Monthly Progress Report – September 2019
Multipurpose Facility
September 2-6
▪Excavation and fill removal from the site continued as earthwork crews progressed in getting the
site up to proper grade. (1)
▪Utility crews continued to excavate and install the new water line and storm sewer piping. (2)
▪Mason crews completed blockwork for the Zamboni room and enclosed the area.
September 9-13
▪The new water line installation completed.
▪Rebar layouts for the multipurpose facility’s foundation was laid. (5)
▪The south end of the site was graded which will become the material staging zone and designated
contractor parking area.
September 16-20
▪ Foundation work continued and pouring of the footings began. (4)
September 23-27
▪Foundation work is nearing completion!
▪Masons began blockwork in the northwest corner which will be the site of new locker rooms. (3)
▪Masonry work continues for the next few weeks to complete blockwork by late October.
(1)
(3)
(2)
(4)(5)
Item: 9
Lion John Weicht Park
September 2-6
▪Earthwork crews began milling the existing parking lot.
▪Soil correction analyses continued.
September 9-13
▪New fill was brought in to perform soil corrections necessary to begin construction of the
expanded parking area and new pavilion. (1)
▪Installation of the new water line underway. (2)
September 16-20
▪Hauling operations went into full effect to remove saturated, organic soils and replace with new
sand fill to support the new parking area and pavilion. (4)
▪Water and sewer installation continued.
September 23-27
▪Parking lot inspection led to a decision to use GeoGrid ®, a soil reinforcement product placed
between the sand and asphalt milling sections to improve the sub-base of the parking area.
▪Challenging soil conditions found a backhoe in a sticky situation (it was able to get out). (5)
▪Storm sewer line installation continued.
▪Grading of the ballfields and further soil correction work continued at the pavilion site. (3)
Thank you for your continued interest in the Active Elk River, a comprehensive plan to reinvest in the city’s
recreational facilities, major parks, and most significant natural/outdoor resources. For additional information
visit ActiveElkRiver.com, and be sure to sign up for Notify Me, the city’s online alert tool if you’d like to receive
these updates right to your email inbox or cellphone.
(1)(2)(3)
(5)(4)