6.1.G ERMUSR 5-12-2020UTILITIES COMMISSION MEETING
TO:FROM:
ERMU Commission Mark Fuchs – Operations Director
MEETING DATE: AGENDA ITEM NUMBER:
May 12, 2020 6.1g
SUBJECT:
Staff Update
ACTION REQUESTED:
None
DISCUSSION:
th
Staff has been working with the City of Otsego on the ParkviewAvenue and 88 Street
project, located south of the Coborn’s that is being built. The project requires the
installation of three phase underground primary infrastructurefor an apartment
buildingand future developments, as well as forstreetlights.
Elk River High School will be modifying theirparkinglotthis summer, with thesignal
system needing to be moved to the west from its current location. During the
modification, the existing water main in the parking lot will also be replaced.
Staff continues working with MNDOT on the reconstruction and improvement of
Highway 10that is slated to be completedin 2021.
Staff continues to work with Kodet Architectural Group on the new field services
building. We are looking at our current needs and considering options that would help
us meet future needs. Most importantly, the building costs need to be in line with
budget.
Staff is also working with Power Systems Engineering (PSE) on plans to install electrical
infrastructure to make room for the new field services building.