3.2. SR 03-21-2005
Item # *3.2*
MEMORANDUM
TO: Mayor and City Council
FROM: Lori Johnson, Finance and Administrative Services Director
DATE: March 21, 2005
SUBJECT: Consider Change Orders
The following change orders have been requested on the city hall building project.
Contractor
Bid Package Change Order Change Order
Number Number Amount
CITY HALL
Reliance Electric
(Move transformers, add circuits, rewire)
Systems Management & Balancing
(New heating coils)
Direct Digital Controls
(GRV damper control)
Total
Previously Approved
Total Change Orders to Date
38 12 $5,780.00
39 420.00
37 6 1,547.00
7,747.00
208,822.51
$216,569.51
Action Requested
The City Council is asked to approve the change orders as noted above.