5.5 ERMUSR 03-10-2020UTILITIES COMMISSION MEETING TO:FROM: ERMU Commission Troy Adams, P.E. –General Manager MEETING DATE: AGENDA ITEM NUMBER: March 10, 2020 5.5 SUBJECT: AuburnStreet Water Tower ReconditioningProject Update ACTION REQUESTED: None BACKGROUND: At the September 11, 2018 commission meeting, the commission awarded the contract for the Auburn Street Water Tower Reconditioning Project to Classic Protective Coatings, Inc. A contract agreement between Elk River Municipal Utilities and Classic Protective Coatings, Inc. was entered into and executed on January 16, 2019. As part of that agreement it was agreed upon that the work for the project would start on or before July 26, 2019, with a completion deadline of on or before October 11, 2019. Even after ERMU’s project manager communicated with the contractor on numerous occasions concern that their late start would put their ability to complete the project by the contractual deadline at risk, the contractor assured ERMU that they would be able to complete the project on time. The contractor was unable to finish by the October 11 deadline and meet the contractual obligations. And because of temperature requirements for paint curing, the project had to be shut down for the season. This created water system operational challenges because this tower needed to remain empty and out of operation until the project is completed in spring. This resulted in changes for winter operation, requiring ERMU to use the Johnson Street Water Tower, which is typically emptied due to freezing issues. Operating the Johnson Street Water Tower for the winter necessitated the installation of a mixer to prevent freezing, an expense incurred by ERMU because of the failure of Classic Protective Coatings to meet the Auburn Street Water Tower project deadline. The contract for the Auburn Street Water Tower project includes daily financial penalty provisions for not meeting the contractual deadline. ERMU’s project manager communicated with Classic Protective Coatings that ERMU would exercise the liquidated damages provisions in the contract. Classic Protective Coatings’ attorney has since communicated with ERMU that their client disagrees and doesn’t believe that they should be held accountable for any liquidated damages. ERMU has not released any payment to Classic Protective Coatings to date. DISCUSSION: Attorney Beck will provide a verbal update at the meeting. ______________________________________________________________________________ Page 1 of 1 78