,563.20 12889.03 TON $704,385.49 12,889.03 TON $704,385.49 29 2411.618 MODULAR BLOCK RETAINING WALL $30.53 525 SQ FT $16,028.25 0 SQ FT $0.00 0.00 SQ FT $0.00 30 2501.515 12" RC PIPE APRON $602.64 16 EACH $9,642.24 16 EACH $9,642.24 16.00 EACH $9,642.24 31 2501.515 15" RC PIPE APRON $693.30 6 EACH $4,159.80 6 EACH $4,159.80 6.00 EACH $4,159.80 32 2501.515 18" RC PIPE APRON $735.96 6 EACH $4,415.76 6 EACH $4,415.76 6.00 EACH $4,415.76 33 2501.601 DRAINAGE IMPROVEMENTS AND REPAIR PIPE CULVERT $3,749.16 1 LUMP SUM $3,749.16 1 LUMP SUM $3,749.16 1.00 LUMP SUM $3,749.16 34 2501.602 TRASH GUARD FOR 12" PIPE ARPON $351.98 16 EACH $5,631.68 18 EACH $6,335.64 18.00 EACH $6,335.64 35 2501.602 TRASH GUARD FOR 15" PIPE ARPON $405.31 6 EACH $2,431.86 6 EACH $2,431.86 6.00 EACH $2,431.86 36 2501.602 TRASH GUARD FOR 18" PIPE ARPON $474.64 6 EACH $2,847.84 6 EACH $2,847.84 6.00 EACH $2,847Z4 37 2503.541 12" RC PIPE SEWER DESIGN 3006 CLASS V $30.93 532 LIN FT $16,454.76 424 LIN FT $13,114.32 424.00 LIN FT $13,114.32 38 2503.541 15" RC PIPE SEWER DESIGN 3006 CLASS V $33.07 229 LIN FT $7,573.03 268 LIN FT $8,862.76 268.00 LIN FT $8,862.76 39 40 2503.541 18" RC PIPE SEWER DESIGN 3006 CLASS V 2504.602 ADJUST GATE VALVE AND BOX $37.33 $266.65 300 13 LIN FT EACH $11,199.00 $3,466.45 272 13 LIN FT EACH $10,153.76 $3,466.45 272.00 16.00 LIN FT EACH $10,153.76 $4,266.40 Partial Pay Estimate No.: ,-'? FI 2015 STREET IMPROVEMENTS CITY OF ELK RIVER SAP 204-135-001, 204-107-007, 204114-003, 204116-002 BMI PROJECT NO. N15.108340 `:fr7OR✓ �v�^^ �tL--Cis __BEY: ' "` L�i� Y '_ 20,',S ITEM NO. ITEM UNIT PRICE AS BID ESTIMATED QUANTITY ESTIMATED AMOUNT PREVIOUS ESTIMATE ESTIMATED ESTIMATED QUANTITY AMOUNT COMPLETED TO DATE ESTIMATED ESTIMATED QUANTITY AMOUNT 41 2504.602 RECONSTRUCT VALVE BOX $719.97 4 EACH $2,879.88 0 EACH $0.00 0.00 EACH $0.00 42 2506.522 ADJUST FRAME AND RING CASTING $426.65 25 EACH $10,666.25 30 EACH $12,799.50 30.00 EACH $12,799.50 43 2511.501 RANDOM RIPRAP CLASS If $98.13 42 CU YD $4,121.46 42 CU YD $4,121.46 42.00 CU YD $4,121.46 44 2521.602 6" CONCRETE SPILLWAY SPECIAL $213.32 89 EACH $18,985.48 82 EACH $17,492.24 82.00 EACH $17,492.24 45 2531.501 CONCRETE CURB &GUTTER DESIGN B618 $10.61 26613 LIN FT $282,363.93 25708 LIN FT $272.767.88 25,708.00 LIN FT $272,761.88 46 2531.501 CONCRETE CURB & GUTTER DESIGN B818 MEDIAN $10.61 760 LIN FT $8,063.60 0 LIN FT $0.00 0.00 LIN FT $0.00 47 2531.503 CONCRETE MEDIAN 5" $38.40 96 SQ YD $3,686.40 0 SQ YD $0.00 0.00 SQ YD $0.00 48 2531.507 CONCRETE DRIVEWAY PAVEMENT 7"} $43.20 1897 SQ YD $81,950.40 1075.03 SQ YD $46,441.30 1,075.03 SQ YD $46,441.30 49 2531.604 CONCRETE MEDIAN NOSE - SPECIAL $57.60 42 SQ YD $2,419.20 0 SQ YD $0.00 0.00 SQ YD $0.00 50 2531.604 7" CONCRETE VALLEY GUTTER $57.60 40 SQ YD $2,304.00 56.2 SQ YD $3,237.12 56.20 SO YD $3,237.12 51 2535.501 BITUMINOUS CURB 6" $6.24 2100 LIN FT $13,104.00 5299.5 LIN FT $33,068.88 5,299.50 LIN FT $33,068.88 52 2563.601 TRAFFIC CONTROL $8,746.24 1 LUMP SUM $8,746.24 1 LUMP SUM $8,746.24 1.00 LUMP SUM $8,746.24 53 2563.601 FLAG PERSON BNSF CROSSING $15,999.23 1 LUMP SUM $15,999.23 0.25 LUMP SUM $3,999.81 0.25 LUMP SUM $3,999.81 54 2554.531 SIGN PANEL TYPE C $32.00 435 SQ FT $13,920.00 374.2 SQ FT $11,974.40 374.20 SQ FT $11,974.40 55 2565.602 NMC LOOP DETECTOR 6'X 6' $1,056.42 39 EACH $41,200.38 381 EACH $40,143.96 38.001 EACH $40,143.96 56 2573.502 SILT FENCE TYPE MACHINE SLICED $1.92 6498 LIN FT $12,476.16 40261 LIN FT $7,729.92 4,026.00 LIN FT $7,729.92 57 2573.53 STORM DRAIN INLET PROTECTION $127.99 48 EACH $6,143.52 45 EACH $5,759.55 45.001 EACH $5,759.55 58 2573.533 SEDIMENT CONTROL LOG TYPE WOOD CHIP $3.04 3870 LIN FT $11,764.80 1696 LIN FT $5,155.84 2,620.00 LIN FT $7,964.80 59 2573.535 STABILIZED CONSTRUCTION EXIT $874.63 2 EACH $1,749.26 0 EACH $0.00 0.00 EACH $0.00 60 2574.508 FERTILIZER TYPE 3 $0.53 1745 POUND $924.85 3040 POUND $1,611.20 3,360.00 POUND $1,780.80 61 2574.525 COMMON TOPSOIL BORROW C $9.07 2360 CU YD $21,405.20 37 CU YD $335.59 37.00 CU YD $335.59 62 2575.501 SEEDING $133.33 5 ACRE $666.65 8.7 ACRE $1,159.97 9.40 ACRE $1,253.30 63 2575.502 SEED MIXTURE 25-121 $3.35 305 POUND $1,021.75 532 POUND $1,782.20 635.77 POUND $2,129.83 64 2575.562 HYDRAULIC MATRIX TYPE BONDED FIBER $1.07 17500 POUND $18,725.00 30400 POUND $32,528.00 33,150.00 POUND $35,470.50 65 2582.501 PAVEMENT MESSAGE LEFT TURN ARROW) EPDXY $124.88 9 EACH $1,123.92 8 EACH $999.04 8.00 EACH $999.04 66 2582.501 PAVEMENT MESSAGE RIGHT TURN ARROW EPDXY $124.88 6 EACH $749.28 7 EACH $874.16 7.00 EACH $874.16 67 2582.501 PAVEMENT MESSAGE LEFT-THRU ARROW EPDXY $192.99 2 EACH $385.98 2 EACH $385.98 2.00 EACH $385.98 68 2582.501 PAVEMENT MESSAGE HRU ARROW) EPDXY $124.88 2 EACH $249.76 3 EACH $374.64 3.00 EACH $374.64 69 2582.501 PAVEMENT MESSAGE RR XING EPDXY $737.91 4 EACH $2,951.64 4 EACH $2,951.64 4.00 EACH $2,951.64 70 2582,502 4" SOLID LINE WHITE - EPDXY $0.26 26856 LIN FT $6,982.56 262371 LIN FT $6,821.62 26,237.00 LIN FT $6,821.62 71 2582.502 4" BROKEN LINE WHITE - EPDXY $0.26 1660 LIN FT $431.60 1740 LIN FT $452.40 1,740.00 LIN FT $452.40 72 2582.502 4" SOLID DOUBLE LINE YELLOW - EPDXY $0.51 26428 LIN FT $13,478.28 31731 LIN FT $16,182.81 31,731.00 LIN FT $16,182.81 73 2582,502 24" SOLID LINE WHITE - EPDXY $7.95 285 LIN FT $2,265.75 218.5 LIN FT $1,737.08 218.50 LIN FT $1,737.08 74 2582.503 CROSSWALK MARKING - EPDXY $4.54 14581 SQ FT 1 $6,619.32 1314 SQ FT $5,965.56 1,314,00 SQ FT $5,965.56 TOTAL AMOUNT: $3,731,843.70 $3,789,342.20 $3,841,892.21 CHANGE ORDER #1 75 2021.501 MOBILIZATION $149,206.38 0.05 LUMP SUM $7,460.32 0.05 LUMP SUM $77460.32 0.05 LUMP SUM $7,460.32 76 2105.501 REMOVE CONCRETE CURB & GUTTER $4.80 35 LIN FT $168.00 10 LIN FT $48.00 10.00 LIN FT $48.00 77 2231.501 BITUMINOUS PATCHING MIXTURE $0.01 25 TON $0.25 0 TON Koo 0.00 TON $0.00 78 2232.501 MILL BITUMINOUS SURFACE 1.5" $1.38 9900 SQ YD $13,662.00 9611 SQ YD $13,263.18 9,611.00 SQ YD $13,263.18 79 2360.501 TYPE SP 9.5 WEARING COURSE MIXTURE 2,C $61.02 850 TON $51,867.00 781.05 TON $47,659.67 781.05 TON $47,659.67 80 2531.501 CONCRETE CURB & GUTTER DESIGN 8618 $10.61 35 LIN FT $371.35 10 LIN FT $106.10 10.00 LIN FT $106.10 Partial Pay Estimate No.: 53 RNA 2015 STREET IMPROVEMENTS CITY OF ELK RIVER SAP 204135-001, 204-107-007, 204-114-003, 204116-002 BMI PROJECT NO. N15.108340 -- T G C ROUGH 7 , 2016 AS BID PREVIOUS ESTIMATE COMPLETED TO DATE UNIT ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ITEM ITEM PRICE QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT NO $73,528.92 $68,537.27 $68,537.27 CHANGE ORDER #2 $149,206.38 0.05 LUMP SUM $7,460.32 0.05 LUMP SUM $7,460.32 0.05 LUMP SUMI $7,460.32 81 2021.501 MOBILIZATION $4.80 50 LIN FT $240.00 01 LIN FT $0.00 0.00 LIN FT $0.00 82 2104.501 REMOVE CONCRETE CURB & GUTTER $17.60 815 CU YD $14,344.00 6901 CU YD $12,144.00 690.00 CU YD $12,144.00 83 2105.501 COMMON EXCAVATION P BITUMINOUS PAVEMENT RECLAMATION 8" DEPTH $2.08 5870 SO YD $12,209.60 -49641 SO YD $10,325.12 4,964.00 SO YD $10,325.12 84 85 2215.501 2232.501 MILL BITUMINOUS SURFACE TAPER 0" - 2" $0.92 535 SO YD $492.20 5601 SQ YD $515.20 560.00 SO YD $515.20 $49,781.95 86 2360.501 TYPE SP 9.5 WEARING COURSE MIXTURE 2,C $61.02 865 TON $52,782.30 815.83 TON $49,781.95 815.83 TON 87 2360.502 TYPE SP 12.5 NON WEARING COURSE MIXTURE 2,C $54.68 10161 TON $55,554.88 818.76 TON $44,769.89 818.76 TON $44,769.80 88 2531.501 CONCRETE CURB & GUTTER DESIGN 8618 $10.51 50 LIN FT $530.50 0 LIN FT LUMP SUM $0.00 $2,186.56 0.00 LIN FT 0.25 LUMP SUM $0.00 $2,186.56 89 2563.601 TRAFFIC CONTROL $8,746.24 0.25 LUMP SUM $2,186.56 0.25 EACH $0.00 0.00 EACH $0.00 90 2573.530 STORM DRAIN INLET PROTECTION $127.99 5 EACH $639.95 0 0 LIN FT $0.00 0.00 LIN FT $0.00 91 2582.502 4" SOLID LINE WHITE - EPDXY $0.26 2400 LIN FT LIN FT $624.00 $612.00 1135 LIN FT $578.85 1,135.00 LIN FT $578.85 92 2582.502 4" SOLID DOUBLE LINE YELLOW - EPDXY $0.51 1200 LIN FT $190.80 0 LIN FT $0.00 0.00 LIN FT $0.00 93 2582.502 24" SOLID LINE WHITE - EPDXY $7.95 24 $147,867.11 $127,761.79 $127,761.79 TOTAL AMOUNT: $3,953,239.73 $3,985,641.26 $4,038,191.27 Final Pay Estimate No.:3 (Final)EASTERN AREA TRAIL AND MOBILITY IMPROVEMENTSCITY OF ELK RIVERSP 204-090-003, MN PROJECT NUMBER TA 7115BMI PROJECT NO. N15.108488WORK COMPLETED THROUGH SEPTEMBER 2, 2016ITEM MNDOT UNIT ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATEDNO. NO.ITEMPRICE QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT1 2021.501 MOBILIZATION$25,000.00 1 LUMP SUM $25,000.00 1 LUMP SUM $25,000.00 1 LUMP SUM $25,000.002 2101.502 CLEARING$170.00 56 TREE $9,520.00 24 TREE $4,080.00 24 TREE $4,080.003 2101.507 GRUBBING$85.00 56 TREE $4,760.00 24 TREE $2,040.00 24 TREE $2,040.004 2104.501 REMOVE CURB AND GUTTER$4.10 324 LIN FT $1,328.40 503 LIN FT $2,062.30 503 LIN FT $2,062.305 2104.503 REMOVE CONCRETE SIDEWALK$1.10 707 SQ FT $777.70 615 SQ FT $676.50 615 SQ FT $676.506 2104.505 REMOVE BITUMINOUS TRAIL / DRIVEWAY PAVEMENT $5.80 119 SQ YD $690.20 83 SQ YD $481.40 83 SQ YD $481.407 2104.505 REMOVE BITUMINOUS PAVEMENT$5.00 385 SQ YD $1,925.00 449 SQ YD $2,245.00 449 SQ YD $2,245.008 2104.513 SAWING BITUMINOUS PAVEMENT (FULL DEPTH) $4.30 1400 LIN FT $6,020.00 1467.5 LIN FT $6,310.25 1556 LIN FT $6,690.809 2104.521 SALVAGE FENCE$28.50 75 LIN FT $2,137.50 48 LIN FT $1,368.00 48 LIN FT $1,368.0010 2104.523 SALVAGE PIPE APRON$220.00 1 EACH $220.00 1 EACH $220.00 1 EACH $220.0011 2104.601 RELOCATE MONUMENT$1,365.00 1 LUMP SUM $1,365.00 1 LUMP SUM $1,365.00 1 LUMP SUM $1,365.0012 2105.501 COMMON EXCAVATION (EV) (P)$26.50 1647 CU YD $43,645.50 1647 CU YD $43,645.50 1647 CU YD $43,645.5013 2105.507 SUBGRADE EXCAVATION (EV)$26.50 165 CU YD $4,372.50 0 CU YD $0.00 0 CU YD $0.0014 2105.507 STABILIZING AGGREGATE$65.50 165 CU YD $10,807.50 0 CU YD $0.00 0 CU YD $0.0015 2118.501 AGGREGATE SURFACING, CLASS 2$101.00 10 TON $1,010.00 0 TON $0.00 0 TON $0.0016 2211.501 AGGREGATE BASE, CLASS 5$17.00 2165 TON $36,805.00 2234.5 TON $37,986.50 2332.81 TON $39,657.7717 2231.604 TYPE SP 12.5 BITUMINOUS PATCH SPECIAL [SPWEB340B] $53.25 330 SQ YD $17,572.50 450.7 SQ YD $23,999.78 450.70 SQ YD $23,999.7818 2360.501 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) [SPWEA240B] $105.50 707 TON $74,588.50 519.46 TON $54,803.03 776.97 TON $81,970.3419 2411.618 MODULAR BLOCK RETAINING WALL$30.50 1320 SQ FT $40,260.00 995 SQ FT $30,347.50 995 SQ FT$30,347.5020 2501.573 INSTALL PIPE APRON$2,710.00 1 EACH $2,710.00 1 EACH $2,710.00 1 EACH $2,710.0021 2503.511 27" RC PIPE SEWER CLASS 3$143.00 8 LIN FT $1,144.00 8 LIN FT $1,144.00 8 LIN FT $1,144.0022 2504.602 ADJUST GATE VALVE & BOX$559.00 1 EACH $559.00 4 EACH $2,236.00 4 EACH $2,236.0023 2504.602 RELOCATE HYDRANT$2,530.00 1 EACH $2,530.00 1 EACH $2,530.00 1 EACH $2,530.0024 2506.522 ADJUST FRAME AND RING CASTING$807.00 1 EACH $807.00 1 EACH $807.00 1 EACH $807.0025 2521.501 5" CONCRETE WALK$6.30 5313 SQ FT $33,471.90 4129 SQ FT $26,012.70 4129 SQ FT $26,012.7026 2531.501 CONCRETE CURB & GUTTER DESIGN B618 $30.00 1374 LIN FT $41,220.00 1435 LIN FT $43,050.00 1457 LIN FT $43,710.0027 2531.533 PEDESTRIAN CURB RAMP$105.00 202 SQ YD $21,210.00 325.6 SQ YD $34,188.00 387 SQ YD $40,635.0028 2531.618 TRUNCATED DOMES$46.00 328 SQ FT $15,088.00 308 SQ FT $14,168.00 308 SQ FT $14,168.0029 2545.602 ADJUST HANDHOLE$636.00 2 EACH $1,272.00 3 EACH $1,908.00 3 EACH $1,908.0030 2554.603 INSTALL FENCE$85.00 75 LIN FT $6,375.00 48 LIN FT $4,080.00 48 LIN FT $4,080.0031 2557.501 WIRE FENCE DESIGN 48V-9322$175.00 60 LIN FT $10,500.00 56 LIN FT $9,800.00 56 LIN FT $9,800.0032 2557.501 WIRE FENCE DESIGN 60V-9322$61.50 330 LIN FT $20,295.00 190 LIN FT $11,685.00 190 LIN FT $11,685.0033 2563.601 TRAFFIC CONTROL$4,950.00 1 LUMP SUM $4,950.00 1 LUMP SUM $4,950.00 1 LUMP SUM $4,950.0034 2563.601 FLAG PERSON (BNSF CROSSING)$7,490.00 1 LUMP SUM $7,490.00 1 LUMP SUM $7,490.00 1 LUMP SUM $7,490.0035 2564.602 RELOCATE SIGN$155.00 12 EACH $1,860.00 14 EACH $2,170.00 14 EACH $2,170.0036 2572.505 PRUNE TREES$182.00 5 HOUR $910.00 3 HOUR $546.00 3 HOUR $546.0037 2573.502 SILT FENCE, TYPE PREASSEMBLED$1.50 5167 LIN FT $7,750.50 4498 LIN FT $6,747.00 4498 LIN FT $6,747.0038 2573.530 STORM DRAIN INLET PROTECTION$165.00 25 EACH $4,125.00 25 EACH $4,125.00 25 EACH $4,125.0039 2573.533 SEDIMENT CONTROL LOG TYPE WOOD FIBER $4.10930 LIN FT $3,813.00 0 LIN FT $0.00 150 LIN FT $615.0040 2574.508 FERTILIZER TYPE 3 (22-5-10)$1.00 1729 POUND $1,729.00 750 POUND $750.00 750 POUND $750.0041 2574.525 COMMON TOPSOIL BORROW (CV)$25.00 1059 CU YD $26,475.00 154 CU YD $3,850.00 167 CU YD $4,175.0042 2575.501 SEEDING$511.00 5 ACRE $2,555.00 1.44 ACRE $735.84 1.44 ACRE $735.84AS BID PREVIOUS ESTIMATE COMPLETED TO DATEESTIMATED Final Pay Estimate No.:3 (Final)EASTERN AREA TRAIL AND MOBILITY IMPROVEMENTSCITY OF ELK RIVERSP 204-090-003, MN PROJECT NUMBER TA 7115BMI PROJECT NO. N15.108488WORK COMPLETED THROUGH SEPTEMBER 2, 2016ITEM MNDOT UNIT ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATEDNO. NO.ITEMPRICE QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNTAS BID PREVIOUS ESTIMATE COMPLETED TO DATEESTIMATED43 2575.502 SEED MIXTURE 25-121$3.40 304 POUND $1,033.60 350 POUND $1,190.00 350 POUND $1,190.0044 2575.523 EROSION CONTROL BLANKET CATEGORY 3 $0.85 23958 SQ YD $20,364.30 6984 SQ YD $5,936.40 6984 SQ YD $5,936.4045 2582.502 4" SOLID LINE WHITE - EPOXY$0.65 1374 LIN FT $893.10 717 LIN FT $466.05 717 LIN FT $466.0546 2582.503 CROSSWALK MARKING - EPOXY$6.10 936 SQ FT $5,709.60 694 SQ FT $4,233.40 865 SQ FT $5,276.50SUBTOTAL AMOUNT$529,645.30 $434,139.15 $472,448.37CHANGE ORDER NO. 11 2105.501 COMMON EXCAVATION$26.50CU YD $0.00 809 CU YD$21,438.50SUBTOTAL AMOUNT$21,438.50TOTAL AMOUNT$529,645.30 $434,139.15 $493,886.87 x xx 11/29/16 11-28-2016 612-756-3440CodyHolmes