9 PRSR 10-09-2019
PROJECT PHASE
ANTICIPATED TIMELINE
Multipurpose Facility
Ice Arena/Banquet space
Senior Center
Fieldhouse
Lease Space
Staff Operations
Available July 2020
Open mid-September 2020
Begin work June 2020, completed Fall 2020
Fall 2020?
June 2020
Lion John Weicht Park
Ball fields
Picnic Pavilion/Restrooms
Available 2021
Completion Summer 2020
Youth Athletic Complex
Field Lighting
Play Structure
Concessions
Restrooms
Purchase/installation - Fall 2019
Purchase 2019/Installation late summer 2020
Design Spring/Summer 2020 – Construction late Summer 2020
Planning Winter 19/20 – Installation late Summer 2020
Lake Orono Dredging
Services RFP
Drawdown
Dredging
Mid-September, review mid-October 2019 - Design/permitting
Begin August 2020 - Completion Sept. 15, 2020
Begin late Dec. 2020/early Jan. 2021 - Complete Feb 15, 2021
Orono Park
A&E
Bids
Construction
Spring 2020
Late Summer
2021 completion late 2021
Trail Improvements 2020-2023
Project Timeline
Item: 9