9.4. SR 04-17-2017 EOty1� ,.,�� Request for Action River To Item Number Mayor and City Council 9.4 Agenda Section Meeting Date Prepared by Work Session Aril 17, 2017 Cal Portner, City Administrator Item Description Reviewed by Recreation Facilities Plans and Cost Estimates Michael Hecker, Parks and Recreation Director Reviewed by Action Requested Receive information, discuss, and provide direction. Background/Discussion The Elk River City Council initiated a task force to comprehensively review aging and deteriorating parks and recreation facilities, namely the Ice Arena, Lions Park Center, and Activity (55+) Center and to recommend possible solutions. The task force worked with JLG Architects and other consultants to identify facility concerns, improvement options, community and stakeholder needs, and potential costs. The result was a recommendation to construct one multipurpose facility to replace existing uses, decrease operational costs,increase revenue potential, accommodate future growth, and minimize short-term impacts. The Council elected to add a ballot measure for a citywide referendum,which occurred in November of 2016. The Council was in unanimous agreement that each of the existing facilities were in need of substantial improvements and investments regardless of the ballot outcome. The initiative failed by roughly 800 votes. The task force's second recommendation was to improve the existing facilities,which coincided with a 2012 architectural study on the Ice Arena by 292 Design Group. Staff worked with 292 Design Group,Wold Architects who are working with ISD#728 on their athletic facility improvements, and JLG Architects to develop alternatives consistent with City Council direction. Further, at the request of Council Member Wagner and Sherburne County Commissioner Tim Dolan, who serves on the Elk River YMCA Board of Directors, the Mayor and staff met with YMCA officials to discuss the potential of moving senior services to the YMCA. Reconstruction of the Ice Arena and providing for future growth encumbers a portion of the high school fastpitch softball field,which would need to be relocated. The district intends to move the tennis courts as a part of their improvements. POWERED 6T A IR Senior Activity Center options include the following: 1) Provide for needed repairs/improvements and growth to existing space,which includes adjoining property acquisition. 2) Consider moving senior services to the YMCA. 3) Consider reconstruction of Lions Park Center to include senior and community space and repurposing the existing senior facility for redevelopment. Lions' Park Center options include: 1) Demolition. The current space could be used for fastpitch softball field replacement. 2) Partial demolition,leaving the existing office space and restrooms for locker room, storage, and concession space. 3) Reconstruction for senior/community space as stated earlier. In each case, added community room space is added to improved facilities to ensure current and future needs are met for community activities such as Lions Club fundraisers, existing, future park programming, and community-wide events,which would also remove one building from the city inventory as a cost reduction. Cost estimates are a result of the information and parameters provided for the planning. All are subject to bid pricing,inflation,bond costs, and specification changes during the value engineering phase of the project. Financial Impact Plans and Cost Estimates for discussion Attachments ■ 292 Design Group Plans and Cost Estimates ■ JLG Plans and Cost Estimates N:APublic Bodies\Agenda Packets\04-17-2017\Final\x9.4 sr Recreation Facilities.docx zy\ wo w U) 220 , <20 '20 , <2<2-00 , D - --- -- --- -- -- 00 , w ry IT U) CY) LLJ 0 LU 2 �F Z 0 0 D I 0 0 1 JY w z �E I w �0- co Lu U) ------------ W ------------------------------------------- -------------------------------------------------------- > z w tiw U)U) w of LL, wfn LL, L) m < f z 0 w7- 2 �2 LLJ 0 U) D U, U W of 0 W U) w L) - ------------------- LLJ� Lu— gof 0 'P U) lw ly L) 0 . 0 0 w 0 �g z z <0 Lu 0 o u LL], of FY COU Z 111 =)of[, ofCO< o it <L)L i� U, LU 2u) (If 0 0 < LLJ 0 <0 w 0 czr D 0 m <0 wo �g m (D w 0 W�<L < = of 0 0 U) z WAR L) s. L-------------------------------------------------------------- 0 2 0 w00 O LL,0 LU fof D =).O� LU �LL, Dy D =)�L 2 0 LL, 0 ----------- --------- Q LLI' O a OF pI z pa � z D ` CD z Z N LLI 1 0 61 � � N O O O O JY \ n ZZ I CE I ZE r I w �\\ O O O 1\\ O w U Z I 7 O J FYI Z I Z LU p w� wm z aLL m I p z Q I �O d 11 of 0 _ I Fw z E= Lr i - z z ro it i N JY Z� � rLJ O O LLJI i I-Z i O O ¢_ i C a w ------------------ J N a SM z � � off N - N Q t N 61 AOR N - 1 �� J w 11 y \ o \ � r _ 11 � ! p wLLl i wW, 7 MT Is Qo� IX-0 J 0 ------------- �Eimoo a a oo wp wo wp ¢ X0 d S 12 I - a 1 Z y o= r v r' a N . N CONSTRUCTION April 12, 2017 Tom Betti Partner 292 Design Group 3533 E Lake St Minneapolis, MN 55406 Re: Elk River Ice Arena Dear Mr. Betti, RIM Construction is pleased to present a preliminary estimate for the Elk River Ice Arena project located in Elk River, Minnesota. Together with The City of Elk River and 292 Design Group, we can work as a team to deliver the project goals of cost, schedule and quality. Our estimate is based upon drawings dated March 27, 2017 and site visit conducted April 10, 2017. Total Base Construction Estimate: $18,768,461 CLARIFICATIONS: No. 1: Value above is the estimated construction value only. Please see the attached estimate summary with additional potential owner cost items. Thank you for the opportunity to provide this estimate. Our team is experienced and competent in your market; this applied knowledge will assist the team in obtaining the best possible project value. Please feel free to contact RIM if you have any questions or need additional information. Sincerely, Eric Sonnenberg Estimator W� 701 Washi%Lon Avenue NO[ .00 Minneapolis, . .00 VP CONSTRUCTION PRELIMINARY ESTIMATE SUMMARY ESTIMATE DATE: April 12, 2017 PROJECT: Elk River Ice Arena ARCHITECT: 292 Design Group DRAWING DATE: March 27, 2017 Base $/sf DESCRIPTION Notes Estimate 125,606 Construction Costs Selective Demolition Interior Demo at Existing Rink $315,240 $2.51 Concrete $646,727 $5.15 Precast Concrete $2,306,118 $18.36 Masonry $838,049 $6.67 Structural Steel $712,184 $5.67 Metal Fabrications $142,884 $1.14 Rough Carpentry $67,751 $0.54 Millwork $118,830 $0.95 Roofing $622,440 $4.96 Waterproofing At Elevator Pit Only $3,000 $0.02 Joint Sealants $18,343 $0.15 Doors Frames Hardware $110,281 $0.88 Glass&Glazing $268,150 $2.13 Finishes $847,803 $6.75 Specialties $19,884 $0.16 Aluminum Benches Locker Room &Stadia Benches $102,800 $0.82 Aluminum Bleacher Relocation $30,000 $0.24 Site Furnishings $3,500 $0.03 Ice Rink System $3,020,000 $24.04 Elevators $75,000 $0.60 Fire Protection $196,951 $1.57 Plumbing $747,804 $5.95 HVAC $1,353,964 $10.78 Electrical $1,561,632 $12.43 Earthwork Includes Barn demo. $428,470 $3.41 Site Paving $5,250 $0.04 Site Concrete $20,481 $0.16 Site Utilities Allowance $75,000 $0.60 Landscaping $16,058 $0.13 Survey $32,372 $0.26 General Conditions&Reimbursable Ex enses $624,213 $4.97 Temp Heat&Barriers $117,952 $0.94 Daily&Final Clean $57,267 $0.46 General Liability Insurance $155,064 $1.23 Builders Risk Insurance $37,215 $0.30 113uilding Permit 1 $180,181 1 $1.43 Bond 1 1 $113,405 1 $0.90 ESTIMATE DATE: April 12, 2017 PROJECT: Elk River Ice Arena ARCHITECT: 292 Design Group DRAWING DATE: March 27, 2017 Subtotal Construction Costs $15,992,264 $127,32 Escalation 2% - 2018 Bidding Assumed $319,845 $2.55 Design Contingency 5% $799,613 $6.37 Construction Contingency 7% $1,141,848 $9.09 Contractor's Fee 2.95% $514,892 $4.10 Total Construction Estimate $18,768,461 $149,42 Owner Costs SAC/WAC Fees Allowance $50,000 $0.40 Site Survey&Soil Borings Allowance $15,000 $0.12 FF&E Allowance $150,000 $1.19 Owner Equipment Allowance $25,000 $0.20 Low Voltage (Phone, Data &SecurityAllowance $75,000 $0.60 Audio Systems Allowance $100,000 $0.80 Zamboni $0 $0.00 Scoreboard Allowance $100,000 $0.80 Environmental Disposal To be determined $0 $0.00 Soil Corrections To be determined $0 $0.00 Owner Moving Expense $0 $0.00 Owner Artwork and Signage $0 $0.00 Subtotal Owner Costs $515,000 $4,10 Design Fees Architectural &Engineering Design Fees $1,253,425 $9.98 Subtotal Design Fees $1,253,425 $9,98 Contingency Owner Contingency 5% $1,026,844 $8.18 Subtotal Contingency $1,026,844 $8,18 Total Project Estimate 1 $21,563,731 $171.68 u O z z z 0 0000a � oa o a ti � �000 � o 00 0 Z z w aD o a � zJ z aa ' v o z H X w V LL LL O 5� a � oa0 N ~ Z H Z w a 0 O 0 cd Z O v Zu JiO��ZQ Z > 0 ANO - o Jv va oow � < a z Qz o 0 r � 00 > v� C� � z ZF � w �� � � � OV Onn - adz z � � 0 (DZ - z < O 0 0000z 00 0 � Z`57<U � wv7 H � Z <nOH Vvo - --i v~io n ^ v o w w v~- O 1 n Q O G 0 o 0 0 L.V OZ LL a o V O 0 0 s ol= � =Iw w � U Q a Y ❑ ❑ ❑ � ❑ ❑ � ❑ 0- .0" ❑ o� z L3 o i Q ❑ 7� ff-fto 1. 2 i �ry ❑ w 8 x i Q F 7 � � ,LL Q C o ❑,❑ E IL c� n I � Do Q-. CD o o " —D C/D u tr O Z C7 y W D I I > z F p aJ 0 m p w I w � I - 0 0 0 a m 0 - I rC G 0000 w w OFD o 8= a U z p= Fy- w DC C3 w Q I � � o � CD � o � � � o u O Z C7 W 0 0 0 0 0 0 O c0 O LP L(1 V«j c0 1� n Le m V�n 0 , Z z K LL a Z° J w a V a Q S Y N LL V ADO wo 5z m G Z Z J QzO O (D Y d N m H Q O m Z- :�E (Dpi puF a z � E - U00 Oao QZ F } p ZOZ � cV ° J Z V J p Q Y Y of } wv vaC� T N ° Op � zOz< 00onz p � �a w oz z z Z m F m p Z Z o W p p w p a Q N N w O ° O �0Z � Q �� zVJV voo � Q � CD � ° ® � S J� QZnZu 0o in <no H 0 � � � pwp � in a - G �, oaNcDv � vNQ O LL O ,,, p � Z z� O p O ale 0o �pv UZ W � Ly- CD O W � LL U _" z 21 CD ® w; U I � Q m - �-�--� 0 u 00 Q Q� Q cn z W 0 CD C CDS 0 Q � 0 0 N 0 N O 0 0 u O Z C7 EO D Vj ti cp I a / m � or Q w c/D I w C� U I o � o 8a F �. � LLO I Z m CD cn o � � z U -� -- - - - - - - Lw o � mG o � � F- Q � n CD ^ o N O 0 0 u O Z C7 0000000 o c� c� H 000000n n r� r� � w 000000n n co co c7 � � rn �vrnov v o o o z z d Z Z d a Ov0J ON >N ~ F(D z N Z 0 N o w � zOo w � J z zpmzm z a > O o00Z0 LL Zv~iz w zN 0J > V Q � o)oZrpz 0z t < o O Oo LL Q O OZ�az a 0a < amain 5 <n N o tx Cl�Din � � � o�wwo � � � G 0oo � � N o oa ��� zu s _ ❑❑❑❑li❑❑ rr- �J 3 zIC w e e o a — o LL z Em ' see o Q CL F1 F-I L I 0. U W � o ® ® -- 15 - -- U z D0 Q 0 00o i--�--i o, z CD I O � c Q � c\ � ola � 0 " w�= o o " —D C/D u O Z C7 EO D Cb AM � o D D F F r UIQ � wz (9 U Q >— w v I � � UC3 c � - - � � C/D CD c f� z o � � F- Q � n o ^ o c� � CD —DC/Do