9.4. SR 09-16-2019 EOty1� ,.,�� Request for Action
River
To Item Number
Mayor and City Council 9.4
Agenda Section Meeting Date Prepared by
Work Session September 16, 2019 Cal Portner, City Administrator
Item Description Reviewed by
Active Elk River Project Timeline
Reviewed by
Action Requested
Information update and discussion as needed.
Background/Discussion
Following the successful local option sales tax referendum, tax implementation,bond sale, and
multipurpose facility construction, an update will be provided regarding the timing of the projects.
Financial Impact
N/A
Attachments
■ Anticipated Timelines
The Elk River Vision
A wehoMing community withrevolutionary and spirited resourcefulness, exceptional POWERED By
service, and community engagement that encourages and inspires prosperity INAMIRE1
Active
Elk
y� River
FOR EVERY GENERATION
Project Timeline
PROJECT
Multipurpose Facility
Ice Arena/Banquet space Available July 2020
Senior Center Open mid-September 2020
Fieldhouse Begin work June 2020, completed Fall 2020
Lease Space Fall 2020?
Staff Operations June 2020
Lion John Weicht Park
Ball fields Available 2021
Picnic Pavilion/Restrooms Completion Summer 2020
Youth Athletic Complex
Field Lighting Purchase/installation - Fall 2019
Play Structure Purchase 2019/Installation late summer 2020
Concessions Design Spring/Summer 2020—Construction late Summer 2020
Restrooms Planning Winter 19/20—Installation late Summer 2020
Lake Orono Dredging
Services RFP Mid-September,review mid-October 2019 - Design/permitting
Drawdown Begin August 2020 - Completion Sept. 15, 2020
Dredging Begin late Dec. 2020/earl an. 2021 - Complete Feb 15, 2021
Orono Park
A&E Spring 2020
Bids Late Summer
Construction 2021 completion late 2021
Trail Improvements 2020-2023