RESOLUTION 93 - 71
RESOLUTION FOR THE CITY OF ELK RIVER
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ELK RIVER
REGARDING THE ENVIRONMENTAL REVIEW PROCESS FOR THE PROPOSED
ELK PARK CENTER PROJECT; RESPONDING TO COMMENTS RECEIVED ON THE
ENVIRONMENTAL ASSESSMENT WORKSHEET; SETTING FORTH THE CITY
COUNCIL'S FINDINGS OF FACT REGARDING THE NEED FOR AN
ENVIRONMENTAL IMPACT STATEMENT; AND DECLARING THAT THE
PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT
IS NOT NECESSARY
WHEREAS, Elk River Associates and Kraus-Anderson
Construction Company (the Developers) propose to construct a
374,000 square foot shopping center (the Project) on
approximately 50 acres of land located north of the school
district property between Jackson Avenue and Highway 169 in the
City of Elk River (the City); and,
WHEREAS, pursuant to Minnesota Rules, Parts 4410.0200 to
4410.7800 (the EQB Rules) the Project requires the preparation
of a mandatory environmental assessment worksheet (EAW) under
the Minnesota Environmental Policy Act (MEPA); and,
WHEREAS, the Developers supplied data on the Project to
the City and the City, as the responsible governmental unit
(RGU) under the EQB Rules, prepared and EAW as required by the
EQB Rules; and,
WHEREAS, the EAW was mailed to the Environmental Quality
Board (EQB); notice of availability of the EAW was published on
February 15, 1993, in the EQB monitor; a press release was
given to the Elk River Star News on February 2, 1993, and
copies of the EAW were supplied to all persons and agencies on
the EQB official EAW distribution list; and,
WHEREAS, the thirty day period under the EQB Rules for
submitting comments on the EAW expired on March 17, 1993; and,
WHEREAS, comments have been received on the EAW from the
following persons and agencies; which comments are responded to
as follows:
1 .
The United States Department of the Army, Corps of
Engineers, by letter dated March 3, 1993, from Ben
Wopat, commenting that a department of the army permit
may be required because of the proximity of the
Project to a wetland basin.
In response, the Developers have confirmed, by letter
dated April 27, 1993, from their consultant, John
e
e
e
Bogart of John Oliver & Associates, that an
application will be submitted at the appropriate time
for a Department of the Army permit.
2.
The Minnesota Historical Society, by letter dated
March 5, 1993, from Britta L. Bloomberg, commenting
that there are no properties in the Project area that
are listed on the National Register of Historic Places
or included in the Minnesota Historical Society
Inventory and that there are no archaeological,
historical, or architectural resources on or in
proximity to the Project site.
3.
Citizens Who Care, by letter dated March 15, 1993,
from Rolfe E. Anderson, with the following three
comments:
a.
The Project is not consistent with the City's
zoning ordinance and comprehensive land use map.
In response, the Project site was rezoned to
Planned Unit Development and the City's
comprehensive land use map amended to designate
the Project site for Highway Business uses by the
Elk River City Council on September 23, 1991
(with respect to the northerly 17 acres), and
June 15, 1992 (with respect to the remaining 33
acres). The proper procedures were followed with
respect to these rezonings and property owners
were notified as required by state law and city
ordinance.
b.
The area will suffer gridlock due to increased
traffic, and an indirect source permit should be
completed.
In response, the City Engineer has conducted a
traffic study which concludes that traffic on
surrounding streets can be managed with certain
improvements at key intersections. The Project
will require the issuance of a conditional use
permit for a planned unit development. It is
anticipated that on one condition of the PUD
approval will be a requirement that the Project
bear the cost of improvements to surrounding
streets and intersections to ensure that the
Project does not degrade levels of service at key
intersections. The most recent communication
from the Minnesota Department of Transportation,
District 3, a letter dated October 15, 1993, from
Anthony J. Kempenich, District Traffic Engineer,
indicates that traffic at the key intersection of
Highway 169 and School Street will be at an
acceptable level of service and that certain
e
improvements could be made to mlnlmize impacts
due to increased traffic. The city will work
with MnDOT to identify potential improvements and
anticipates requiring the Project to bear the
costs of improvements necessary to ensure that
the Project does not degrade service levels at
this and other key intersections. An indirect
source permit (ISP) from the Minnesota Pollution
Control Agency (PCA) will be required for the
Project. The PCA will not act on an ISP until
local governmental approvals have been obtained.
However, no building permits can or will be
issued until an indirect source permit is
obtained.
c.
Requesting that an environmental impact statement
be prepared.
For the reasons set forth in this resolution, the
City has determined that an EIS in not necessary.
4. The Minnesota Department of Natural Resources, by
letter dated March 15, 1993, from Thomas W. Balcom,
with the following comments:
e
a.
The Minnesota Natural Heritage data base
identifies a mixed oak forest within a mile of
the Project.
In response, the mixed oak forest identified in
the Natural Heritage data base is located east of
Highway 169. Since the preparation of the EAW,
the Project has been reduced in size and revised
to eliminate any development on the east side of
Highway 169. The smaller project, located
entirely west of Highway 169, will not have any
impact on the oak forest identified in the
Natural Heritage data base.
b.
The Project will have unacceptable impacts on
wetlands east of Highway 169.
e
In response, since preparation of the EAW, the
Project has been reduced in size and revised to
increase on-site ponding and reduce runoff to the
wetland identified in Mr. Balcom's letter, as
specifically addressed in a letter dated April
27, 1993, from the Developers consultant, John
Oliver & Associates, Inc., to the City. These
changes in the design of the Project, coupled
with City requirements which will be imposed in
the course of Planned Unit Development review and
approval and Corps of Engineers requirements
imposed for a wetland permit, will ensure
e
e
e
protection of the wetland area identified in Mr.
Balcom's letter.
c.
Erosion must be controlled during construction
activity.
In response, erosion control will be implemented
according to the Minnesota Pollution Control
Agency's Best Management Practices Manual.
5. Minnesota Department of Health, by letter dated March
17, 1993, from Judith A. Ball commenting on well
permits and uses.
In response, all requirements of Department of Health
will be met.
6. Minnesota Pollution Control Agency, by letter dated
March 19, 1993, from Paul Hoff, stating that the
Project does not have the potential for adverse
environmental impacts and that the PCA does not
recommend the preparation of an environmental impact
statement. Mr. Hoff goes on to comment briefly on the
issues of noise, air quality, and water quality.
In response, an indirect source permit will be
required before there is any construction activity on
the Project. Indirect source permit application
materials, and the permit itself, will thoroughly
address all noise and air quality issues. See
response to comment number 4 above regarding water
quality issues.
7. Minnesota Department of Transportation, by letter
dated April 12, 1993, from Gerald Larson, commenting
that MnDOT has no environmental comments on the
Project.
WHEREAS, all comments received on the EAW have been
responded to appropriately by the Developers and City as RGU;
and,
WHEREAS, the environmental review process mandated by the
Minnesota Environmental Policy Act and implemented through the
EQB Rules has been followed and this resolution shall be the
City's record of its compliance with the EQB Rules and decision
in this matter; and,
WHEREAS, the City, as RGU, shall order the preparation of
an EIS if the Project has the potential for significant
environmental effects; and,
WHEREAS, in deciding whether a project has the potential
for significant environmental effects, the City is to apply the
e
e
e
criteria set forth in Section 4410.1700 subpart 7 of the EQB
Rules.
NOW, THEREFORE, BASED ON THE INFORMATION GATHERED DURING
THE EAW PROCESS, THE COMMENTS RECEIVED ON THE EAW AND THE
RESPONSES THERETO FROM THE DEVELOPERS AND THE CITY, AND THE NEW
INFORMATION ON THE PROPOSED PROJECT PRESENTED BY THE DEVELOPERS
AT A PUBLIC HEARING HELD ON OCTOBER 26, 1993, THE CITY COUNCIL
OF THE CITY OF ELK RIVER MAKES THE FOLLOWING FINDINGS OF FACT
AND DECISION ON THE NEED FOR AN EIS FOR THE ELK PARK CENTER
PROJECT:
1. The only potential environmental effects of the
Project relate to noise and air quality concerns as a
result of increased traffic; and surface water quality
as a result of increased surface water runoff.
2. The Project as presently proposed is over 100,000
square feet smaller than the Project analyzed in the
EAW. This reduction in size will significantly reduce
traffic and runoff.
3. The Project will require the issuance of a conditional
use permit for a planned unit development from the Elk
River City Council. As part of the PUD approval, it
is proposed that the Project will pay for the costs of
all off-site traffic improvements necessary to ensure
that the Project does not degrade the level of service
at affected intersections.
4. The Project will require an indirect source permit
from the Minnesota Pollution Control Agency. The PCA
will ensure that there will be no adverse noise or air
quality impacts before issuing an ISP.
5. Revised plans for the Project show increased on-site
ponding for sedimentation control and that all
drainage will be filtered through two ponds before
being released to any wetlands. This will ensure that
there will be no significant adverse effects on
wetlands. The City will also require that erosion
control be implemented during construction according
to Best Management Practices.
6. The Project will require a wetlands permit from the
U.S. Army Corps of Engineers, which permitting process
will also ensure the protection of wetlands.
7. For the reasons set forth in this resolution, the
Project does not have the potential for significant
environmental effects as defined in Section 4410.1700
subpart 7 of the EQB Rules. All potential
environmental effects have been identified in the EAW
and will be addressed in the PUD approval for the
e
It
e
Project and other state and federal permits required
for the Project.
8.
Therefore, the Project does not require preparation of
an environmental impact statement.
The
DIETZ
HOLMGREN
Resolution:
Mayor Duitsman,
and Holmgren
foregoing resolution was introduced by Councilmember
and duly seconded by Councilmember
The following voted in favor of the
Councilmembers Dietz, Scheel, Farber
The following voted against: None
The following were absent: None
Whereupon the resolution is adopted.
Passed and adopted by the City Council of the City of Elk River
this 26th day of October, 1993.
Mayor
ATTEST:
k