4.3. SR 01-22-2019
Request for Action
To Item Number
Mayor and City Council 4.3
Agenda Section Meeting Date Prepared by
Consent January 22, 2019 Justin Femrite P.E., Public Works Director
Item Description Reviewed by
Pay Estimates Lori Ziemer, Finance Director
Reviewed by
Cal Portner, City Administrator
Action Requested
Approve, by motion, the pay estimates detailed below.
Background/Discussion
The following pay estimates have been reviewed and found to be accurate and in accordance with the
approved contracts.
Financial Impact
P ROJECT P AY E ST. # C ONTRACTOR A MOUNT
Lion’s Park Pond, Phase 2 1 Peterson Companies, Inc. $28,277.35
Attachments
Pay Estimates
The Elk River Vision
A welcoming community with revolutionary and spirited resourcefulness, exceptional
service, and community engagement that encourages and inspires prosperity
PE #1
Stormwater Pond Dredging, Lion's Park Pond Phase 2
Peterson Companies, Inc.
8326 Wyoming Trail
Chisago City, MN 55013
Date of Work Performed:Dec 1-31, 2018
CONTRACTCOMPLETEDUNITPE
NO.ITEMUNITQUANTITY TODATEPRICEAMOUNT
1Temporary and Permanenet Turf RestorationLS1.000.42$70,870.55$29,765.63
2Pond Excavation, SRV Level 1 (EV)CY5,800.00$15.32$
3Pond Excavation, Above Tier 2 (EV)CY5,653.00$29.25$
Total Earned29,765.63$
Retainage Less 5%(1,488.28)$
Less Previous Payment-$
Total PE 1 - Lion's Park Pond, Phase 2$28,277.35$