08-16-2005 ERMU MIN ELK RIVER MUNICIPAL UTILITIES
REGULAR MEETING OF THE
UTILITIES COMMISSION
August 16,2005
Members Present: Jerry Takle,President;John Dietz,Vice Chair;James Tralle,Trustee
Staff Present: Bryan Adams,General Manager; Glenn Sundeen,Line Superintendent;
Theresa Slominski,Office Manager
Others Present: Pat Klaers,City Administrator
1. Call meeting to order August 16,2005
President Jerry Takle called the August 16,2005,meeting to order at 4:00 p.m.
2. Consider Utilities Agenda
James Tralle moved to approve the August 16,2005,Utilities Agenda with three
additional items for discussion under Other Business. John Dietz seconded the motion.
Motion carried 3-0.
3. Consider Consent Agenda
John Dietz had questions regarding the financials,staff responded.
James Tralle moved to approve the Consent Agenda as follows:
July Check Register
July 12,2005,Minutes
Financials
John Dietz seconded the motion. Motion carried 3-0.
5.1 Staff Up-dates
Bryan Adams reported on the recent law changes that affect Elk River Municipal
Utilities. Minnesota law change reflects that addresses of board members are now considered
private information. The Federal Energy Bill repealed PUHCA which will allow more
mergers of electric utility companies. This could cause higher rates in the future. The
Minnesota Energy Bill has a provision allowing municipal utilities to invest in Transmission
Companies or Transco. Further study is needed to determine the direct impact on Elk River
Municipal Utilities. Discussion followed regarding energy,ethanol,and bio-diesel as alternate
fuel sources. Staff is looking into the financial implications of such projects and will be
addressing that in the future.
5th Street project is near completion other than a few inspections. A few of the water lines had
to be cleaned out and there were more non-copper service lines replaced than anticipated.
Glenn Sundeen informed the Commission of the 30 new services in the past month. Staff is
currently rebuilding the line at the plant to support the new feeder,and also getting prepared
for the Otsego project. There were a few outages which consisted of animals and lightning.
Page 2
Regular meeting of the Elk River Municipal Utilities Commission
August 16,2005
Theresa Slominski notified the Commission we are currently interviewing for
clerk/receptionist position. The IRS tax issue is being dealt with. An electronic payment
system is being looked into as an optional source for customers to pay their bill. It would cost
the utilities$25.00 per month but would save time in the posting process.
5.2 Review Target Data Center Proposal
Staff continues to work on the proposed Target Data Center facility. Bryan Adams and
Jerry Talde recently toured Target Data Center facility in Brooklyn Park. Ryan Companies,
working on behalf of the Target Data Center,is asking for a will-serve letter as part of their
operational analysis. Elk River Municipal Utilities responded to this will-serve letter with
schedule,terms,and conditions thus committing our resources to this project. The question
still remains as to the form of assurance that adequate electric revenues will be derived from
this facility. Pat Klaers asked if Target has made a commitment as to how many years they
would be here. John Dietz asked if we would require a commitment letter. Bryan Adams
replied we cannot require one as it would jeopardize our tax exempt bond status. Staff has
confirmed the expansion of Substation 14 with GRE using USG as engineers,along with
meeting Terry Maurer,City Engineer and MNDOT to find the best electric feeder route and
avoid future problems. A new rate structure for the high capacity availability is being looked
into for the Target facility.
5.3 Update Otsego Growth
On August 8,2005, Otsego City Council with Planning Commission recommendation,
approved the expansion of the Otsego substation located east of Packard Avenue off County
Road 39. The conditions of this expansion were to meet all set backs,bury the distribution
power lines running east,provide a 42"wide easement on north side of property for future
road expansion,paint or replace existing metal meter building(owned by Wright-Hennepin
Cooperative),provide a landscaping plan,and comply with no overnight storage of vehicles.
5.4 Review Antennas on Water Towers
Previous requests for installing communication antennas on utility water towers have
been denied due to safety, space,and maintenance issues. Elk River City council has
requested the utilities to reconsider due to zoning issues. At the July 25,2005, City Council
meeting,it was the concensus of the council that we enter into negotiations with the
telecommunications companies to allow antennas on our water towers instead of building
telecommunication towers. Bryan Adams recently met with Nextel and discussed the options
available. Nextel was going to look into the height and location requirements and get back to
us. Staff is still waiting for a response. The concern Elk River Municipal Utilities has is the
security issues,the manpower stress it would put on the water department,and what would
Nextel be willing to pay for rental. This will be readdressed at a later date. No action taken.
Page 3
Regular meeting of the Elk River Municipal Utilities Commission
August 16,2005
6.1 Review 2006 Budget Schedule
Staff has started the process of assembling the year 2006 budget. Commission reviewed
proposed schedule of Travel&Training along with personnel projections. The Travel&
Training budget is similar to 2005 with some minor changes. The personnel projections
reflect the addition of two people. The first person is a supervisor for metering, generation,
locating,and CAD operator. The second would be locator/CAD operator which is
necessitated due to the new rule making,requiring water and waste water utilities to locate
their facilities in the public right of way. John Dietz recommends checking with the City to
see if we could share an employee.
6.2 Review Large Electric Capital Projects
Otsego's growth,potential Target Data Center facility,and normal growth have initiated
a number of possible projects for the electric department. A list of projects and costs were
discussed along with the reasoning of why we should proceed now instead of wait. Staff is
checking into bond rates with MMUA and conventional rates through the City. This will be
revisited at the next Commission meeting.
6.3 Review Substation Transformer Purchases
Due to the continued growth in Elk River,a$600,000 project was scheduled to upgrade
two substations in 2006. The original plan was to purchase a new 15 MVA 69KV transformer
for West Substation and the existing 12 MVA 69KV substation transformer would go to the
North Substation. Staff is recommending holding off upgrading the North Substation at this
time and instead upgrade the Otsego Substation. Bids for this transformer will be received on
August 30,2005. This bid also contains an option for an additional 69KV transformer for
Station 14 to accommodate the Target project. We will know more after the Target board
meeting on September 14,2005.
Other Business
Bryan Adams reviewed the 2005 Electric Distribution Capital Projects. Staff recommends
delaying two rebuild projects worth$245,000 and accelerating the Feeder 97 construction
from Station 14 to West Business Park increasing the scope of project from$50,000 to
$250,000.
James Tralle moved to approve the change of the 2005 Electric Distribution Capital Projects.
John Dietz seconded the motion. Motion carried 3-0.
John Dietz inquired as to why the lawn at the power plant looks so bad. Glenn Sundeen
informed him that the sprinkling system was recently fixed however,he will have it checked
again as it still is not working properly.
Page 4
Regular meeting of the Elk River Municipal Utilities Commission
August 16,2005
John also was concerned about the proper identification of Elk River Municipal Utilities
employees. All employees should have an identification badge for customers if they are to do
work in or near their home. It was suggested to use a bill stuffer or put an article in the next
Connector that is in the Elk River Star News regarding what to do if a customer is suspicious
of someone saying they are a City or Utility employee needing to get into their home.
There was no other business.
The next regularly scheduled meeting of the Elk River Municipal Utilities Commission
will be Tuesday, September 13,2005.
President Jerry Talde adjourned the regular meeting of the Elk River Municipal Utilities
Commission at 5:30 p.m.
Respectfully ubmitted,
Judy Mc padd%ii,