Loading...
8.3 PRSR 03-13-2019 Request for Action To Parks and Recreation Commission Item Number 8.3 Agenda Section Discussion Meeting Date March 13, 2019 Prepared by Michael Hecker, Parks and Recreation Director Item Description Woodland Trails Regional Park Nature Playground Reviewed by Cal Portner, City Administrator Reviewed by Action Requested Presentation and Discussion Background/Discussion The new playground location and concept design were presented to City Council March 4. Overall, the City Council felt the playground was an interesting concept and approved the Woodland Trails Regional Park (WTRP) Master Plan amendment including the nature playground, nature center and picnic shelter. Council Members suggested including alternates in the bidding process and find ways to not spend the additional costs for changes to the new location, either through a favorable bidding market, donations, or volunteers. The WTRP Master Plan will be amended to reflect the recent changes approvd by City Council. Financial Impact N/A. Attachments  City Council March 4 Meeting Attachments o Staff Report requesting City Council Action to Change WTRP Master Plan o Master Plan Location and Proposed Location o Nature Play Original Master Plan Site Location o Nature Play Latest Concept New Site Location Request for Action To Item Number Mayor and City Council 8.1 Agenda Section Meeting Date Prepared by General Business March 4, 2019 Michael Hecker, Parks and Recreation Director Item Description Reviewed by Woodland Trails Regional Park Master Plan Change Cal Portner, City Administrator Reviewed by Action Requested Discuss the proposed location change of the nature -based playground area, nature center and picnic shelter in the Woodland Trails Regional Park Master Plan. Approve, by motion, change to the Woodland Trails Regional Park Master Plan. Background/Discussion Since November of 2018, the Woodland Trails Regional Park (WTRP) Grant Committee has met several times with WSB consultants planning the nature -based play area, nature center and picnic shelter. Members of the committee strongly feel the location of the nature playground; future nature center and picnic shelter should be moved to a different location than indicated in the master plan. The committee met on January 22 and made a motion to change the preferred locations of the playground, nature center and shelter. The WTRP Master Plan was adopted by City Council and the Greater Minnesota Regional Parks and Trails Commission (GMRPTC) in July of 2016. Both the DNR Grant Coordinator and the GMRPTC Coordinator have reviewed the master plan and commented it may be amended without impacting grant funding. They both noted any cost increases due to the location change is entirely the responsibility of the city. The Parks and Recreation Commission met at a special meeting on January 23 to discuss and unanimously recommend changes to the WTRP Master Plan with the condition any additional costs due to change of location do not come out of either the Park Improvement Fund or Park Dedication Fund. WSB Consultant Candace Amberg will present to City Council the latest playground design concepts at the proposed location, including estimated costs. The major implication of the changed location is the additional costs for grading and earthwork required with the higher elevations west side of the parking lot, and additional work required by WSB. The original scope of the project in which WSB was chosen for their design work is based on the WTRP Master Plan. While the nature center facility as shown in the master plan is not part of this project, it is an anchor to the overall project. The new location will need additional trails and trail improvements for an ADA A IR accessible route from the parking lot to the building. This building would be designed and constructed in the future with grant funds available through the GRMPTC. Because of the additional work making changes to location and design, we will not meet the original timeline in project scope of an early April bidding period. The extended timeline will not affect the work tasks and related consultant fees. We still hope for a competive bidding environment later this year. Financial Impact Relocation of the nature playground to the west side of the parking lot will require additional site grading and earthwork estimated to cost between $12,000 to $15,000. The additional work required to make changes to the design is between $2,000 to $4,000, depending on the number of changes and meetings required. This is in addition to the total fee of $43,000 for WSB, which comes from the Park Improvement Fund. The nature center relocation to the west side will require an accessible trail from the parking lot and, if the nature center is built higher than the existing trail elevation on the north side of the parking lot, additional trails will be required to access the higher elevation estimated at $28,000. This location change will also require moving the parking lot lights estimated at $10,000. The preliminary estimated cost for a future nature center is $600,000. If the nature center were to include more than one level as discussed by the committee, an interior elevator would be necessary, estimated at an additional $90,000. Attachments WTRP Master Plan Site Location and Proposed Site Location WTRP Playground Concept Plan Master Plan Location WTRP Playground Concept Plan Master Plan Proposed Location Park Improvement Fund Spreadsheet N:APublic Bodies\Agenda Packets\03-04-2019\Final\x8.1 sr Woodland Trails Master Plan change.docx Wetland Restoration Ir a ? ? A L. Small Open Av Picnic Shelter__ -,' J r ' \` y r Site To Be Determined)--- i PROPOSED ;,Y• e ,,` _ --- 14 LOCATION 'r. __ ., >, .• ',,_ _ ` - 5 Kiosk/Trailhead Enhanced Wayfinding Medium Sized Nature Center With j _ [ MASTER PLAN - Moderate Level of Programming Site To Be Determined) f a l ,k Y / f' Re-configure d parking lot with ! •' ti ha - / t{` — _ - -- enhanced drainage A' \ f / ,.''! J / - Large,reaNatureBasedPlayA Never Relocated Park Storage with Screening ` ; ,{e. F Y- r J - I '-' 1- (Site To Be Determined) Enh Couase Bunced ilding ening of Golf r r`dw r l 200 - / / i 1 ti , V ' \ .. } nCf) Nature Play I Concept izmargement Elk River, Minnesota February 26, 20191 WSB Project number: 013222-000 s 0 WS% s ie Fees FUTURE NATU CENTER SEEENLARGEMENT SMALL I o TURErjFU PICNICHELTER I rr I APS; WETLAND I LARGE GROUP SHELTER I I FUTURE . TRAILS PARKING LOT i rr City of Elk River Park Improvement Fund updated 02/27/2019 Actual 2017 2018F 2019F 2020F 2021 F 2022F 2023F Notes Revenues Other Revenue Interest Income 7,724 5,000 2,000 2,000 2,000 2,000 2,000 Youth Baseball Association - Dugouts 26,540 11,540 11,540 11,540 Youth Football - Oak Knoll Lights 15,000 12,000 7,416 7,416 7,416 7,416 Lacrosse - Oak Knoll Lights 12,000 7,416 7,416 7,416 7,416 Youth Basketball - Lions Park Courts 13,400 Grants 362,000 Misc. 175 Land Lease 12,000 Transfer In -Liquor Fund 228,016 197,174 195,000 195,000 195,000 195,000 195,000 Transfer In -Excess Fund Balance 119,382 Donations 9,526 1,245 Total Revenue 391,823 267,359 585,372 223,372 223,372 211,832 197,000 Expenditures Athletic field improvements - dugouts 77,770 63,718 Athletic field improvements - scoreboards 79,687 Bailey Point - amenities 5,875 Barrington Playground Replacement 88,209 DAAC Fence Replacement Future Funds DAAC Infield Reconstruction Future Funds DAAC Irrigation 97,437 DAAC Scoreboards 25,990 Replace 4 scoreboards Deerfield Basketball Court 25,000 Deerfield Playground Replacement 81,011 purchase and installation, playground is in need of replacement Heritage Landing Trail (Country Crossing) 120,000 Hillside Park Improvements 54,974 49,572 Phase 1 and 2 mtn bike trail reconstruction Houlton restoration (FMR match) 10,000 10,000 10,000 10,000 obligated funds to restoration grant Lions Basketball Court 18,440 Replace 4 hoops, add 4 LED lights Lions Park Bitumunous Trails Referendum??? ($203,280) Lions Park Center Parking Lot Referendum ($200,000) Lions Park Master Plan 15,000 Lions Park Playground 200,000 Oak Knoll Lights/Scoreboard 120,836 Add lights to Oak Knoll 4 and scoreboard Oak Knoll Parking Lot 153,000 Orono Park Master Plan 8,490 Park Property Lines 3,275 Parks Master Plan Update 7,149 22,084 Picnic tables/benches 9,000 Rivers Edge - Plaza Improvements 24,246 Skate Park Design 11,625 Barrington (1/2), Country Crossing (Full), Lions (2 Full), Fresno (Full), Sport Court Resurfacing 50,000 Deerfield (1/2) Sport Court Resurfacing 9,000 Highlands Tennis and Basketball (1/2) Trott Brook Basketball (1), West Oaks Basketball (1/2), Riverplace Basketball (1), Ridgewood Basketball (1/2), Kliever Point (1/2), Kliever Sport Court Resurfacing 40,000 Lake (1/2), Tennis Court Replacement - Trott Brook 150,000 City of Elk River Park Improvement Fund updated 02/27/2019 Actual 2017 2018F 2019F 2020F 2021 F 2022F 2023F Notes Tennis Court Resurface - Trott Brook 12,600 Trail Repairs & Connections 134,054 17,390 Woodland Trails Signs 10,000 Woodland Trails Survey 27,365 Woodland Trails Design Services 43,000 Woodland Trails Grant Match ($125,000 Total), Wayfinding/Sign/Kiosk 50,000), GF Buckthorn Removal 2019-2020 ($50,000), Other Woodland Trails Grant Match 25,000 25,000) Woodland Trail Grant Projects 362,000 Woodland Trails Storage Garage Replacement 100,000 Misc. park maintenance 395 Total Expenditures 527,349 506,478 542,365 210,000 282,000 175,000 140,000 Revenues less Expenditures 135,526) 239,119) 43,007 13,372 58,628) 36,832 57,000 Cash Balance - Beginning 430,802 295,276 56,157 99,164 112,536 53,908 90,740 Cash Balance - Ending 295,276 56,157 M 99,164 112,536 53,908 90,740 1471740