07-17-1987 CC MIN
MAIN STREET MEETING OF RESIDENTS
HELD AT HANDKE ELEMENTARY
ON JULY 17. 1987
~ Present: Pat Klaers. City Administrator. Terry Maurer. City Engineer, Estelle
Gunkel. Mayor. Councilmembers Schuldt and Tralle (7:00)
The meeting began at 6:35 p.m. with a welcome from Councilmember Schuldt
followed by some background on the project by Mayor Gunkel. Gunkel stated
that a 1985 feasibility study was done on a comprehensive Main Street project.
This study included the sewer. water. storm sewer. and street systems. Gunkel
stated that this meeting was being held so that the City could inform property
owners of the plans for the 1988 project. which is planned to go from "bridge
to bridge". and in turn hear comments and concerns from the residents.
Terry Maurer. City Engineer then took the floor to explain what elements the
project will include and the construction time frame. Mr. Maurer began by
stating that the existing trunk interceptor sewer line runs along the
Mississippi River bank and is approximately 50 years old. He stated that if
there were a breakdown. it could not be repaired which would cause serious
problems for a majority of the sewer system users in the City.
Maurer also mentioned funding of the project.
year in MSA funds for street projects and it
years worth of funds will be needed. if not more.
The City receives $300.000 a
is planned that at least two
e
The project will include Main Street. the block of Jackson Avenue from Highway
10 to Main Street and Proctor Avenue from Highway 10 to Main Street. The City
Council thought that since these streets are also in need of repair. this is a
good time to do it all at once.
Maurer
went through a hand-out explaining the proposed improvements including
water. storm sewer. street widths. concrete gutters. curbs. sidewalks
street lighting. He stated that Main Street will be wider in the
area to allow for more parking and will then taper down further
sewer.
and new
downtown
west.
Maurer informed the property owners that the main improvement will be to the
street and the central sewer system. He does not see any significant problems
with the water main but stated that some lines. hydrants and valves will be
changed. Maurer does not expect any major improvements with the storm sewer
either. The City would like to do some work with the County when they begin
on Proctor to prevent any unnecessary dips that hold excessive amounts of
water.
Maurer then went through the tenative project schedule. The feasibility study
will be available to the Council in August or September. From there. a public
hearing will be held to discuss costs and funding and the plans and
specifications will be ordered. Upon approval of the plans. Maurer is
anticipating the bidding to take place in November with the project beginning
in April or May of 1988. This is expected to be a one year project. The
assessment hearing for the project is planned to be held in the fall of
1988.
e
Resident Main Street Meeting
July 17. 1987
-------------
-------------
4It. Maurer explained the City's assessment policy and stated that the abutting
property owners will be assessed for a portion of the upgrading of the street
even though MSA monies will finance part of the street and the street will be
built to MSA standards. There will be an area wide assessment for the sewer
because they are expecting to put in an oversized system which can serve
properties currently not on the system. Maurer does not anticipate any
water assessments and stated that the storm sewer will be funded by MSA
dollars. There will only be a small assessment for the sidewalks and
gutter.
Councilmember Schuldt spoke briefly on the sanitary sewer system and stated
that now is the best time to construct a new interceptor line. If the
existing sewer line were to breakdown after the Main Street project is
completed. Main Street would have to be dug up again and property owners would
have to pay again.
One resident questioned the water main. Maurer stated that pipes in various
areas will be replaced but not the entire line. This line is adequately sized
so they will mainly be concentrating on the maintenance problems.
e
Questions were also raised regarding the age of the sewer line. when the City
will know how much work needs to be done to the water main. and the abandoning
of the sewer line. Maurer stated that the sewer line will be abandoned as a
trunk line but will still function as a lateral line. After a question being
raised about abandoning of the lateral line. Maurer stated that he could not
give a specific time until the feasibility study is completed but the City is
trying to avoid expensive temporary fixes to replace/repair the existing river
bank line.
Downtown
1.
2.
3.
parking was then discussed and Maurer gave the options:
Parallel parking on both sides of street.
Diagonal parking on one side and parallel parking on the other side.
Diagonal parking on one side and no parking on the other side.
Questions were then raised on the sanitary sewer assessment area. which is yet
undecided. and on the sidewalks.
There were accessibility questions asked concerning Handke Elementary and the
Public Library.
Councilmember Tralle stated that the larger the project is. the larger the
construction company will be. and the less time the project will take. Also.
if various projects can be tied together. the less the cost will be.
Incentive clauses and penalty clauses were questioned. There will be penalty
clauses. but incentive clauses are still questionable.
The businesses which will be affected by the Main Street project will be
inconvenienced as little as possible. The project will be broken down into
pieces and the contractor will attempt to work around the delivery schedules
of these businesses so that access is always available.
-
Residents Main Street Meeting
July 17. 1987
-------------
-------------
4It Residents raised questions regarding the shutting off of water and sewer.
Maurer stated that water may have to be shut off for a few hours at a time but
that residents will never need to know of sewer shut offs. It will be the job
of the contractor to make arrangements for continuous sewer service.
The Main Street curve (by the dam) was discussed and the down grading of the
curve was a topic. Also. downtown parking was discussed further.
One resident. also a downtown business owner. questioned when the Business
Committee meets to discuss the project. These meetings are held on Tuesday
mornings at the Sunshine Depot. Pat Klaers stated that the purpose of this
committee is to give feedback to the City regarding the project. He
indicated that residents may want to form a committee for the same
purpose.
Councilmember Tralle questioned those in attendance on their feelings about
the downtown appearance. Some items of concern were: trees in the
boulevards. underground utility lines. water pipes in homes. the
narrowing of streets. and lighting. Other discussion topics included
extending businesses West on Main Street and striping on city streets
including parking stalls and painting the word "STOP" on streets near certain
intersections.
All
take
good
utilities. such as natural gas. will be notified when the project is to
place. If these utilities would like to install service. this would be a
time to do so. but the home owners must order service.
e
The next Main Street meeting will be
September. Financial information will be
approximately 28 individuals attending
Council members.
the public hearing in August or
available at this time. There were
the meeting. excluding staff and
The meeting adjourned
j)~tc
at 7:50 p.m.
Danille Mathison
Recording Secretary
CUL
e