Athletic Field Update
Parks Maintenance Division staff completed preparation of the athletic fields in time for the Ice Breaker
Tournament. Between last fall and this short spring staff removed the benches and concrete slabs from
the old dugouts,rebuilt the infield playing surfaces at YAC and OKAC,reconstructed the pitching
mount on OKAC Field 1,conducted fence repairs,infield lip removal,removed and realigned base
anchors on all fields,installed new benches for the dugouts on YAC 5 and 6 and OKAC 1 and 2, and
conducted extensive clean-up of the grounds.
The contractors for the dugout project completed all work on Friday,May 4th,just in time for the
dugouts to be used for the Ice Breaker Tournament.
Staff completed striping of the lacrosse fields at OKAC 1 and 2 and the soccer field at YAC, over the
weekend there will be 14 lacrosse games played at OKAC and one soccer game at YAC.
The OKAC lighting project continues to move along. Installation of the new light poles is complete
and conduit has been installed for the lights and new scoreboard. Kilmer Electric will be back the week
of May 14th to complete wiring of the lights and conduct training.
The DAAC and OKAC scoreboards are all on order with installation expected at OKAC Field 4
sometime in May and the DAAC 1-4 scoreboards in mid-June.
Staff is working with ERMU and a vendor to on the installation of the light poles for the Lions John
Weicht Park basketball courts. It is expected that installation will happen sometime in May.
P011018 er