8.1. SR 11-20-2017 EOty1� ,.,�� Request for Action River To Item Number Mayor and City Council 8.1 Agenda Section Meeting Date Prepared by General Business November 20, 2017 Justin Femrite P.E., City Engineer Item Description Reviewed by Select Construction Manager for the Ice Arena and Cal Portner, City Administrator Lion John Weicht Park Improvement Project Reviewed by Michael Hecker, Park and Recreation Director Action Requested Approve,by motion, entering into a contract with RJM Construction for Construction Management Services on the Ice Arena and Lion John Weicht Park Improvement project. Background/Discussion With direction from Council, staff prepared and advertised a request seeking proposals for construction management services. Seven proposals were submitted and reviewed by the Ice Arena Committee. The proposals were reviewed against the scoring criteria laid out in the RFP. From this scoring, staff members of the committee interviewed the top three ranked firms. These firms included RJM Construction,Kraus-Anderson, and Terra General Contractors. Upon review of the proposals and completion of the interviews, the Committee recommends the Council approve entering into a contract with RJM Construction. Their proposal is attached. RJM brings the most experienced team to our project along with some unique ides to consider during the schematic design phase. There proposed fee was also the most competitive of all proposals received. We further recommend following the proposed model of hiring RJM Construction as a Construction Manager at Risk as detailed in the proposal. If approved,we will work with our legal counsel to draft the contract with RJM Construction. Financial Impact The proposed fee for this service contract is $735,752. This amount has been planned for and included in the overall project budget which remains estimated in the $20M to $25M range. Part of brining the construction manager on board at this time is to assist in refining the project estimates and determining where project costs can be minimized as we move into final design. Attachments ■ RJM Construction's Proposal The Elk River Vision A PehoMing community 2a itb revolutionary and spirited resourcefulness, exceptional POWERED By service, and community engagement that encourages and inspires prosperity INAMIRE1 Elk River Ice Arena & Lion John Weicht Park Facilities November 7, 2017 830 Boone Avenue North Golden Valley, Minnesota 55427 952-837-8600 RJMConstruction.com November 7, 2017 Mr. Justin Femrite, PE, City Engineer City of Elk River, City Hall 13065 Orono Parkway Elk River, MN 55330 Re: Elk River Ice Arena and Lion John Weicht Park Facilities Dear Mr. Femrite, RJM Construction is pleased to present our response to the request for proposal for the Elk River Ice Arena and Lion John Weicht Park Facilities. We value our relationship with the City of Elk River and are excited to continue our commitment as your construction management partner. Your requirements for this project demand the expertise and value we can provide: • Ice Arena Specialists: RJM has completed dozens of ice arenas, over 13 alone with 292 Design Group and Stevens Engineers. Our most recent example is a two-sheet facility for the City of Shakopee. We are pleased to propose the exact same RJM team from the Shakopee project. There is no learning curve with RJM as your partner. • Extensive CM Experience: RJM has worked with over 19 municipalities on construction management projects, including two projects with the City of Elk River. Our team includes senior leadership that will guide you through the process from design through post-construction. • Project Understanding: Over the past ten years we have assisted the City of Elk River through 292 Design Group with cost estimating, constructability reviews and various scheduling scenarios for this project. We are ready to make an immediate impact! • Proven Value: We are committed to developing an innovative project approach. We will establish accurate budgets, provide valuable cost savings options, and guide the team in making smart, effective decisions – all while maintaining your goal of limiting disruption to neighboring schools and maximizing programming at both the ice arena and park facilities. We stand ready to begin work immediately with your team on this exciting project for the City of Elk River community. Sincerely, Brian Recker President 952-837-8636 brian.recker@rjmconstruction.com 2 TABLE OF CONTENTS:Part I: Business Organization & History Part II: Team Identification Part III: Key Qualifications & Approach Part IV: Project Examples, Supplemental Information Part V: Cost Proposal Exhibits Elk River Ice Arena and Lion John Weicht Park Facilities 3 Part I: Business Organization & History Elk River Ice Arena and Lion John Weicht Park Facilities 4 A) Firm History RJM Construction was founded on a simple principle - to serve the client. Led by our team of construction professionals, our project delivery process is designed to ensure that our clients have a productive, rewarding project experience. Our clients appreciate that they can count on the RJM team to always put their interests first. Our commitment to our clients’ vision is supported by construction expertise on a wide variety of projects for community leaders, property owners, health care professionals and building tenants. We are dedicated to providing leadership and value enhancing insights to every construction project. With our headquarters in Golden Valley, Minnesota, RJM Construction LLC was established in 1981 and is owned by industry veterans Robert Jossart, Joe Maddy, Brian Recker and Ted Beckman. Today, RJM has more than 150 specialized staff members and annual construction volume of $250 million. Construction Management Services RJM Construction is an industry leader in delivering construction management services. Over the past ten years our team has delivered Construction Manager at Risk services (CMar), and for the past 18 years, Construction Manager Advisor (CMa) services to municipalities throughout the Twin Cities metro region. We are especially proud of our work with the City of Elk River, starting with the Elk River Community Center YMCA, and most recently your Public Works Facility. Our greatest compliment is when a client chooses to partner with us on a repeat basis. Part I: Business Organization & CM History Elk River Ice Arena and Lion John Weicht Park Facilities Driven by your vision It starts with your idea and grows into a vision. At RJM Construction, we first gain an understanding of your needs. Then we develop a strategy to help you capture your vision. With insightful planning, a collaborative spirit and fiscal responsibility, we bring your vision to life. BRAND Driven by your vision RJM has partnered with many municipalities throughout the Twin Cities metropolitan area. 5 B) Other Services As one of the largest contractors in the Twin Cities, RJM focuses on three primary markets: community, healthcare and corporate. Our success has always relied on strategic partnerships, so clients can expect us to be collaborative and responsive throughout all phases of the building process. Whether it’s new construction or a renovation, we provide construction solutions that meet your needs. Our services include a range of offerings in general contracting, construction management, design/build and pre-construction planning that can be easily tailored for your project. Both public and private clients have hired us directly to perform mechanical commissioning as well as existing building condition assessments. Architects continuously hire us for constructability reviews, cost consulting, and project scheduling. 292 Design Group has engaged us on this project multiple times over the past ten years. Elk River Ice Arena and Lion John Weicht Park Facilities Part I: Business Organization & CM History 6 Part I: Business Organization & CM History Elk River Ice Arena and Lion John Weicht Park Facilities Project Examples There is no substitute for experience. RJM understands how to work in collaboration with all stakeholders to effectively plan and execute the complex project requirements. Our experience gives the City of Elk River the assurance that RJM is a reliable, qualified partner. The table below illustrates the projects that are CMar and CMa, as well as ice arena projects. Project Name Ice 292 Design Stevens Eng. CMar CMa City of Andover YMCA / Community Center X X X City of Chanhassen Public Works X City of Chaska Community Center Aquatics X City of Chaska Lodge Addition X City of Chaska Wellness Center X City of Coon Rapids Ice Arena*X X City of Eden Prairie Aquatic Center*X City of Eden Prairie Community Center & Ice Arena X X X City of Edina Braemar Golf Dome*X City of Edina Braemar Hornet’s Nest Addition*X City of Edina Braemar Sports Dome*X City of Edina Pamela Park*X City of Elk River Community Center / YMCA X City of Elk River Public Works*X X City of Hopkins Pavilion Ice Arena**X X X X City of Inver Grove Heights Community Center X X City of Maple Grove Central Park*X X City of Maple Grove Community Center & Ice Arena X X X X City of Maple Grove Gymnasium*X City of Maple Grove Sports Dome*X City of Maple Grove Town Green Bandshell*X City of Medina Public Works / Police Station*X X City of Plymouth Ice Center X X X X City of Plymouth Ice Training Center*X X X City of Red Wing Ice Arena X X X X City of Rogers Ice Arena X X X X City of Rogers Police Station X City of St. Louis Park Recreation Outdoor Center & Ice Arena*X X X City of St. Louis Park Westwood Hills Nature Center**X City of Shakopee Community Center / Ice Arena*X X X X City of Shoreview Community Center Expansion (under construction)* X City of Woodbury Public Works*X City of Worthington Community Center / YMCA X Ice Den Phoenix Coyotes, Scottsdale, AZ*X X X St. Thomas Ice Arena X *Indicates projects within the last five years. **In preconstruction. 7 Part I: Business Organization & CM History Elk River Ice Arena and Lion John Weicht Park Facilities Project References RJM is pleased to provide the following contact information and letter of recommendation as references for the City of Elk River. City of Shakopee Jamie Polley 952-233-9514 City of St. Louis Park Cindy Walsh 952-924-2541 City of Eden Prairie Jay Lotthammer 952-949-8441 City of Maple Grove Chuck Stifter 763-494-6000 292 Design Group Tom Betti 612-767-3773 St. Paul Port Authority Lee Krueger 651-204-6226 1 Mindy Bohumolski From:Mindy Bohumolski Sent:Monday, October 09, 2017 10:11 PM To:Mindy Bohumolski Subject:RE: Letter of Recommendation     From: Jamie Polley [mailto:JPolley@ShakopeeMN.gov]   Sent: Friday, October 6, 2017 5:12 PM  To: Brian Recker <brian.recker@rjmconstruction.com>  Subject: RE: A favor....    Brian,  Here are a few words…    To Whom it May Concern,  RJM was the Construction Manager on the City of Shakopee’s Community Center renovation and Ice Arena Construction  project. I have worked closely with Mike Seigley and Tara Blotske over the past 18 months. It has been a great  experience.     Tara was an advocate for the City throughout the entire project. She had the hard conversations with the trades and  stood up for the City when questions needed to be asked. She managed the budget very closely and communicated any  changes immediately. Mike is a great superintendent and kept all the different trades on task and on time. He was  reliable and made sure the finished project was what the city expected. He managed a very difficult phased project with  the ability to see the small items before they became a problem.     RJM managed the project with the City’s expectations and best interests always at the forefront. It was a pleasure  working with RJM and I would recommend them to other organizations completing a Community Center or Ice Arena  project.     Please feel free to contact me with any questions.    Sincerely,      Jamie Polley  Director of Parks & Recreation, City of Shakopee  1255 Fuller St. S., Shakopee MN 55379  952‐233‐9514 | www.ShakopeeMN.gov  Follow us on: Facebook | Twitter | YouTube    From: Brian Recker [mailto:brian.recker@rjmconstruction.com]   Sent: Friday, October 6, 2017 8:03 AM  To: Jamie Polley <JPolley@ShakopeeMN.gov>  Subject: A favor....    Good morning Jamie,  Letter of Recommendation 8 Part II: Team Identification Elk River Ice Arena and Lion John Weicht Park Facilities 9 Part II: Team Identification Key Staff RJM Construction is fortunate to introduce a skilled and experienced team for the Elk River Ice Arena and Lion John Weicht Park Facilities project. The team is comprised of project leadership, support, and coordination roles. In tandem, these groups will act as an extension of the City of Elk River staff and flawlessly execute the project. This allows your team to focus on your community. We are pleased to propose the exact team that recently completed the City of Shakopee Ice Arena project with 292 Design Group. The team includes the direct involvement of senior leadership including Brian Recker and Ted Beckman, who also led the Elk River Public Works project with 292 Design Group. Elk River Ice Arena and Lion John Weicht Park Facilities PRE-CONSTRUCTION PRINCIPAL Ted Beckman PROJECT OVERSIGHT Brian Recker PROJECT MANAGER Tara Blotske Quality Control Manager Mike Johnson General Superintendent Tom Carlson Safety Director John Boben SUPERINTENDENT Mike Seigley MEP Director Jed Field Chief Estimator Justin Johnson Project Scheduler Thomas Hussong BIM Specialist Jake Fisher 10 Experience City of Andover Community Center / YMCA Andover, Minnesota City of Eden Prairie Community Center & Ice Arena Eden Prairie, Minnesota City of Shakopee Ice Arena Shakopee, Minnesota City of Coon Rapids Ice Arena Coon Rapids, Minnesota City of Elk River Public Works Elk River, Minnesota City of Maple Grove Ice Arena Maple Grove, Minnesota City of Maple Grove Central Park Maple Grove, Minnesota City of St. Louis Park Ice Arena St. Louis Park, Minnesota Education Bachelor of Science Degree Civil Engineering University of Minnesota Masters in Business Administration U of M, Carlson School of Management Client References Mr. Justin Femrite City of Elk River 763-635-1051 Ms. Jamie Polley City of Shakopee 952-233-9514 Mr. Jay Lotthammer City of Eden Prairie 952-949-8440 Architect Reference Mr. Mark Wentzell 292 Design Group 612-767-3773 Mr. Ed Kodet Kodet Architecture 612-377-2737 Mr. Greg Fenton BWBR Architects 651-290-1877 Brian Recker President brian.recker@rjmconstruction.com 952-837-8636 Brian Recker has been in the commercial construction industry for 25 years. Since that time, he has worked as a project manager, estimator, senior vice president, and his current role as president. In his 15 years with RJM, Brian has managed a variety of municipal projects including ice arenas, aquatic facilities, fitness centers, outdoor spaces and community facilities. Brian is RJM’s expert in delivering Construction Management contracts, providing these services for both public and private entities. Similar to the City of Elk River Public Works project, Brian will oversee the experienced project team and work directly with Ted Beckman and Tara Blotske from preconstruction through to project completion. Part II: Team Identification Elk River Ice Arena and Lion John Weicht Park Facilities 11 Ted Beckman, LEED AP BD+C Senior Vice President ted.beckman@rjmconstruction.com 952-837-8615 Ted Beckman grew up in the trades as a homebuilder, and has held various positions in pre-construction for over 15 years. Ted’s consistent track record of helping create a feasible project vision is appreciated by clients ranging from property owners, to building tenants, healthcare professionals and community leaders. Beyond his conceptual estimating ability, Ted brings a relationship-focused approach to construction projects. His friendly demeanor and collaborative spirit is reflected in ongoing partnerships with clients and subcontractors alike. As he did for the City of Elk River Public Works project, Ted will oversee the entire preconstruction design phase. His team provides estimating, building information modeling (BIM), project scheduling, and mechanical, electrical, plumbing (MEP) coordination on complex projects. As a LEED Accredited Professional, Ted can provide insight to green building concepts and project certification. His familiarity with the evaluation of the LEED process will help the team strike a balance between sustainability goals and best value costs. Experience City of Elk River Public Works Elk River, Minnesota City of Shakopee Ice Arena Shakopee, Minnesota City of St. Louis Park Ice Arena St. Louis Park, Minnesota City of Coon Rapids Ice Arena Coon Rapids, Minnesota City of Maple Grove Ice Arena Maple Grove, Minnesota City of Maple Grove Central Park Maple Grove, Minnesota TRIA Rink St. Paul, Minnesota Education Bachelor of Science Degree Construction Management University of Wisconsin - Stout Client Reference Mr. Chuck Stifter City of Maple Grove 763-494-6000 Ms. Jamie Polley City of Shakopee 952-233-9514 Ms. Cindy Walsh City of St. Louis Park 952-924-2541 Architect Reference Mr. Tom Betti 292 Design Group 612-767-3773 Mr. Victor Pechaty HGA Architects 612-758-4000 Mr. Greg Fenton BWBR Architects 651-290-1877 Part II: Team Identification Elk River Ice Arena and Lion John Weicht Park Facilities 12 Part II: Team Identification Elk River Ice Arena and Lion John Weicht Park Facilities Tara Blotske Project Manager tara.blotske@rjmconstruction.com 952-893-8248 Tara has been in the construction industry for 13 years. She has held positions in pre-construction and project management, on a variety of project types. Tara’s experience has led her to an in-depth understanding of the construction manager delivery process. This unique background ensures your project will be organized, coordinated and delivered in accordance with all local and state bid procurement statutes. As project manager, Tara will manage the overall construction process by developing schedules, tracking submittals, processing RFI’s and coordinating with subcontractors. She provides valuable project assistance in all areas of information management, always keeping the client informed of project status. Tara manages her projects with a simple and straightforward approach. She thrives in team settings and enjoys sharing her experiences and knowledge by mentoring her younger colleagues. Experience City of Shakopee Ice Arena & Community Center City of Eden Prairie Aquatics Center City of Edina Pamela Park City of Maple Grove Ice Maintenance Building City of Eden Prairie Miracle Field City of St. Louis Park Ice Arena & Recreation Outdoor Center Hmong Academy Phase IV Charter School St. Paul Education Bachelor of Science Interior Design & Construction Management Minnesota State University, Mankato Client Reference Cindy Walsh City of St. Louis Park 952-924-2541 Ms. Jamie Polley City of Shakopee 952-233-9514 Mr. Chuck Stifter City of Maple Grove 763-494-6000 Architect Reference Mr. Paul Crosland HGA 612.758.4207 Ms. Michelle Maiers 292 Design Group 612-767-3773 Ms. Teri Nagel Kodet Architectural Group 612-377-2737 13 Part II: Team Identification Elk River Ice Arena and Lion John Weicht Park Facilities Experience City of Shakopee Ice Arena & Community Center Phoenix Coyotes Ice Den Scottsdale, Arizona City of Andover Community Center & Ice Arena City of Eden Prairie Community Center & Ice Arena City of Rogers Ice Arena City of Coon Rapids Ice Arena City of Maple Grove Ice Arena Expansion Hmong Academy Phase IV Charter School St. Paul Education Carpenter’s Local Union #851 Member since 1977 Mike Seigley Superintendent mike.seigley@rjmconstruction.com 952-837-8600 Mike Seigley began his construction career in 1978 as an apprentice and quickly worked his way up to the position of superintendent. Mike’s experience and personal commitment will deliver a quality construction project. He is a valuable member and resource to any project team. As superintendent, Mike will play a vital role in ensuring the completed project exceeds the established goals. In addition, his experience working in a functioning facility environment is a real asset to ensuring a successful project for all stakeholders. Mike has supervised installation of ten ice sheets for RJM and his unique expertise will ensure the rink improvements will be executed flawlessly. Client Reference Mr. Jay Lotthammer City of Eden Prairie 952-949-8441 Ms. Jamie Polley City of Shakopee 952-233-9514 Mr. Chuck Stifter City of Maple Grove 763-494-6000 Architect Reference Ms. Michelle Maiers 292 Design Group 612-767-3773 Ms. Teri Nagel Kodet Architectural Group 612-377-2737 Mr. Tom Betti 292 Design Group 612-747-4330 14 Part II: Team Identification Elk River Ice Arena and Lion John Weicht Park Facilities Project Availability We have evaluated the workloads for our team members and they have the resources, capacity and commitment needed to effectively complete the pre- construction and construction schedule without any conflicts. Brian Recker will oversee all phases of the project. Ted Beckman will lead the pre-construction phase in its entirety. Tara Blotske, project manager, will lead the construction phase. Tara will be working on one other project, and Mike Seigley, RJM’s superintendent, will be dedicated to the project full time. Hours assigned have been included as part of Part V: Cost Proposal. RJM Construcion staff always provide the City with accurate, well thought out cost estimates, construction timelines and communication models. Alan Madsen Administrator (retired) City of Maple Grove “ “ 15 Part III: Key Qualifications & Approach Elk River Ice Arena and Lion John Weicht Park Facilities 16 Why RJM Construction? RJM considers ourselves an extension of the City of Elk River staff. We understand the project needs from both a function and an aesthetic perspective. Through this leveled approach, RJM will foster a spirit of collaboration with the project team in meeting schedule and budget needs, while creating a facility that will serve the community for years to come. RJM brings leadership and provides value-based solutions whenever needed. Our experienced staff anticipates what lies ahead and strives to protect your interests. Our team keeps the project moving forward and true to your vision. Project Understanding With RJM’s significant history of preconstruction work on the Elk River Ice Arena and Lion John Weicht Park Facilities we know how to make your vision a reality. Since 2007, RJM has assisted 292 Design Group and JLG Architects with cost estimating, scheduling, construction sequencing and value engineering. Through these partners we have provided the City of Elk River our expertise in the decision to renovate, build new, or relocate sites. The current plan incorporates and balances the best ideas presented during this preconstruction phase and we are excited to be your project partner. With the addition of the Lion John Weicht Park Facilities, the City of Elk River can further count on RJM’s experience and smooth project execution. We have worked with several municipalities on both sports fields and park pavilion facilities. We know that maintaining operations during construction—including access to all facilities—holds equal importance to successful project completion. Our understanding of the project phasing, including the shared parking lot and school land deed process, will be paramount in developing a comprehensive project schedule. Ice Arena Experience RJM has extensive experience working on ice arena projects, and we know how to skillfully lead the team. Ice arenas are specialized facilities that must withstand extreme climate fluctuations. In Minnesota, this is especially important during the summer months. We understand the key components that require careful consideration in the design and construction of the building envelope including: • Proper roofing material and insulation to limit condensation • Under-slab vapor barrier selection and placement to avoid concrete curling • Dehumidification manufacturers and system balancing to maximize efficiency and performance Of equal importance is the performance of the ice plant and playing surface to make for an enjoyable and competition-level experience for both athletes and spectators. RJM has also completed many system replacements and refrigeration updates. Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach RJM handled this project with outstanding service and delivery.  They thought of every detail, providing outstanding communication and delivery of the work as if we were their only client.  We appreciate the outstanding service. Ann Bourg Cushman & Wakefield “ “ 17 As with the building envelope, there are many key elements that require specialized expertise: • Planning the sequencing of refrigeration system installation to ensure continuous use during switchover • Analyzing the use of waste-heat by utilizing for snow-melt and other potential efficiencies • Selection and placement of rink lighting to ensure competition-level quality and enjoyment for spectators A large-capacity rink such as the City of Elk River’s proposed facility will require careful planning when selecting and designing the mechanical equipment. As we did with the Shakopee Ice Arena project, RJM will work closely with 292 Design Group engineers to ensure the highest quality design. Additionally, RJM will proactively manage the installation and balancing of these systems to provide the highest level of energy efficiency. Construction Manager Experience and Council Liaison RJM will bring its construction management expertise to the City of Elk River. Since 2007 we have worked with over 19 municipalities on CMa and CMar projects, with many hiring RJM on a repeat basis. When you engage our services we view our relationship as a partnership, working closely alongside City staff. Your RJM construction manager will act as an extension of your team. To achieve your project goals and successful outcomes we work as your advocate during design, approvals, construction and post-construction. Our team will guide City staff through the City Council process, including the scheduling of Council actions. We will develop supporting documentation and provide expertise at Council workshops, study sessions and official Council meetings. RJM understands what level of information is desired by Council and will stand by your side to present it. This approach keeps the Council informed and ensures timely project delivery. What makes RJM unique in the market is that we are builders that perform construction management. Many firms offer construction management but do not have the expertise to lead the design from a constructability standpoint. Our team knows how to build, and we will use that knowledge to ensure the Elk River Ice Arena and Lion John Weicht Park Facilties project is constructed to the highest quality level possible. Another aspect that makes RJM different is that while some construction managers attempt to enhance their fees by performing trade work on the project, we believe this creates a conflict of interest. We are your advocate and for this reason, we choose to not self-perform any of the bid packages. Experience with 292 Design Group RJM and 292 Design Group specialize in ice arena construction and our teams have worked together on 13 ice arena projects, the most recent being Shakopee Ice Arena. As demonstrated in our preliminary work on this project, we work collaboratively as a team. Because there is no learning curve between RJM and 292 Design Group, you can count on a smooth project delivery. Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach 18 Project Administration Pre-Construction Estimating Techniques The Elk River ice Arena and Lion John Weicht Park Facilties project construction budget is $20 million with a total project budget not to exceed $25 million. Budget is a driving concern in ensuring the best possible value is achieved. As the design progresses, we provide continual, real-time cost evaluations so that the cost impact to design choices are immediate. Being proactive in this process saves critical time and costs, helping the architect understand budget impacts before designs are complete. At the core of our pre-construction team is our staff of eight full-time estimators. This team ensures estimates are accurately completed in a timely fashion without the daily distractions of project management. Estimating is a continuous process for RJM Construction—as early as possible we will quantify work items and apply unit costs. We start with an overall conceptual budget, followed by a schematic design budget and a design development budget. The RJM Difference Our team also provides a final estimate at 95% completion of the design. The intent of this final estimate is to confirm the 95% drawings and specifications align with the budget and that we have 100% subcontractor support to prove it. This final confirmation allows us to accurately track where the final bids will be when received. Allowing one last opportunity to make slight adjustments to the plans prior to bidding assures the project will be delivered on budget. Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach RJM provides a final estimate at 95% completion of design. Estimates are provided continuously through design: conceptual schematic design design development 95% design 19 Value Engineering In our role as Construction Manager, we know it is our job to provide as many cost-saving ideas that are available for the team’s evaluation for implementation. From our experience with ice arena facilities we understand where costs can be reduced, without sacrificing the function of the building, or the vision and design intent of the client and architect. Historically our value engineering process has saved 9 - 13% in value between schematic design and construction document completion. For a large-scale project like the Elk River Ice Arena and Lion John Weicht Park Facilities, our experience can help the City reach potential cost savings in the range of $1.8 million to $2.6 million. Constructability Reviews At RJM we have a proactive mindset and we continuously seek ways to enhance design to arrive at the most efficient and highest quality installation. At each phase of design, RJM will engage our internal quality control team to review all aspects of design and make suggestions to 292 Design Group for minor design modifications. Offering these changes prior to bidding will facilitate more accurate bids from the contractors, making for a smooth installation and ultimately, a higher quality finished product. Building Information Modeling (BIM) RJM has the capability to develop three-dimensional models on projects to simulate the real world building process. Our BIM Specialist, Jake Fisher, collaborates with the entire project team, providing value in systems analysis and constructability reviews, enabling the team to make more informed decisions regarding the design, systems, efficiency and quality of a project. RJM used BIM for the Elk River Public Works project when laying out the equipment in the mechanics garage. We modeled the entire department and virtually laid out all power runs. This allowed the deparment heads to make adjustments prior to the commencement of work on-site. Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach TIMEOPPORTUNITYBest Opportunityto Maximize Value Pre-construction Phase SchematicDesign DesignDevelopment ConstructionDrawings Construction ProjectCloseout 90% of Value Captured During Pre-construction 20 Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach Mechanical, Electrical, Plumbing Design and Coordination (MEP) Specialized mechanical, electrical and plumbing systems require close attention. RJM’s Director of MEP Design and Coordination, Jed Field, will analyze the mechanical and electrical designs and act as a liaison between the design team and the contractors. A licensed engineer, Jed fully understands detailed mechanical and electrical scopes and can guide pre-fabrication and installation plans, ultimately resulting in efficiencies and increased cost savings. He has the ability to understand design intent and coordinate the prefabrication and installation plans which will ultimately result in efficiencies and increased cost savings. Development of Bid Packages RJM will work with City staff to place the bid advertisement in the City’s required publications such as Elk River Star News and others including Minneapolis and St. Paul Builders Exchange and The Dodge Report. In addition, RJM’s extensive experience in the ice arena market gives us a diverse list of subcontracting partners we can carefully analyze and tailor to meet the needs of the City of Elk River. We will reach out to qualified subcontractors by means of electronic notification, as well as personal phone calls, to generate as much interest as possible, increasing the number of received bids, and ensuring the lowest possible price on bid day. RJM has also developed a bidding strategy that can allow for more local contractor participation for smaller project work scopes through the City’s quote process. By breaking larger bid packages into smaller, more manageable ones we can often generate more interest from local contractors who may not have the capabilities to perform the entire large scope of work. RJM will facilitate the bid receipt and conduct the public opening process. Subsequently, RJM will conduct a thorough review of each bid for completeness, clarify any potential discrepancies, and conduct a scope review with all apparent low contractors. Recommendations are presented to the team along with a comprehensive project budget. In addition, RJM assists in obtaining approvals from regulatory agencies. After approval of the contractor awards, RJM will prepare and process the appropriate contracts. Scheduling Scheduling begins at project definition and identifies design, client planning, bidding and actual construction duration. RJM will support the project team with a comprehensive schedule taking into account all critical milestones. This will be a collaborative effort with the entire project team to ensure realistic expectations are set within efficient work sequences. RJM’s scheduler will prepare and issue master schedules, analysis and variance reports. Our team has outlined multiple options for the proposed sequence of events for the Elk River Ice Arena and Lion John Weicht Park Facilities project. This is based upon a combination of preliminary project information coupled with similar experience. 21 Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach RJM will work with the team to develop a project schedule that limits disruption to the school parking, ball fields, tennis courts and ice arena programming. An accurate schedule begins with a strong understanding of the project goals. Below we have identified some initial parameters and possible solutions for your project: 1. Limit school disruption both with noise and parking lot usage until end of 2017-2018 school year. • Off hours trucking • Start heavy work after school year ends 2. Maintain one sheet of ice programming for duration of project (minimal shutdowns). • Modify design of future shared refrigeration room so that existing Olympic plant can remain in use during construction • Temporary entrance through either NE or SE corner while new lobby is constructed • Possible temporary solution needed for existing snow-melt • Possible temporary team rooms and bathrooms depending on extent of phasing 3. New softball field ready for play at start of 2019 season. • Assuming sand and peat vs. turf, seeding complete in 2018 4. Extend use of tennis courts until end of 2017-2018 school year. • Depending on phasing all or at least two can remain useable until school lets out 5. Electrical utility relocation needed prior to new rink addition. • Confirm with Energy provider timing of relocation • Might make more sense to start Olympic renovations first while this work is happening Construction Construction projects within occupied facilities provide challenges that require an experienced construction manager. RJM specializes in the renovation of occupied facilities. This experience will guide the project team through proactive solutions: • Studies of existing conditions • Schedule development and phasing • Public egress • Systems operation and shutdowns • Communication with the public 22 Phasing Strategies There are at least five potential phasing strategies for the City of Elk River to consider, each with its own pros and cons. Below we have outlined some initial ideas for consideration. We welcome the opportunity to discuss these and other options in person. Strategy 1 Start Olympic renovation and begin demolition of Barn in March 2018. • New rink in September of 2018 season and full facility before end of 18/19 season. Strategy 2 Start Olympic renovation in March 2018 and begin demolition of Barn in June 2018. • New rink in September of 2018 season; full facility won’t be done until after 2018 season. Strategy 3 Start Olympic renovation in March 2018 and begin demolition of Barn in October 2018 • New rink in September of 2018 and maintain Barn ice; long schedule = higher cost. Strategy 4 Demolish Barn in June 2018 and renovate Olympic starting in February 2019 • New ice early 2019. Maintain Olympic ice during construction. Full facility done at end of 2018-2019 season. Strategy 5 Demolish entire facility starting in March 2018 and build new. • New rink in October/November 2018. All new facility. Fast schedule with efficient design. However, no ice until first sheet is available. As an example, a phasing plan for Strategy 1 is attached as an exhibit. Part III: Key Qualifications & Approach Elk River Ice Arena and Lion John Weicht Park Facilities After setting the expectations at the beginning of the project, RJM kept to the expectations and delivered a great project. Mike Seigley and Tara Blotske are a great team and kept a very close eye on the project and the budget. Jamie Polley City of Shakopee “ “ 23 Part III: Key Qualifications & Approach Based on a 10-month schedule we have assembled the following milestone schedule. The schedule and phasing certainly are open for discussion as we would very much welcome a conversation and a deeper dive into the details of your preferred plan. Elk River Ice Arena and Lion John Weicht Park Facilities Preconstruction Bid Pack 1 (Arena Precast) Bid Period (4 weeks)1/15/18 - 2/14/18 Bid Opening 2/15/2018 Review Bids with team 2/20/2018 Precast Procurement Start (14 Weeks)3/1/2018 Bid Pack 2 (Arena) Bid Period (4 weeks)2/2/18 - 3/1/18 Bid Opening 3/1/2018 Meet w/Team to Review Bids 3/8/2018 Bid Pack 3 (Park & Field) Bid Period (4 weeks)2/2/18 - 3/1/18 Bid Opening 3/1/2018 Meet w/Team to Review Bids 3/8/2018 Construction (Arena) Olympic Rink Close 3/15/2018 Olympic Rink Renovation Start Demolition 3/15/2018 Demo Complete-Start Rink Renovation 4/16/2018 Rink Renovation Completion 9/15/2018 Barn Mobilization/Demo/Foundations 3/15/18 - 6/1/18 Precast/Structural Steel 6/1/18 - 7/15/18 Roofing Complete 8/15/2018 Ready for Refrigeration Equipment 10/1/2018 Ready to Make Ice-Rink Addition 1/15/2019 Substantial Completion - Rink Addition 2/1/2019 Construction (Park & Field) Construction Start 5/15/2018 Pavilion & Field Construction 5/15/18 - 10/15/18 Field Ready for Play Spring 2019 A detailed construction schedule is attached as an exhibit. 24 On-Site Management RJM will provide full-time on-site supervision for all work. Our highest priority on the project is to provide and maintain a safe working environment for everyone on site. We understand that monitoring the quality of work daily is in the best interest of everyone and RJM takes this responsibility seriously. Project Safety RJM’s superintendent closely monitors work of the contractors ensuring safety procedures are being followed. RJM Construction has been recognized by the Minnesota Department of Labor and Industry and AGC of Minnesota as a Construction Health and Safety Excellence (CHASE) partner. The CHASE partnership charter acknowledges the importance of providing a safe, healthful work environment in construction and seeks a working relationship that creates mutual trust and respect among all parties, including project owners and construction workers, involved in the construction process. Schedule Control RJM’s scheduler, Thomas Hussong, will review all contracts for specific scheduling needs and profile critical time lines. The master schedule is updated regularly, with an eye always on the overall completion date. We also provide three week projection schedules that provide a breakdown of current project tasks, which are utilized in the management of the contractors and vendors. These tools will be used when coordinating work sequencing to ensure materials and labor arrive as scheduled. Subcontractors will be held accountable to meet these schedules as they will be developed early as a tool to use when awarding subcontracts. A low-cost subcontractor is only qualified if they can meet the project milestones. Cost Control During construction we diligently manage the project budget and contingency. At each project meeting we will provide an updated budget so everyone is aware of the financial status of the project at all times. Should cost issues arise, RJM will collaborate with the design team to provide several options to solve the challenge, mitigating cost impact. RJM will keep the team aware of the status of the project contingency throughout construction. As project milestones are met, options for utilizing contingency dollars for owner-desired scope enhancements are given. Through careful planning and tight project cost control, RJM will assist the City of Elk River in completing the project on budget. Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach As a CHASE partner, RJM has been publically recognized for enforcing the importance of providing a safe, healthful work environment. We seek a working relationship that creates mutual trust and respect among all parties, including project owners and construction workers. 25 Elk River Ice Arena and Lion John Weicht Park Facilities Part III: Key Qualifications & Approach RJM is willing and capable to serve as CMa or CMar and will not bid or act as a constructor for any of the work. RJM believes in acting solely as the City of Elk River’s advocate and working as a constructor is, in our opinion, a conflict of interest. Quality Control During the design process RJM will collaborate with 292 Design Group in the quality review process. Unique among other CMs, we are builders and we utilize this expertise to assist the designers in coordinating document details. During bid solicitation, our team will ensure qualified contractors are hired for critical areas of work. RJM has developed specifications that outline qualifications to accompany select bids. This extra step gives assurance that a balance of value and quality will be achieved. During construction RJM will conduct pre-installation meetings with all stakeholders to ensure proper sequencing and focus on details. RJM will manage the development of mockups to help the team make informed material decisions, but more importantly, hold the installation to an agreed quality standard. CMa versus CMar Project Delivery The investment in the renovation of the existing Elk River Ice Arena and Lion John Weicht Park facilities can represent a challenge for the City of Elk River. Leaders seek to spend tax dollars as wisely as possible, while ensuring that new facilities are well constructed for the long term. In general, the Construction Management delivery method is a smart choice to complete your project. This process gives the City of Elk River control over the entire process from start to finish, and provides an on-time project with improved quality and reduced change orders. For the Elk River Ice Arena and Lion John Weicht Park Facilities project, RJM will work with the City to arrive at the best delivery model for this project. Our team is experienced and open to executing either process. Construction Manager Advisor In the Construction Management Advisor (CMa) delivery, a contracting partner is selected based on their qualifications and experience with the type of project being constructed. The construction manager provides a host of pre-construction services including phasing planning, developing the pre-construction schedule and budgeting throughout the entire design process. The construction manager essentially serves as an extension of the city staff, meeting with various user groups and carefully reviewing the Architect’s plans for completeness and constructability. Because the construction manager is providing budgeting services during the entire design process, they can identify when the design is exceeding the budget and make recommendations to bring it back into alignment. In addition, they can foresee items not clearly noted in the plans and make provisions for this work in the bid packages, eliminating opportunity for change orders. Although the CMa delivery method has many benefits, there are drawbacks. In this delivery, the City enters into a contract with each individual subcontractor on the project. This presents risk to the City as they are contractually responsible for subcontractor failure. 26 The number of contacts subsequently increases the amount of administration for City staff. With each contract comes monthly pay applications for each contractor, as well as processing documentation for any design changes. In addition, because the CMa does not hold any of the contracts or a Guaranteed Maximum Price, there can be the perception of lack of ownership by the CMa regarding schedule and budget. Construction Manager at Risk To address the drawbacks of the agency construction management process, many cities have elected to utilize the Construction Manager at Risk (CMar) delivery method. This process provides the advantages of the CMa process while allowing the City to execute one contract, with the CMar. With this delivery method, the CMar holds a contingency for unforeseen conditions on the project, and the city holds a contingency for scope changes. This is different from the CMa process, where the city holds the entire project contingency. This is the only perceived disadvantage of the CMar process. In our experience, cities that have utilized the CMar delivery model continue to use it on subsequent projects. To serve as the CMar on the Elk River Ice Arena and Lion John Weicht Park Facilities project, the primary milestone requirements would be as follows: Construction Manager Advisor (CMa)Construction Manager at Risk (CMar) RJM advertises and solicits public bids on behalf of the City RJM advertises and solicits public bids on behalf of the City Sealed bids are received at the City and are read publicly Sealed bids are received at the City and are read publicly RJM evaluates and qualifies all bids received RJM evaluates and qualifies all bids received RJM provides recommendation to City Council for award of qualified low bid- der for each bid category RJM provides recommendation to City Council for award of qualified low bidder for each bid category After Council award is made, RJM drafts contracts between the City and each awarded contractor After Council award is made, the City approves a motion to reassign all con- tracts to RJM Construction City holds each contract directly, and pays each contractor individually throughout the course of the project City holds only one contract with RJM directly City holds contractual risk of failure of individual contractors to perform, although a performance and payment bond is provided by each contractor to the City RJM holds contractual risk of failure of individual contractors to perform, although a dual oblige-performance and payment bond is provided by each contractor to the City and RJM Construction Thank you for all your hard work. The pressure, the coordination of priorities, the detail to get it right and the risk if you get it wrong. There would be no project without you. Doug Holmberg Treasure Island Center “ “ Part III: Key Qualifications & Approach Elk River Ice Arena and Lion John Weicht Park Facilities 27 Part IV: Project Examples, Supplemental Information Elk River Ice Arena and Lion John Weicht Park Facilities 28 Part IV: Project Examples, Supplemental Information Elk River Ice Arena and Lion John Weicht Park Facilities Value-Added Qualities As outlined on the previous pages, we believe the following attributes will allow us to serve the needs of the City of Elk River in ways that go above and beyond your expectations: • Previous working knowledge of this opportunity • Successful track record working on other projects for the City of Elk River • Established relationship with 292 Design Group • Ice arena experts • Comprehensive pre-construction services • Final estimate at 95% completion of design • Strong partnership and communication Additionally, we employ technology and tools for maximum efficiency throughout all project phases, including: On-Screen Takeoff On-Screen Takeoff quantifies lengths, areas, volumes and counts. It calculates measurements needed for estimates. On-Screen automatically saves calculations for incoming addendum before bid day, change orders and revised specs, enabling the team to be efficient and responsive. Sage Estimating Using a master historic cost database, the estimating team can effectively put together a conceptual project cost estimate. Then they are able to incorporate bids from subcontractors and analyze the information. Pre-built assemblies and models backed by industry standard pricing are also accessible within Sage. Viewpoint CS Viewpoint CS is a fully integrated construction management software system that is utilized by RJM. This software allows team to track all correspondence on our project in one central database, from meeting minutes to purchase orders to final billings. A wide variety of reports can be generated by Viewpoint during all phases of the project, providing the project team with the information needed to keep the project on track. Citrix ShareFile ShareFile is a cloud based solution where RJM can share documents of all sizes with owners, architects and trades. A password protected site would be tailored to your project, which the entire project team can access at any time. Items such as plans, meeting minutes and progress photos can be stored here. AutoDesk Revit With Revit, RJM’s BIM Specialist, Jake Fisher, has the capability to develop three dimensional models on projects to simulate the real world building process. Through these models, we collaborate with the entire project team, providing value in systems analysis and constructability reviews, enabling the team to make more informed decisions regarding the design, systems, efficiency and quality of a project. 29 Part IV: Project Examples, Supplemental Information Elk River Ice Arena and Lion John Weicht Park Facilities Navisworks Using Navisworks, Jake can implement solutions for clash detection and scheduled time lapse videos. Working closely with project partners, he can link architect, engineer and contractor-created documents to run simulations to view potential clashes. The team is able to meet and discuss issues months in advance before issues have been identified in the field. The Navisworks time lapse feature visually shows what has been finished, work underway and a look at what’s ahead on the job site. 360 Degree Camera RJM has a unique camera that can capture a 360 degree view of a job site. The image is stitched together and uploaded to a secure website. There, viewers can rotate through the image and get a complete view of progress or other pertinent details needed. The camera makes a fun marketing opportunity as well, sharing project progress with a broader audience. 30 Project Examples For over a decade RJM has worked with a variety of municipalities to deliver successful community projects such as ice arenas and other types of sports facilities including ball fields. Working closely in alignment with City leaders, architects, and contractors, RJM’s dedicated teams thrive on making our clients’ dreams become reality. On the following pages we show our wide range of experience that makes us the best fit for the Elk River ice Arena and Lion John Weicht Park Facilities project. Part IV: Project Examples, Supplemental Information Elk River Ice Arena and Lion John Weicht Park Facilities 31 VALUE $16,695,000 PROJECT ASSIGNMENT CMar ARCHITECT U+B Architecture & Design RJM recently completed this new community park for the City of Maple Grove, located adjacent to the Town Green and Community Center. The park includes an open lawn for outdoor events, a basketball and pickle ball sport court, outdoor splash pad, playground area and refrigerated ice skating loop. Lighted walking paths were incorporated, extending to the north side of the 20-acre site. In addition to the outdoor spaces, a 15,000 sq.-ft. warming house and event center was built. This center includes meeting space, concessions, rental offices, toilet rooms and a catering kitchen. Two new parking lots were also added to accommodate visitors. City of Maple Grove Central Park Maple Grove, MN Part IV: Project Examples, Supplemental Information PROJECT SIMILARITIES P Refrigerated ice P Pavilion building P Sports fields P Phased construction P Shared parking Elk River Ice Arena and Lion John Weicht Park Facilities 32 VALUE $10,570,000 PROJECT ASSIGNMENT CMa ARCHITECT Perkins + Will The City of Coon Rapids Ice Center facility consists of a full size sheet of ice, locker rooms, concession stand and a second floor mezzanine. Unique to this project is the second refrigerated outdoor rink including dasher boards, lighting and other amenities. The installed ice plan has capacity for a future outdoor skating loop/trail. City of Coon Rapids Ice Center Coon Rapids, MN Part IV: Project Examples, Supplemental Information Elk River Ice Arena and Lion John Weicht Park Facilities PROJECT SIMILARITIES P Two-story facility P Lobby amenity space P Multiple stakeholders P Two-sheet facility and planned infrastructure for a third 33 Elk River Ice Arena and Lion John Weicht Park Facilities Part IV: Project Examples, Supplemental Information VALUE $30,410,000 PROJECT ASSIGNMENT CMar ARCHITECT 292 Design Group RJM Construction was selected by the City of Shakopee to oversee construction of a new two-sheet ice arena. The project is an extension to the Shakopee Community Center and includes a remodel of the existing recreational facility. The project was completed in multiple phases, beginning with construction of the ice arena. Renovations to the existing facility include changing the current ice arena to an aquatic center, enhancing the fitness center and studios and adding an indoor play area, senior lounge and large community room. As construction manager, RJM assisted the City with complicated scheduling and completed the ice arena component in eight months. City of Shakopee Ice Arena and Community Center Shakopee, MN PROJECT SIMILARITIES P Two-sheet facility P Phased construction P 292 Design Group P Stevens Engineers P Proposed team P Relocated fields P Shared parking w/community center P Rink remained operational 34 Elk River Ice Arena and Lion John Weicht Park Facilities Part IV: Project Examples, Supplemental Information VALUE $7,200,000 PROJECT ASSIGNMENT CMa ARCHITECT RSP Architects Stevens Engineers RJM Construction was hired by the City of St. Louis Park to oversee construction of a multi-use outdoor recreational facility on the campus of The Rec Center. The project includes an NHL-sized refrigerated outdoor ice rink that can be converted into a covered turfed field each spring. This project was in coordination with the full replacement of the existing rec centers’ ice system upgrade and relocation to refrigeration room. The roof structure was built with glue laminated beams, tensile fabric and steel cabling support. The spectator area includes bleachers and an outdoor plaza with a fire pit. The project also includes team locker rooms and a covered walkway which will lead from the main sidewalk through the plaza area and into The Rec Center. City of St. Louis Park ROC (Recreation Outdoor Center) St. Louis Park, MN PROJECT SIMILARITIES P Two-sheet facility P Phased construction P Stevens Engineers P Coordinated ice plant replacement P New refrigeration room P Rinks remained operational 35 Elk River Ice Arena and Lion John Weicht Park Facilities Part IV: Project Examples, Supplemental Information VALUE $19,500,000 PROJECT ASSIGNMENT General Contractor ARCHITECT Collaborative Design Group Stevens Engineers RJM Construction is nearly complete converting the former Macy’s store in downtown St. Paul into Treasure Island Center. Plans for the 540,000-square-foot building include a mix of new office and retail tenants, topped off by an 1,100- seat hockey practice facility. The rooftop NHL-sized ice rink, named The TRIA Rink, is the most distinctive feature of the building. Crews placed a 100,000-pound crane atop the roof to hoist structural steel, mechanical equipment and other supplies. This innovative idea saved the project over $1 million and two months of schedule time. TRIA Rink St. Paul, MN PROJECT SIMILARITIES P Building addition and renovation P Phased construction P Multiple stakeholders P Shared parking 36 VALUE $14,765,000 PROJECT ASSIGNMENT CMar ARCHITECT Delano Erickson Architects The Eden Prairie Community Center renovation features a new inviting front entrance with an open solarium and a concession area. The facility contains racquetball courts, group fitness studios, new locker rooms and community meeting rooms. The project also included a third ice arena, a baseball stadium, state of the art baseball field and renovations to Birch Lake Park. City of Eden Prairie Community Center Eden Prairie, MN Part IV: Project Examples, Supplemental Information PROJECT SIMILARITIES P Sports fields P Building addition P Ice system upgrade P Shared parking with high school P Park renovations Elk River Ice Arena and Lion John Weicht Park Facilities 37 TABLE OF CONTENTS:Part V: Cost Proposal Elk River Ice Arena and Lion John Weicht Park Facilities 38 Elk River Ice Arena and Lion John Weicht Park Facilities Cost Proposal Elk River Ice Arena and Lion John Weicht Park Facilities RJM Construction CM Fee Proposal November 7, 2017 Preconstruction & Bidding Phase 3 Months Description Quantity Unit Unit Cost Total Project Principal 120 HRS 130.40$ 15,681$ Project Manager 52 HRS 98.40$ 5,117$ Estimator 104 HRS 98.40$ 10,234$ Project Scheduler 8 HRS 91.40$ 713$ MEP Coordinator 40 HRS 115.40$ 4,651$ BIM Specialist 8 HRS 91.40$ 713$ Document Quality Control Team 8 HRS 106.90$ 834$ Subtotal Preconstruction & Bidding 37,941$ Proposed Preconstruction & Bidding Fee $0 Project Reimbursable Expenses 10 Months Description Quantity Unit Unit Cost Total Project Principal 528 HRS 130.40$ In Base Fee Project Manager 880 HRS 98.40$ 86,592$ General Superintendent 88 HRS 106.90$ 9,407$ Superintendent (40 hours per week)1760 HRS 101.90$ 179,344$ Estimator 44 HRS 98.40$ 4,330$ Project Scheduler 44 HRS 91.40$ 4,022$ MEP Coordinator 44 HRS 115.40$ 5,078$ BIM Specialist 44 HRS 91.40$ 4,022$ Safety Director 44 HRS 106.90$ 4,704$ Quality Control Director 44 HRS 106.90$ 4,704$ Project Assistant 352 HRS 49.40$ 17,389$ Trucking/Deliveries 88 HRS 73.90$ 6,503$ Subtotal Reimbursable Expenses 326,093$ General Conditions Costs 10 Months Description Quantity Unit Unit Cost Total Electronic Documentation 44 WK 75.00$ 3,300$ Cell Phone 44 WK 15.00$ 660$ Blue Prints 10 MO 350.00$ 3,557$ Postage & Delivery 10 MO 75.00$ 762$ Temporary Toilets 10 MO 300.00$ 3,048$ Office Equipment 10 MO 150.00$ 1,524$ Truck 1980 HRS 4.00$ 7,920$ Fuel 39 WK 85.00$ 3,315$ Site Trailer 10 MO 450.00$ 4,573$ Small Tools 44 WK 250.00$ 11,000$ Subtotal General Conditions 39,659$ Construction Manager Fee *Based on $20,000,000 Construction Manager Advisor 1 LS 1.95%390,000$ OR Construction Manager At Risk 1 LS 1.85%370,000$ *RJM would like to offer our full Preconstruction and Bidding Services for zero cost as our commitment to the City of Elk River. **The Project Reimbursables, General Conditions and Fees outlined above are an estimate of anticipated services. We believe they are complete and competitive. However, we welcome the opportunity to customize to further align with your needs. 39 Elk River Ice Arena and Lion John Weicht Park Facilities Cost Proposal Guaranteed Maximum Price RJM’s process to arrive at a GMP whether the City chooses CMa or CMar is the same process as outlined in Part III of our response. The only difference is that we discount our fee slightly for the CMar delivery method. We can offer this discount based on the reduced administration process that we have established in delivering CMar projects, resulting from direct contracts with the subcontractors. RJM will not act as a constructor in either delivery model. With RJM, you have a true advocate that will always act in the City of Elk River’s best interests. 40 EXHIBITS 1) Phasing Plan Example - Strategy 1 2) Construction Schedule Elk River Ice Arena and Lion John Weicht Park Facilities 41 Date: 11/6/2017ELK RIVER ICE ARENALine Name Duration Start Finish20182019FebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchJanuary1522295121926512192629162330714212841118252916233061320273101724181522295121926310172431714212841118254111825126128130132134136138140142144146148150152154156158160162164166168170172174176178180182184186123456789101112131415161718192021222324252627282930313233PreconstructionBid Pack 1 (Arena Precast)BiddingBid OpeningReview Bids with TeamsPrecast ProcurementBid Pack 2 (Arena )BiddingBid OpeningReview Bids with TeamsBid Pack 3 (Park and Field)BiddingBid OpeningReview Bids with TeamsNEW ICE ARENAINFRASTRUCTUREMOBILIZATIONSIGNAGE/TEMP FENCESDEMO BARNEARTHWORKSITE UTILITIESFOOTINGS/FOUNDATIONSBEARING WALLSREADY FOR PRECASTPRECASTWATERPROOFING STRUCTURAL STEELROOFINGEXTERIOR DOORSEXTERIOR STOREFRONTEXTERIOR WINDOWSRINKSMEP UNDERGROUND97d97d23d4d70d25d20d5d25d20d5d229d127d4d1d30d10d10d20d15d25d5d10d19d5d15d5d121d5d01/15/1801/15/1801/15/1802/15/1802/15/1802/21/1802/02/1802/02/1803/01/1803/02/1803/19/1803/19/1804/13/1804/16/1803/08/1803/08/1803/08/1803/08/1803/14/1804/25/1804/25/1805/02/1805/10/1805/31/1806/01/1806/29/1807/09/1807/23/1808/08/1808/08/1808/29/1807/23/1807/23/1805/30/1805/30/1802/14/1802/15/1802/20/1805/30/1803/08/1803/01/1803/01/1803/08/1804/20/1804/13/1804/13/1804/20/1802/01/1909/05/1803/13/1803/08/1804/24/1805/08/1805/08/1805/30/1805/31/1805/31/1807/06/1807/06/1807/20/1808/16/1808/14/1808/28/1809/05/1801/16/1907/27/18PreconstructionBid Pack 1 (Arena Precast)BiddingBid OpeningReview Bids with TeamsPrecast ProcurementBid Pack 2 (Arena )BiddingBid OpeningReview Bids with TeamsBid Pack 3 (Park and Field)BiddingBid OpeningReview Bids with TeamsNEW ICE ARENAINFRASTRUCTUREMOBILIZATIONSIGNAGE/TEMP FENCESDEMO BARNEARTHWORKSITE UTILITIESFOOTINGS/FOUNDATIONSBEARING WALLSREADY FOR PRECASTPRECASTWATERPROOFING STRUCTURAL STEELROOFINGEXTERIOR DOORSEXTERIOR STOREFRONTEXTERIOR WINDOWSRINKSMEP UNDERGROUNDPreconstructionBid Pack 1 (Arena Precast)BiddingBid OpeningReview Bids with TeamsPrecast ProcurementBid Pack 2 (Arena )BiddingBid OpeningReview Bids with TeamsBid Pack 3 (Park and Field)BiddingBid OpeningReview Bids with TeamsNEW ICE ARENAINFRASTRUCTUREMOBILIZATIONSIGNAGE/TEMP FENCESDEMO BARNEARTHWORKSITE UTILITIESFOOTINGS/FOUNDATIONSBEARING WALLSREADY FOR PRECASTPRECASTWATERPROOFING STRUCTURAL STEELROOFINGEXTERIOR DOORSEXTERIOR STOREFRONTEXTERIOR WINDOWSRINKSMEP UNDERGROUND1d Date: 11/6/2017ELK RIVER ICE ARENALine Name Duration Start Finish20182019FebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchJanuary1522295121926512192629162330714212841118252916233061320273101724181522295121926310172431714212841118254111825126128130132134136138140142144146148150152154156158160162164166168170172174176178180182184186343536373839404142434445464748495051525354555657585960616263646566SLAB ON GRADE/RAMPSPIPING/INSULATION/SLAB POURCONCRETE CURE TIME READY FOR REFRIGERATION EQUIPMENTMEP REFRIGERATION ROOMPAINTMEP FINISHES CHECK/TEST/STARTUPREADY TO MAKE ICEICE ARENA-MECHANICAL/CONCOURSE-LOWERLEVELBLOCK WALLSMEP UNDERGROUNDSLAB ON GRADESLAB ON GRADE/RAMPSBLOCK WALLS-THICKENED SLABMEP ROUGH PAINTCERAMIC TILEDOORS/HARDWARECEILING GRIDMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA-LOBBY LOWER LEVELBLOCK WALLSMEP UNDERGROUNDSLAB ON GRADE/RAMPSMEP ROUGH BLOCK WALLS-THICKENED SLABPAINTDOORS/HARDWARECEILING GRID7d20d20d60d10d15d20d85d15d15d5d10d20d14d15d15d10d3d20d5d2d10d84d10d15d10d15d5d15d5d3d07/30/1808/08/1809/06/1810/02/1810/02/1810/04/1810/18/1812/14/1801/16/1907/23/1807/23/1808/13/1808/21/1808/28/1808/28/1809/04/1809/12/1809/24/1810/03/1810/03/1810/05/1811/02/1811/02/1811/06/1808/13/1808/13/1808/27/1809/11/1809/25/1809/25/1810/09/1810/30/1810/30/1808/07/1809/05/1810/03/1810/02/1812/28/1810/17/1811/07/1801/15/1901/16/1911/19/1808/10/1808/31/1808/27/1809/11/1809/25/1809/21/1810/02/1810/12/1810/16/1810/05/1811/01/1811/08/1811/05/1811/19/1812/11/1808/24/1809/17/1809/24/1810/15/1810/01/1810/29/1811/05/1811/01/18SLAB ON GRADE/RAMPSPIPING/INSULATION/SLAB POURCONCRETE CURE TIME READY FOR REFRIGERATION EQUIPMENTMEP REFRIGERATION ROOMPAINTMEP FINISHES CHECK/TEST/STARTUPREADY TO MAKE ICEICE ARENA-MECHANICAL/CONCOURSE-LOWER LEVELBLOCK WALLSMEP UNDERGROUNDSLAB ON GRADESLAB ON GRADE/RAMPSBLOCK WALLS-THICKENED SLABMEP ROUGH PAINTCERAMIC TILEDOORS/HARDWARECEILING GRIDMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA-LOBBY LOWER LEVELBLOCK WALLSMEP UNDERGROUNDSLAB ON GRADE/RAMPSMEP ROUGH BLOCK WALLS-THICKENED SLABPAINTDOORS/HARDWARECEILING GRIDSLAB ON GRADE/RAMPSPIPING/INSULATION/SLAB POURCONCRETE CURE TIME READY FOR REFRIGERATION EQUIPMENTMEP REFRIGERATION ROOMPAINTMEP FINISHES CHECK/TEST/STARTUPREADY TO MAKE ICEICE ARENA-MECHANICAL/CONCOURSE-LOWER LEVELBLOCK WALLSMEP UNDERGROUNDSLAB ON GRADESLAB ON GRADE/RAMPSBLOCK WALLS-THICKENED SLABMEP ROUGH PAINTCERAMIC TILEDOORS/HARDWARECEILING GRIDMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA-LOBBY LOWER LEVELBLOCK WALLSMEP UNDERGROUNDSLAB ON GRADE/RAMPSMEP ROUGH BLOCK WALLS-THICKENED SLABPAINTDOORS/HARDWARECEILING GRID4d Date: 11/6/2017ELK RIVER ICE ARENALine Name Duration Start Finish20182019FebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchJanuary152229512192651219262916233071421284111825291623306132027310172418152229512192631017243171421284111825411182512612813013213413613814014214414614815015215415615816016216416616817017217417617818018218418667686970717273747576777879808182838485868788899091929394959697CERAMIC TILEMILLWORKMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA-UPPER LEVELCONCRETE TOPPINGBLOCK WALLSMEP ROUGH PAINTDOORS/HARDWARECEILING GRIDCERAMIC TILEMILLWORKMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA PROJECT CLOSEOUTINSPECTIONSPUNCHLISTOWNER TRAININGSUBSTANTIAL COMPLETION ARENA OPENICE RINK RENOVATIONINTERIOR DEMODEMO OLD RINK/INSTALL NEW ICE RINKTI FINISHESPAVILION & FIELD CONSTRUCTION PAVILION & FIELD CONSTRUCTION15d15d15d5d2d10d69d5d10d15d10d2d3d10d5d15d5d2d10d13d13d10d10d128d20d109d50d53d53d10/30/1810/30/1811/01/1811/26/1811/26/1811/28/1808/17/1808/17/1808/24/1809/10/1810/01/1810/15/1810/15/1810/15/1810/15/1810/17/1811/07/1811/07/1811/09/1801/16/1901/16/1901/21/1901/21/1902/01/1902/01/1903/08/1803/08/1804/04/1804/05/1806/01/1806/01/1811/19/1811/19/1811/21/1811/30/1811/27/1812/11/1811/26/1808/23/1809/07/1809/28/1810/12/1810/16/1810/17/1810/26/1810/19/1811/06/1811/13/1811/08/1811/26/1802/01/1902/01/1902/01/1902/01/1902/01/1902/01/1909/06/1804/04/1809/06/1806/14/1808/15/1808/15/18CERAMIC TILEMILLWORKMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA-UPPER LEVELCONCRETE TOPPINGBLOCK WALLSMEP ROUGH PAINTDOORS/HARDWARECEILING GRIDCERAMIC TILEMILLWORKMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA PROJECT CLOSEOUTINSPECTIONSPUNCHLISTOWNER TRAININGSUBSTANTIAL COMPLETION ARENA OPENICE RINK RENOVATIONINTERIOR DEMODEMO OLD RINK/INSTALL NEW ICE RINKTI FINISHESPAVILION & FIELD CONSTRUCTION PAVILION & FIELD CONSTRUCTIONCERAMIC TILEMILLWORKMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA-UPPER LEVELCONCRETE TOPPINGBLOCK WALLSMEP ROUGH PAINTDOORS/HARDWARECEILING GRIDCERAMIC TILEMILLWORKMEP FINISHESTOILET PARTITIONS/GRAB BARSCEILING PADFLOORINGICE ARENA PROJECT CLOSEOUTINSPECTIONSPUNCHLISTOWNER TRAININGSUBSTANTIAL COMPLETION ARENA OPENICE RINK RENOVATIONINTERIOR DEMODEMO OLD RINK/INSTALL NEW ICE RINKTI FINISHESPAVILION & FIELD CONSTRUCTION PAVILION & FIELD CONSTRUCTION