Loading...
4.5 SR 07-06-2020City of Elk* River Request for Action To Item Number Mayor and City Council 4.5 Agenda Section Meeting Date Prepared by Consent July 6, 2020 Justin Femrite, P.E., Public Works Director Item Description Reviewed by Set Public Hearing for 169 Redefine Project Cal Portner, City Administrator Reviewed by Action Requested Set, by motion, August 17, 2020, the date to hold a public hearing to review the preliminary layout for the 969 Redefine project. Background/Discussion In accordance with state statute, MnDOT has requested the consideration for granting municipal consent to the layout for the 969 Redefine project. The steps toward considering this approval are detailed in the attached June 26, 2020, letter from MnDOT's project manager. Per statute, we developed the following schedule to meet the deadline: July 6 — CC to set date for public hearing July 17 — Advertise for public hearing August 17 — Conduct Public Hearing September 8 — Council to consider approval of layout via resolution In addition to the above schedule, staff asked the MnDOT design team to consider an open house in early August to further communicate the preliminary design layout. The layout is loaded on the project website and additional informational videos are loaded there that detail the proposed improvements. Financial Impact None Attachments ■ Memo from MnDOT The Elk River Vision A welcoming community with revolutionary and spirited resourcefulness, exceptional,` 01 e service, and community engagement that encourages and inspires pi ospei l_ y INAMIRE1 NESpTg2° Minnesota Department of Transportation District 3 7694 Industrial Park Road OPTRN Baxter, MN 56425-8096 June 261h, 2020 Justin Femrite, P.E. Public Works Director/Chief Engineer City of Elk River 13065 Orono Parkway Elk River, MN 55330 RE: Request for City Approval (Municipal Consent) of the Final Layout for SP 7106-87 Dear Mr. Femrite, MnDOT is proceeding with plans to complete State Project 7106-87 TH 169 Reconstruction through the City of Elk River. In accordance with Minnesota Statute 161.164, 1 am submitting for City approval the project's Final Layout, identified as Layout No. 1B, S.P. 7106-87. The City's approval (municipal consent) is required for this project because it alters access to TH 169 through Elk River by creating four new grade separated interchanges, increases highway traffic capacity by adding auxiliary lanes to northbound and southbound TH 169, and requires acquisition of permanent rights of way to accommodate the proposed interchange footprints and associated drainage needs. Municipal consent of MnDOT projects is described in Minnesota Statutes 161.162 through 161.167 (attached). Approval or disapproval of the final layout is by resolution of the City Council. (A sample resolution is attached). However, if the City neither approves nor disapproves the final layout within 90 days of the public hearing, the layout is deemed approved (per MN Statute 161.164). The deadlines (per MN Statute 161.164) for the City's responsibilities regarding municipal consent of the attached layout are as follows, based on a submittal date of the final layout to the City of 6/26/2020: • Within 15 days of receiving the final layout, schedule a public hearing (by 7/11/2020). • Within 60 days of receiving the final layout, conduct the public hearing (by 8/25/2020). • Provide at least 30-days' notice of the public hearing. • Within 90 days of the public hearing, approve or disapprove the layout by resolution. MnDOT will attend the public hearing to present the final layout and answer questions, as required by statute. An Equal Opportunity Employer 0 0 0 0 0 a a 0 Page 2 of 3 Project Purpose The purpose of the TH 169 reconstruction project is to improve vehicle safety and mobility along the TH 169 corridor between the Mississippi River and 197th Avenue, in Elk River. The project received Corridors of Commerce funding in 2018 to convert TH 169 to a freeway section through Elk River. Pedestrian safety and mobility will also be increased with the project. Project Description The TH 169 reconstruction project stretches approximately five miles along TH 169 from the Mississippi River at the South to the intersection with 197th Avenue at the North. The proposed project will eliminate five existing signal systems along TH 169 through revisions to the TH 10/TH 101/TH 169 system interchange and by adding four new grade separated interchanges at cross streets through Elk River. TH 169 will be reconstructed as an urban highway with median barrier separation and curb & gutter along the outsides. Auxiliary lanes will also be added between several interchanges to accommodate traffic demand. Five new bridges will be constructed with the project along with new trail and walk connections throughout the corridor. Planned Project Schedule Final design work for the TH 169 project is anticipated to begin summer of 2020. Construction will begin following a summer 2022 letting and last through the 2024 construction season. A minimum of a single thru lane of traffic will be maintained along TH 169 throughout construction. A minimum of two intersection access points will be maintained to and from TH 169 in Elk River throughout construction. Temporary bypasses, weekend closures, and detour routes are anticipated to facilitate construction. City's Estimated Project Costs Some project costs are the City's responsibility, as detailed in MnDOT's cost participation policy. (See the policy and the Cost Participation and Maintenance with Local Units of Government Manual at MnDOT's this website: http://www.dot.state.mn.us/policy/financial/fmO11.html). Total project costs for S.P. 7106-87 are estimated to be approximately $160 million. Based on the staff approved layout, the City of Elk River's cost participation is estimated to be approximately $3 million. Attached is MnDOT's current estimate of the City's costs for S.P. 7106-87. Please note that the estimated costs represent a good faith cost estimate based on preliminary design work. Costs will be refined and further validated as final design progresses. An Equal Opportunity Employer 0 00 0 0a e 0 Page 3 of 3 City's Maintenance Responsibilities MnDOT will own the bridges carrying TH 169 over Main Street and 193,d Avenue as well as the bridges carrying School Street and 197th Avenue over TH 169. MnDOT will be responsible for all maintenance involving the bridge structures and decks. The City of Elk River will be responsible for non-structural maintenance activities of the proposed School Street and 197th Avenue bridges including snow and ice removal. MnDOT will maintain all proposed interchange ramps and adjacent roadway infrastructure. The City of Elk River will be responsible for all maintenance of Main Street and 193,d Avenue as well as all maintenance of School Street and 197th Avenue exterior to the bridge approach panels including all adjacent roadway infrastructure. Maintenance of proposed traffic signals and other roadway features that may arise will be discussed as final design progresses. Please feel free to contact me if you have any questions about this submittal. Sincerely, Darren Nelson Darren Nelson Digitally signed by Darren Nelson Date: 2020.06.25 14:24:49-05'00' Project Manager 7694 Industrial Park Road Baxter, MN 56425 Office: 218-828-5760 Cell: 218-838-4473 Attachments: Final Layout for SP 7106-87, dated June 2020 MN Statutes 161.162 — 161.167 Estimated Project Costs Sample City Resolution cc: Dave Nelson, P.E. — SRF PM An Equal Opportunity Employer 0 0 0 0 0 a e 0