5.3 ERMUSR 2-11-2020UTILITIES COMMISSION MEETING
TO: FROM:
ERMU Commission Troy Adams, P.E. General Manager
MEETING DATE: AGENDA ITEM NUMBER:
February 11, 2020 5.3
SUBJECT:
Strategic Plan and 2019 Annual Business Plan Results
ACTION REQUESTED:
Discussion on effectiveness of the Strategic Plan and the Annual Business Plan as organizational
health assessment and planning tools; discussion on ongoing improvement and progress
toward organizational mission and goals.
BACKGROUND:
In August 2017, the commission adopted a comprehensive manual of governance policies
based on the Carver Model of governance. Included in those governance policies is Governance
Policy G.2c Agenda Planning. This policy notes that in the first quarter and
Management will review E
Business Plan for the preceding fiscal year This annual review was confirmed and scheduled
20 Governance Agenda, which is included in the
monthly commission meeting materials, and which is available to the public.
DISCUSSION:
The Strategic Plan consists of Governance Policies G.1c-g. These policies are summarized on the
attached mission, vision, fundamentals, values, and planning themes handout. Additionally, the
Strategic Plan includes a dashboard of initiatives, a management tool used to track project
preparation for consideration in the budget, oversee the status of currently implemented
projects, track future priorities currently on hold, and to track overall productivity and
organizational resources. The Annual Business Plan consists of the budget and the schedule of
rates.
The purpose for the Strategic Plan is to establish the long-term direction and goals for an
organization and develop the plan to get there. A good strategic planning process incorporates
assessing risks and developing contingency plans based on risk mitigation in the journey toward
the long-term direction and goals. The purpose of the Annual Business Plan is that of a tool. It is
a tool used to measure organizational performance and provide usable information to take
corrective actions to move the organization toward the long-term direction and goals
established by the strategic plan. The Strategic Plan is a long-term forward-looking tool.
The Annual Business Plan contains the budget and the schedule of rates. The budget is a
financial tool used to forecast and quantify expected business performance. This financial tool
______________________________________________________________________________
Page 1 of 9
84
contains both knownor fixed components as well as variable or unknown components. To
measure performance, ERMU uses a monthly financial report. This report is a tool used to
gauge performance, collect data needed to make corrective actions as needed to move the
organization toward the short term goals established by the budget and Annual Business Plan,
but also to move the organization toward the long term goals and direction established by the
Strategic Plan. Monthly reports provide information for what has already happened. Their value
comes from the interpretation of the data applied toward achieving the annual short-term
goals and the farther out long-term goals and vision. The Annual Business Plan is a short-term
forward-looking tool dependent upon backwards looking data analysis.
Review of the Strategic Plan
All policies, decisions, initiatives, and tasks by ERMU on behalf of our consumer owners should
be in direct line to the ERMU Mission. All planning is conducted through a process which
categorizes initiatives under commission adopted planning themes aligned with our mission,
vision, fundamentals, and values. This framework clearly defines how ERMU is expected to
operate. This process is intentionally transparent to our consumer owners.
The following include highlights, challenges, and results from the 2019 initiatives as well as
forward-looking initiatives and goals:
Theme 1: Communication Improve the effectiveness of our communications inside the
organization, with our customers, and with the community.
Bill Presentation Staff worked with National Information Solutions Cooperative (NISC),
our accounting/billing software provider, to modify the back end calculation of our bill
layout to separate ERMU and city services for better clarity on the responsible party.
The second phase is to now work with NISC to streamline the layout and appearance
with a new design that will improve readability of that information in an effort to
improve understanding. Phase 2 is a 2020 initiative already underway.
Builder/Developer Outreach Staff completed seven standardized packets of
information to assist residential and commercial customers, builders, and developers in
applying for electric and water services. These information packets are helpful to new or
existing customers requesting services because they have step-by-step instructions and
contact information for electric and water staff members. The information included in
each packet varies depending on the project, but in general they include applications,
contracts, and fee schedules. The checklists also include the contact information for
each citys building departments that ERMU operates in.
Disaster Recovery Plan Staff established a 2019 initiative to develop a utility specific
Disaster Recovery (DR) plan that would complement the existing City of Elk River
Emergency Operations Plan. While the existing city plan is focused more on emergency
restoration efforts following a disaster, the utilities DR plan will be comprehensive,
identifying all-hazards facing the utilities, utilizing best practices found within the
______________________________________________________________________________
Page 2 of 9
85
National Incident Management System (NIMS),and following Incident Command System
(ICS) structures. Included as part of this plan will be a component addressing Business
Continuity throughout the recovery effort. This work is being coordinated with the Fire
ERMU DR
plan development continues into 2020 and will be a continuously evolving document as
it is tested during annual exercises and real incidents.
Website A request for proposal was developed and a vendor selection process was
completed in 2019. The website update initiative was budgeted as a 2020 project. Staff
has been working with our vendor on the early stages of the site layout and navigation
design. The project is expected to be complete by end of 3Q2020.
Theme 2: Personnel and Governance Develop our most valuable and vulnerable assets, our
commissioners, employees, leaders, and future leaders.
Governance Manual and Annual Training There was significant progress completed
during 2019 in the continuation of this multiyear initiative. Nearly all of the old policies
were addressed with the exception of three: A.1 Service Policies, E.1 Electric
Department Rules, and W.1 Water Department Rules. These three remaining policies
will undergo similar analysis to determine which parts should remain under direct
commission authority and which should be under indirect commission control, being
delegated to management to oversee. These three polices are scheduled to be
presented to the commission in late 1Q or early 2Q.
Manager Pay Group Benchmarking The commission directed staff and the Wage &
Benefits Committee (W&BC) to implement an initiative to benchmark the manager pay
group with the assistance of a third-party. This process was completed and resulted in
market adjustments and the implementation of organizational structure changes
creating director level leadership positions.
Succession Planning Procedure The initiative to develop a succession planning and
staff addition procedure for use by the Wage & Benefits Committee (W&BC) was not
started in 2019 and had been tabled for 2020 due to leadership bandwidth.
Safety Training Workgroup, Safety Manual and Training As a result of the
organizational effectiveness survey that was conducted in 2019, one of the initiatives to
come out of that survey was to evaluate the current safety training program and
establish safety training expectations. A Safety Training Workgroup was created to
provide perspective from all departments for the purpose of improving our safety
training program. The workgroup is comprised of an employee from each department:
office, water, electric, and tech services. The workgroup also includes an operations
manager and an administrations manager. The workgroup successfully established
program goals, priorities, and identified opportunities for improvement. And with the
changeover of our Minnesota Municipal Utilities Association (MMUA) Regional Safety
Coordinator, the training expectations were communicated early on. In addition to
______________________________________________________________________________
Page 3 of 9
86
mandated trainings,the 2020 safety training scheduleincludessome newsafety
trainings thatwere a direct result of thesafety committee membersidentifying the
needs of their departments and the trainings that would benefit them. Review of the
safety manual is on hold until later in 2020.
Employee Recognition Workgroup Another action item to come out of the
organizational effectiveness survey was to implement an effective cross-organizational
recognition program. An employee workgroup was created to develop ideas and work
through the budgeting and approval processes required to implement solutions.
Similarly, the workgroup was comprised of an employee from all departments: office,
water, electric, and tech services. The workgroup also included an operations manager
and an administrations manager.This group developed and then went through the
process to receive commission approval for a new employee milestone recognition
program.
Theme 3: Strategic Thinking Create a culture of strategic thinking and ensure line of sight from
mission to vision.
Conservation Improvement Program (CIP) Redevelopment In 2019, staff has been
working with Minnesota Municipal Utilities Association (MMUA) and the Minnesota
Rural Electric Association (MREA) in a joint effort to modernize CIP. The proposed
improvements to CIP would allow for local flexibility to achieve savings goals while
providing statutory approval to incorporate beneficial and efficient electrification into
the program. These efforts stalled due to misalignment of goals between the Senates
position and the House and the Administrations position. For 2020, the focus has
shifted to the Governors Clean Energy First plan effectively putting CIP modernization
on hold. It is likely that CIP modernization will be a part of any energy policy moving
forward this session, but CIP will not be the driver in what gets done.
Load Management Programs Staff had been working with the Minnesota Municipal
Power Agency (MMPA) on a load management (LM) program that could replace the
legacy LM program ERMU had built based on the Great River Energy (GRE) LM program
and communication/control system. For two reasons, MMPA has backed away from
adding any LM programs similar to the GRE legacy programs. First, those types of LM
programs are not financially viable in the current Mid-continent Independent System
Operator (MISO) energy, demand, and transmission markets. That means under current
and foreseeable market conditions, there is not a financial incentive for the investment;
this potentially could change due to changes in regulations, grid congestion, or capacity
prices. Second, there was not uniform interest from all the MMPA member cities. The
MMPA then voted to not continue to explore LM.
Both considerations are also relevant for ERMU at the distribution system and retail
rates level, meaning ERMU would not achieve ROI with a legacy style LM program. This
initiative has been tabled for future consideration after Advanced Metering
Infrastructure (AMI) has been explored.
______________________________________________________________________________
Page 4 of 9
87
MMPA Hometown Solar Grant Staff worked with the City, Energy City Commission,
and MMPA to install a 5 kW solar photovoltaic array at City Hall. The purpose of the
Hometown Solar Grant installation is to provide our community with an educational
asset to teach people how sunlight is converted into electricity and the unique
generation characteristics of solar power. This was a great addition to the community
and another demonstration site for Minnesotas designated Energy City.
Theme 4: Technology Implement the prudent use of technology to improve efficiency and
increase customer choice, communication, and value.
ESRI GIS Mapping Over the past few years ERMU has made significant progress in
transitioning from AutoCAD (CAD) maps to an ESRI ArcGIS (GIS)geospatial database.
Most of this progress can be directly attributed to the 2016 decision to hire a full-time
GIS/Mapping Technician. While the water model was initially constructed in 2015 by an
outside vendor who collected GPS data for hydrants and valves, the electric model was
built inhouse with minimal outside help and has proven to be a substantially more time-
consuming project to update. To assist in this process, locators collect, record, and GPS
electrical equipment data utilizing iPads with ESRIs Collector app and a Trimble R1 GPS
receiver. We have been able to maintain the highest accuracy of data. This data
collection equipment has also been utilized by the lineworkers and the water
department to further enhance the accuracy of the data within the electric and water
models. With the recent purchase of ESRI Enterprise Agreement, the goal to transition
field staff entirely to GIS can now be accomplished through Portal for ArcGIS on a web-
based application in 2020. The next phase of the project will integrate the GIS models
with NISC software databases to provide additional map functionality and efficiencies as
well as make GIS data available to all ERMU employees. The future roadmap will include
transitioning from a geometric network to ArcGIS Utility Network which is the next
evolution of GIS.
Cyber & Physical Security and IT/OT Support The background: Staff has worked with
the city and a third-party consultant to evaluate cyber and physical security for ERMU
and the city. A joint committee was created. A small work group with the third-party
consultant developed the framework for a comprehensive cyber, physical, and
information security policy. Progress stopped when the refinement of those policies
exceeded staff resources. The initiative was tabled until the budgeted ERMU
Operational Technology Supervisor was hired. ERMU was unable to fill the position and
so the position was reworked and posted, but again ERMU was unsuccessful in filling the
position. The W&BC reviewed the position and the core needs. Numerous other
initiatives have this initiative as a prerequisite. Filling this position and reactivating the
cyber and physical security initiative is a high priority for 2020.
NISC Module Integration There are many modules in NISC that staff is exploring
including: Meter Data Management System (MDMS) which is required to implement
Advanced Metering Infrastructure (AMI), Outage Management Systems (OMS), Mobile
______________________________________________________________________________
Page 5 of 9
88
Workforce and AppSuite, etc.Analysis for these modules for potentialfuture
implementationis based on need, returnoninvestment, and other delivered value. NISC
conducted a technology roadmap analysis for ERMU in 2018. The result of that analysis
showed that Mobile Workforce and AppSuite was the foundation and needed to be first.
The initiative to implement Mobile Workforce and AppSuite was a 2019 budgeted
initiative which went live February 3, 2020. Staff and NISC have been working on
improving the process and other items relating to the implementation. The module at
full implementation allows for employees to work paperlessly and share and access data
from the field improving workflow and efficiency.
Advanced Metering Infrastructure (AMI) and Smart Grid Analysis Staff continues to
move forward with analysis on this multi-year initiative. The actual metering equipment
upgrade will not occur until after the construction of the new field services building. The
plan that staff developed includes; a list of three potential equipment vendors,
identified the need for an outside consultant to develop the request for proposal for the
project, estimated a project budget of $2 to $3 million, and developed an
implementation timeframe of late 2022 to early 2023.
Theme 5: Growth Assess the growth curve to make decisions regarding organizational change.
Electric Service Territory Expansion Plan Staff successfully developed and
implemented a plan to safely transfer 82 customers in Areas 7&8 per the 2015
Connexus electric service territory transfer agreement. The processes for these transfers
have become highly refined and efficient. The coordination and communication with
Connexus made these transfers safer, quicker, and more cost-effective. Staff also
successfully filed with the Minnesota Public Utilities Commission (MPUC) a request to
change the electric service territory boundaries to reflect the 2018 transfer of Areas 5&6
and the 2019 transfer of Areas 7&8. This initiative is complete.
Field Services Facility Expansion Plan & Site Preparation Staff continued to plan for the
future field services expansion. The building construction is forecasted for 2023. A sub-
initiative to this project was the construction of a tempered storage building located on
ERMU land adjacent tubstation and the City Public Works Facility. This
was budgeted for construction in 2019 and was completed in January 2020. The next
phase is site preparation work including the relocation of the power plant substation,
electrical feeders, and other underground facilities. And, the rental properties will need
to be removed. Staff is working with the architectural firm on updating the drawings for
the site work as well as bid documents for the building itself. Management will look to
reactivate the Field Service Facility Expansion Committee early in 2020. There should be
one to two commissioners appointed to this committee; appointments should occur
during the March commission meeting when the commission appoints representation
for the other ERMU committees.
Road Projects Staff has been involved in the planning stages for multiple upcoming
road projects including the MnDOT Highway 169 Redefine project, MnDot Highway 10
______________________________________________________________________________
Page 6 of 9
89
project, Sherburne CountyCountyRoad12 project, and Wright CountyCountyRoad
39 project.
Electric Construction Projects In addition to the aforementioned service territory
transfer and the Main Street decorative streetlighting project, there were many electric
construction projects completed during the year. Some of the more notable and/or
larger projects were: 143 new electric services installed, four months of tree trimming
th
completed, Monroe Estates project, Hill Side 11 project, Cooper electric switchgear
testing, Jarvis Street rebuild, Pascal and Troy Street rebuild, Nantucket project in
Otsego, the Citys multipurpose building construction, and Lions park construction.
Well #8 control building project Construction of the building is complete, we started
running the well again in November 2019.
Auburn Street Water Tower Rehabilitation This project was started in 2019, but the
contractor failed to meet contractual obligations for completion. The project was then
shut down for the winter and painting will resume in spring of 2020. The contractor is
liable for liquidated damages.
Otsego and Elk River Decorative Street Lighting Staff successfully completed the Elk
River downtown decorative streetlight initiative in 2019. The sister initiative to take over
the ownership, maintenance, and operation of the 108 streetlights and begin to replace
them with decorative streetlights, which match the Elk River downtown lights, is well
underway. The Otsego decorative streetlighting project will continue in spring of 2020.
Theme 6: Process, Measurement, and Financial Health Improve processes and measurement
to better determine and report efficiency and effectiveness of organization and to ensure
financial and organizational health.
Reliable Public Power Provider (RP3) Application The designation for this national best
practices benchmarking must be renewed every three years. The RP3 panel looks at best
practices in reliability, safety, system improvement, and workforce development. The
best practice standards evolve every time to reflect current industry best practices. The
submittal process involves pulling data and policy from all areas of the organization. The
collection and submission of information required in the application for this designation
was completed and submitted on time. The designations will be announced during the
American Public Power Lineworker Rodeo and Engineering & Operations
Conference in April.
Smart Energy Provider Designation This is the first year that APPA offered the
designation which will last through 2022. The designation recognizes public power
utilities for demonstrating a commitment to and proficiency in energy efficiency and
environmental initiatives that focus on affordable, quality, safe, and reliable electric
service. ERMU joins more that 60 other utilities nationwide in receiving this designation.
______________________________________________________________________________
Page 7 of 9
90
City of Elk River Local Option Sales Tax (LOST) The successful referendum to create a
LOST has an operational and financial impact on ERMU because of our billing system.
The LOST will apply to some, but not all sales through ERMU. To implement this, ERMU
worked with NISC to create custom software updates that were successfully
implemented October 1, 2019.
Annual Business Plan and Budget Presentation Improvements Per the direction of the
commission during the Strategic Plan and 2018 Annual Business Plan Results review in
February 2019, staff had developed and implement a 20-year capital improvement plan
to be incorporated with the budgeting process. Additionally, staff implemented
formatting and presentation improvements so that the different sections of the budget
were presented in a similar format for improved readability and so that the annual
budget formatting was more similar to the formatting of the monthly reports.
Review of the 2019 Annual Business Plan
The purpose of reviewing the 2019 Annual Business Plan is to evaluate the budget as a tool in
addition to performance. By evaluating the usefulness of the tool, staff will be better able to
provide monthly information and reports to help the commission evaluate the organization
health and direction. Understanding and exploring the areas of risk and sensitivity factors
improved the governing set policy redirecting an organization toward the short
term and long-term goals. The Annual Business Plan review should help the commission identify
areas of higher risk, evaluate options to mitigate risk, establish their comfort level with risk, and
help the commission clearly communicate expectation in handling the risk.
Overall Electric Utility performance for 2019 was positive on a year where sales were down
because of weather and the 5% rate decrease. Unaudited financials indicate that electric
margins significantly outperformed budget ($1,593,658 budget, $2,870,619 actual). While
revenue performance was 1% lower than budgeted due to weather and the 5% rate reduction,
the annual expenses were 5% lower than budget. And net to reserve was higher than budgeted
($503,296 budget, $2,970,629 actual). This was our first full year purchasing power from
Minnesota Municipal Power Association (MMPA).
Overall Water Utility performance for 2019 was positive even when considering weather.
Unaudited financials indicate that water margins outperformed budget (-$144,494 budget,
$340,866 actual). Revenue was up 9% ($2,768,491 budget, $3,019,809 actual) while annual
water expenses were down by 8% ($2,912,985 budget, $2,678,943 actual). And net to reserves
was higher than budgeted ($522,399 budget, $1,157,062 actual).
An overview of 2019 budget verses actual (unaudited) for both electric and water is provided in
the attached summary.
______________________________________________________________________________
Page 8 of 9
91
Summary
The Strategic Plan and the Annual Business Plan are long-term and short-term tools for the
commission to use in governing the organization, establishing policy to clearly communicate
goals, and helping the commission lead ERMU toward the organizational vision. These tools
should evolve with the o effectively evaluate and govern. It is important to
annually discuss these tools for their function; separate from the review of the data they
contain.
2019 initiatives were positive, and it is good to
recognize our successes.
An important component to organizational health is communication. Communication is critical
in all areas of an organization, both external an internal. This includes communication between
the commission and management, communication between management and staff, and
communication between departments. Specific to communication between the commission
and management, does the commission have what they need to govern ERMU to sustainable
success? Are these tools providing the information the commission needs to effectively
evaluate the organization? Are these tools clearly identifying the areas of highest risk, enabling
the commission to effectively monitor, evaluate, and take corrective action when needed? Are
these tools providing the information needed for the commission to effectively lead the
organization toward our mission and vision? Staff looks for commission discussion regarding
the 2019 results and for discussion regarding the effectiveness of the tools used to provide the
commission with meaningful and timely information.
ATTACHMENTS:
ERMU Mission/Vision/Fundamentals/Values/Themes
ERMU Summary Comparison 2019 Budget vs Actual (Unaudited)
______________________________________________________________________________
Page 9 of 9
92
OUROUR
MISSIONVALUES
To provide our customers with safe, reliable,
INTEGRITY
QUALITY
OUR
COMMUNICATION
VISION
SAFETY
OUR
A culture that protects our
FUNDAMENTALS
COMPETITIVE
Provide the best value for the
ERMUMN.COM | 763.441.2020 | 13069 ORONO PARKWAY | PO BOX 430 | ELK RIVER, MN 55330-0430
93
OUR
PLANNING THEMES
1 | COMMUNICATION
2 | PERSONNEL AND GOVERNANCE
3 | STRATEGIC THINKING
4 | TECHNOLOGY
5 | GROWTH
6 | PROCESS, MEASUREMENT AND FINANCIAL HEALTH
ERMUMN.COM | 763.441.2020 | 13069 ORONO PARKWAY | PO BOX 430 | ELK RIVER, MN 55330-0430