6.0. SR 06-28-1999
rei ---\)
( );
~l}{
Item 6.
River
MEMORANDUM
TO:
Mayor & City Council
FROM:
Alice Heinecke, Executive Secretary
DATE:
June 24, 1999
SUBJECT: Capital Improvement Program
The CIP was delivered on Wednesday, June 23,1999, in order to provide
more time for your review of the document. Please remember to bring your
copy of the CIP to the June 28, 1999, City Council meeting.
.
.
13065 Orono Parkway · P.O. Box 490 · Elk River, MN 55330. TDD & Phone: (612) 441-7420 · Fax: (612) 441-7425
.
.
.
Item 6.
Howard R. Green Company
CONSULTING ENGINEERS
June 23, 1999
File: 230000m
Mr. Pat Klaers
City Administrator
City of Elk River
P.O. Box 490
Elk River, Minnesota 55330-0490
RE: STATUS OF CURRENT PROJECTS
Dear Mr. Klaers:
As you requested, this letter is intended to give you the current status of projects we are working
on. They are as follows:
1.
East Elk River Utility Improvements
SR Weidema, Inc. is the Contractor for this project. The project has been underway for
about two months. The Contractor has worked primarily in the area of Elk River Crossing
and Vandenberg Industrial Site. The lift station is approximately half built. The deep
sewer is approaching the northerly Brown property line. The second crew is working on
watermain currently in the CSAH 13 area. All of the easements for the sewer and water
have been acquired. Evergreen Land Services is still working on right-of-way acquisition
from three properties north of County Road 12.
Construction on this project is anticipated to go late into the fall of 1999 and then
continue into the summer of 2000 prior to completion. The Contractor is obligated to
have sewer and water available by this fall for Elk River Crossing, Trott Brook Farms,
and the Vandenberg Industrial Development.
2. East Elk River Street and Storm Sewer Project.
Plans and specifications are 85% complete. At this point in time, we are waiting for the
right-of-way acquisition to be completed. Plans cannot be submitted and approved by
Mn/DOT until land acquisition has been completed and all of the right-of-way necessary
for the project is in control of the City. We anticipate that those acquisition issues will be
complete sometime late this summer. Plans will be submitted and reviewed by Mn/DOT
in that time frame. We would hope to have the project bid by early fall and under
construction this year. The contractor on this project could proceed on much of the storm
sewer and dirt work this fall. The actual street construction will continue on through the
construction season of the year 2000.
O:\PROJ\230000M\OOO-2302.june99.doc
1326 Energy Park Drive. St. Paul, MN 55108 . 651/644-4389 fax651/644-9446 toll free 888/368-4389
.
.
.
Mr. Pat Klaers
June 23, 1999
Page Two
3. CSAH 12 Reconstruction
This project is an undertaking by Sherburne County to upgrade CSAH 12 from CSAH 13
to the east City limits. As you are aware, we prepared the plans and specifications for
this project. These plans and specifications were complete some time ago. Right now
the County is actively pursuing land acquisition necessary to upgrade the road. This
project also has federal dollars involved in it. The federal paperwork was just recently
approved by MnDOT. Given that some of the land acquisition issues will undoubtedly
require condemnation proceedings, I believe that the project will not be let until late fall
with the majority of the construction taking place in calendar year 2000.
It is important to note that as this project proceeds along with our Tyler Street project, it
will be important to coordinate the two projects in an attempt to minimize disruptions and
detours for the eastern part of the City of Elk River.
4.
Trunk Highway 169 Pedestrian Bridge
This project again is federally funded. The plans and specifications have recently been
approved by MnDOT and an August 3, 1999, bid date has been set. Because of the
federal dollars involved in the project, MnDOT will be responsible for bidding the project
and awarding the contract. Bids will be opened at City Hall, the City Council will be
asked to pass a resolution, recommending to MnDOT, award of the contract to the
lowest responsible bidder. We anticipated it will take MnDOT approximately 30 days to
do the necessary contract paperwork to award this project. Therefore, the project will
begin construction sometime in early September and be built through the October -
November timeframe.
5.
School Street Improvement
This project consists of the widening of School Street to four lanes from just east of
Jackson Avenue to Proctor Avenue. It also includes construction of a six-foot wide
concrete sidewalk along the entire south side of School Street. The project was started
the week of June 14. Thus far the contractor has subcut for widening and is currently
moving hydrants and catchbasins. It is a relatively small project and should be easily
completed before the fall school session begins.
6. Trunk Highway 10/171st Avenue Signalization Improvement
This project is under construction. Currently, the Contractor has placed the bases and
the wiring for the new signal system. The minor geometric improvements are being
constructed. These include closing one of the driveways at Houle Oil Company and
constructing a concrete median on 171 st Avenue. Anticipated completion date for the
signal is the first part of July.
O:\PROJ\230000M\OOO-2302.june99.doc
Howard R. Green Company
CONSULTING ENGINEERS
.
.
.
Mr. Pat Klaers
June 23, 1999
Page Three
7. EVP/LED Signal Improvements
This project consisted of installing emergency vehicle preemption equipment at all of the
signals in the City. At the same time, the bulbs on all of the signals were replaced with
LED bulbs, which burn brighter and much longer, making them far more energy efficient.
All of the work under contract on this project has been completed. The project has not
been finalled out at this time. The emergency vehicle preemption systems need to be
turned on by MnDOT. This has not happened at this time. We anticipate that these will
be operational within the next several weeks. At that time the project can be finalled.
This project was done under a cooperative agreement with MnDOT. They are funding
approximately half of the project cost. Once the project is tinalled with the Contractor;
paperwork can be completed to receive the MnDOT reimbursement.
8. 175th Street Improvements
It is anticipated this project will receive some federal funding in FY 2002. We are
proceeding with plans and preparing right-of-way documents so the City can start the
land acquisition. It is very likely that if the City is ready to proceed with this project, it can
be moved up in the funding cycle to next summer.
9.
Dodge Avenue
After the east Elk River improvement is complete, the only road in this general area that
will have not been upgraded to a concrete curb and gutter urban section, will be the
south end of Dodge Avenue. The northern end of Dodge Avenue was upgraded several
years ago. This project is currently being preliminarily designed, anticipating that the
major landowner along the stretch of roadway will submit a petition to undertake this
project in the year 2000.
10. CSAH No. 1 I County Road 77 Signalization
I have recently discussed this issue with Rhonda Lewis, Assistant County Engineer.
She informed me their consultant had completed the traffic counts and would have an
updated warrant study for this intersection within a week. Hopefully, it will be available
before Monday night's City Council meeting.
O:\PROJ\230000M\OOO-2302.june99.doc
Howard R. Green Company
CONSULTING ENGINEERS
.
.
.
Mr. Pat Klaers
June 23, 1999
Page Four
11. County Road 33/ County Road 77
This is the project through the mining area of the City of Elk River. The City has helped
to facilitate meetings between the County, City, and the two gravel mine operators. The
last indication we had was that Tiller Corporation, one of the gravel mining operators,
would be getting back to the county sometime during the summer of 1999, to inform
them of their plans for restoration of the gravel mine. This will put the ball in motion for
planning and constructing of the new roadbeds and new road alignment. City staff will
continue to monitor this situation and help to facilitate the meetings. We believe,
because it is two county roads, that the cost of the improvements should be born by the
county and the benefiting property owners, being the two mining operators.
12.
Business Center Drive / Waco Street
This would be the Western Area Phase 4 improvement through the Stewart Wilson
property. MnDOT has programmed cooperative agreement money, for fiscal year 2000,
to help fund the frontage road and the signalization of Waco Street and TH1 O. Recently,
city staff has met with Stewart Wilson to discuss the road alignment through his property.
This improvement would consist of extending Business Center Drive to Waco; realigning
Waco Street to east of the small wetland, so that it will allow stacking distance on the
north side of Trunk Highway 10; signalizing the new intersection of Waco and Trunk
Highway 10; and closing the median cross over and access at the Government Center.
This project could be put on a fast track and constructed in the year 2000, but more
realistically, given the MnDOT plan approval and agreements that need to be worked
out, it will be a 2001 project.
13.
County Road 33 / Trunk Highway 169 Signalization
Some 18 months ago, the City Council asked the county to look at the warrants for
signal at the intersection of County Road 33 and Trunk Highway 169. The concern here
is the large number of gravel mining trucks that need to access the highway at this
intersection, and the potential they cause for accidents. The county turned to MnDOT to
have them perform the warrant study. I have recently talked to Gary Dirlam, District 3
Traffic Engineer, to inquire on the status of this. He recalled the counts being done, but
did not recall what the outcome of those counts were. I have asked him to pull his file
and get back to me with the current status. This is something I also hope to have by
Monday evening's meeting.
14. Miscellaneous Trails
We are currently working on two trail projects. One, being along the north side of Trunk
Highway 10 from Upland Avenue to the main entrance of the Cretex plant. This is the
portion of frontage road that was removed last year with the Upland Avenue intersection
improvement. The other trail project that we are working on is paving of the railroad trail.
O:\PROJ\230000M\OOO-2302.june99.doc
Howard R. Green Company
CONSULTING ENGINEERS
.
.
.
Mr. Pat Klaers
June 23, 1999
Page Five
15. Trott Brook Farms
This is the approximately 630-unit residential development located on the Schultz
property north of County Road 12. We are currently reviewing the final construction
plans for the first phase of that improvement. The first phase includes the four plats
recently approved by the City Council. We anticipate that the Developer will be
submitting final utility and street plans and specifications within the next month. The
Developer has indicated he will be proceeding with the final platting of the first phase in
June.
16. Elk River Crossing
This is the commercial development on the Earl Hohlen property. Recently, the City
Council gave preliminary plat approval to this project. The City is in the process of
acquiring two private pieces of property to facilitate this project. Until these acquisitions
are complete, we do not anticipate the project to proceed onto final plat. It is anticipated
that the Developers will start the mass grading of this project sometime in the late
summer or early fall of 1999, followed immediately by utility and street construction and
the initiation of the building for the first major tenant in the development.
17.
Vandenberg Industrial Development
This is the development of the 40-acre industrial site just south of Elk River Crossing.
This project received preliminary plat approval some time ago. We have been meeting
with the Developer to coordinate the timing of the final plat, internal improvements, and
the start of the first building. From our latest meeting, it appears that a building could be
started in the early summer of 2000, anticipating that the building would be ready for
occupancy by winter as well as the public improvements and streets necessary to
service the building.
18. Lafayette Woods Third Addition
This project is the three small cul-de-sacs in the Lafayette Woods Development. The
Developer put in the sewer and water earlier this spring. It is now waiting for street
construction. We recently approved the final development plan on this project and
started to issue building permits.
19. Cherrywood Hills Second Addition
This is the development that is just southeast of Lafayette Woods. The Developer has
initiated construction on the second addition, which will complete that project. The
Contractor is currently completing the streets. We anticipate that it will be a few weeks
before the project is complete and ready for building permits.
O:\PROJ\230000M\OOO-2302.june99.doc
Howard R. Green Company
CONSULTING ENGINEERS
.
.
.
Mr. Pat Klaers
June 23, 1999
Page Six
20. Hillside Estates Ninth Addition
This portion of the project is located in the southeast corner of the Hillside Estates Area.
The Developer has received preliminary plat approval and we anticipate he will proceed
to construction on a portion of the area, trying to get buildable lots in the 1999
construction season.
If you have questions regarding any of these projects please call.
Sincerely,
Howard R. Green Company
,::::; , ,,().4V:.
~/''7Q;~~
Terry J. -~~er, P.E.
TJM:djw
O:\PROJ\230000M\OOO-2302.june99.doc
Howard R. Green Company
CONSULTING ENGINEERS